AIRA CONDOMINIUM PROJECT

PROJECT PLAN

CONSTRUCTION OF MIX RESIDENTIAL


DEVELOPMENT AT PLOT C4-4,HULHUMALE

BY
ENSIS GROUP OF COMPANIES
Introduction

Aira Condominium is a project


comprises of mixed-use
Commercial & Residential
Project, developing by Nirutha
Pvt Ltd, Ensis group of
Companies.
Project & Surrounding Area

The neighborhood is
characterized by a diversity of
retail & commercial options with
multiple storefronts. The project
is located in fithuroanu magu,
Hulhumale. The Project area is
situated just opposite to
Hulhumale ferry terminal.
Project overview

Aira condominium project buildings


typically, with commercial use on the
ground floor and ground mezzanine
floor with generally 2-10 residential
stories above.

The specific block C4-4 comprising


the project area of 2593 sq. m, east
side vacant land and west side
existing proposed road, north side
Project overview

They are characterized by multiple stores, with a


mix of retail and commercial services on the ground
and ground mezzanine floor and residential units
above.

The site has an existing frontage of 59.6 m along


fithuroanu magu road.

The project comprises plinth area of 2350 sq. m in


the ground floor and having parking facilities in
basement and ground floor mezzanine.
Project overview

Parking Facilities:
In basement
Car park (general) =34 nos
Car park (visitors) =11 nos
Motorcycles =92 nos
In ground floor mezzanine
Motor cycle (general) = 83 nos
Motor cycle (visitors) =11 nos
Project overview

From first Floor, the residential units are to be


constructed and classified into tower A and tower
B
There are
Type
94 luxurious
Area
residential units in
Total Nos
different
A1sizes 480 sq. ft. 13 nos
B1 950 sq. ft. 15 nos
B2 1012 sq. ft. 11 nos
C1 1278 sq. ft. 30 nos
C2 1254 sq. ft. 15 nos

In addition, 10 different sizes of pent of


pent houses.
Project overview

The design architect of this project


Ten architects, Singapore and
contractor Island Line, Maldives

This project estimated to complete


by 25.11.2018
SCOPE STATEMENT
Purpose of Project:
Construction of Commercial & residential apartments.
Background:
Our group has been awarded the contract for construction of a residential
apartment by Housing Development corporation Hulhumale, Maldives.
The project will help our group to build a good repute for expansion of our
operations in construction industry.
Deliverables:
Construction of a Mix residential apartment
Linking the residential apartment with external services.

Stakeholders:
1. Project sponsors

2. End users of the output of the project

3. Administrative users (HR, Finance, Marketing, Business Development, Sales)

4. Project Team (Top Management, Project Manager, Project Team)

5. Contractors
SCHEDULE
SCHEDULE
SCHEDULE
SCHEDULE
SCHEDULE
Timeline
HUMAN RESOURCE PLAN
Aira Condominium
Mr. Mohammed Mr. Abdulla
Mr. Abdul wahid
waseem Saeed
Thoufeeq
Managing Managing
Managing Director
Director Director

Mr.Usamath
Project Head

Ms.Aishath Mr.Naahee Mr. Perumal Raja


Fazla Asst Project Asst Project
Admin/PO Manager Manager
Site
Assistant/Coordina
tor

Civil Electrical MEP HSE


QA/QC
Engineer Engineer Engineer Supervisor

Site Electrical Mechanical


engineer supervisor supervisor Nirutha pvt Ltd
Man hours of all trades
Project: Aira Condominium

Sub: Manhours Trade wise

SL.NO DESCRIPTION MANHOURS TRADE


1 Sheet pile 242.3 sheet piles
2 CONVENTIONAL FORMWORKS INSTALLATION 12638.1 Formwork team
3 REBAR WORKS 30417.5 Steel Fixer Team
4 CONCRETING WORKS 3819.6 concrete team
MASONRY WORKS
5 CHB LAYING AND BRICK WORKS 35856.9 Mason team
6 PLAIN CEMENT PLASTER FINISH ON CHB 55241.0 Mason team
7 TILE LAYING 10082.0 tile team
CEILING FINISHES
8 RUBBED CONC. AREA + GRINDING + SKIMCOAT 16991.6 general labours
9 9MM GYPSUM BOARD AREA 3308.5 gypsum technicians
FLOOR FINISHES
10 Plain cement Straight to Finish 4927.0 Mason team
DOORS AND WINDOWS
11 DOOR (INC. JAMB AND HINGES) 1808.0 carpenter&alu
12 WINDOWS 716.0 Aluminium team
FINISHING HARDWARES AND ACCESSORIES
13 TOILET FIXTURES 4727.0 plumbing
14 PAINTING WORKS 19496.0 painting
15 ALUMINUM AND GLASS WORKS 298.5 Aluminum team
MISC. METAL STEEL WORKS 11098.0
Mep services
16 electrical 12860.0 electrical
17 plumbing 4640.0 plumbing
18 HVAC 5500.0 HVAC
19 Fire fighting 1860.0 mechanical
MAINTENANCE & EXTRA WORKS
20 Kitchen counter and equipment 7700.0 finishing carpenter
21 Garbage disposal chute every floor 660.0 mechanical
22 Supply of garbage container & garbage vehicle 36.0 general labors
23 Footpath and canopy 1500.0 Mason team
24 Access control system every floor 350.0 IT & mechanical

Total man hours 246774.0


Man power of all Trades
Project: Aira Condominium

Sub: Manhours Trade wise

SL.NO DESCRIPTION MANHOURS TRADE NO OF SET EACH TRADE


1 Sheet pile 242.3 sheet piles
2 CONVENTIONAL FORMWORKS INSTALLATION 12638.1 Formwork team 2X15 SETS
3 REBAR WORKS 30417.5 Steel Fixer Team 2X15 SETS
4 CONCRETING WORKS 3819.6 concrete team 2X15 SETS
MASONRY WORKS
5 CHB LAYING AND BRICK WORKS 35856.9 Mason team 2X15 SETS
6 PLAIN CEMENT PLASTER FINISH ON CHB 55241.0 Mason team 2X15 SETS
7 TILE LAYING 10082.0 tile team 2X10 SETS
CEILING FINISHES
8 RUBBED CONC. AREA + GRINDING + SKIMCOAT 16991.6 general labours 15 SETS
9 9MM GYPSUM BOARD AREA 3308.5 gypsum technicians 10 SETS
FLOOR FINISHES
10 Plain cement Straight to Finish 4927.0 Mason team 10 SETS
DOORS AND WINDOWS
11 DOOR (INC. JAMB AND HINGES) 1808.0 carpenter&alu 15 SETS
12 WINDOWS 716.0 Aluminium team 10 SETS
FINISHING HARDWARES AND ACCESSORIES
13 TOILET FIXTURES 4727.0 plumbing 10 SETS
14 PAINTING WORKS 19496.0 painting 15 SETS
15 ALUMINUM AND GLASS WORKS 298.5 Aluminium team 10 SETS
MISC. METAL STEEL WORKS 11098.0
Mep services
16 electrical 12860.0 electrical 10 SETS
17 plumbing 4640.0 plumbing 10 SETS
18 HVAC 5500.0 HVAC 6 SETS
19 Fire fighting 1860.0 mechanical 4 SETS
MAINTENANCE & EXTRA WORKS
20 Kitchen counter and equipment 7700.0 finishing carpenter 8 SETS
21 Garbage disposal chute every floor 660.0 mechanical 3 SETS
22 Supply of garbage container & garbage vehicle 36.0 general labours
23 Footpath and canopy 1500.0 Mason team 8 SETS
24 Access control system every floor 350.0 IT&mechanical 3 SETS

Total Hours (app) 246774.0


Equipment

Project: Aira Condominium


Sub: Equipment

SL.NO DESCRIPTION NOS


1 EXCAVATOR WITH MULTI FUNCTION 2
2 TOWER CRANE 1
3 DUMP TRUCKS 2
4 CONCRETE TRANSIT TRUCKS 3
5 CONCRETE PUMP 1
6 DEWATERING PUMPS 2
7 CRANE 1
8 COMPACTORS 3
Current Status

Aira Condominium Project site officially handed over by


HDC on 20-04-2017.
Excavation & Temporary fence works is in progress