Académique Documents
Professionnel Documents
Culture Documents
PROJECT
2013
A PRESENTATION BY:
VISMAY SHAH
16014111028
Hello!
I am Vismay Shah
Welcome to Microsoft Project 2013
Microsoft Project (or MSP) is a project management
software program.
BRIEF DETAILS OF PRESENTATION
In this Presentation you will cover following topics.
DURATION is PREDECESSORS
START is you start date
Total time taken to contains main 4
of the Activity,
complete an constraints that can
It can be the Current
activity. decide that which
Date or Any date of the
This will be in activities will start
calendar.
terms of Days. together or parallel or
will finish together.
THINGS TO SET UP BEFORE USE
I. OPEN THE MS PROJEC 2013.
II. Before Start using it , you need to set certain
things on it for that Go to the file menu on
the right hand side upper corner.
III. You will see the Last tab of OPTIONS there.
Click on it
IV. A dialogue box will prompt up as shown in
Image.
PROMPT OF
GO TO LAST TAB
DIALOGUE
FILE MENU OPTIONS
BOX
GENERAL TAB
The 1st TAB you will see of General, In this particular tab You
need to set the DATE & TIME Format from any of the options
above but for the work Convenience go for the DAY DD-MM-YY.
DISPLAY TAB
In the next tab named Display ; You can see the currency options
for this Project. Go to the Currency as shown selected in image &
change it to the INR as shown in Next slide.
SCHEDULE TAB
In the Schedule Tab you can see another label named Schedule
Which denoted that Shows assignment unit as a : Percentage.
Change it to the Decimal From dropdown list.
SCHEDULE TAB
As you can see ; MS Project takes each New Task Manually
Scheduled but for the work Convenience change it to the Auto
Schedule.
SCHEDULE TAB
In MS Project , We usually work with Fix Duration and not with Fix
Units. But By default MS Project take it as Fixed Unit , so we need
to change it as Fixed Duration.
ADVANCED TAB
In MS Project , There are chances of make mistakes in entries , to
overcome that we can undo them by Ctrl+Z , but there is an option in
this TAB by which you can increase this Undo level , By default it is
20. I have changed it to 35.
2 TRY OUT A PRACTICAL EXMAPLE
Now As shown in Image Add some Activities.
But you can see that Each activity starts parallel
to each other but this is not possible in real time
practice . For ex. Tracing of the Soil can not be
started before/ parallel to Excavation so as
Shuttering can not be started before/parallel to
Bar Bending.
Now if you look at bars the only gives the duration of activity
as bar , no other information can be obtained by them.
FORMAT
MENU FORMAT BAR STYLE
You need to change it. SO in the TEXT Tab just change &
write as following
FORMAT
MENU FORMAT BAR STYLE
In the appeared dialogue box scroll through bottom & you will
find the critical name showing red bar. See the Text tab , it is
blank. So we need to repeat the procedure as we did for task.
After changing it as per slide no. 28 just click on OK.
So now you can see the critical task are also changed and
they are showing information like normal tasks.
5 HOW TO GET PROJECT SUMMARY TASK
PROJECT SUMMARY TASK
It is used to determine total summary or total duration of entire
project.
To do the same, select the whole project data from left corner
of screen & ..
DO CHECK
MARK TO
FORMAT UPPER PROJECT
MENU LEFT CORNER SUMMARY
TASK BUTTON
You will see something like show in next slide.
LETS TALK ALL ABOUT CALENDAR IN MS
6 PROJECT
HOW TO CREATE NEW CALENDAR
CHANGE
PROJECT
WORKING
MENU TIME
Then, as You can see a dialogue box , To CREATE a new calendar
of your convince , click on Create New Calendar
PROJECT PROJECT
MENU INFORMATION
EXCEPTION RECURRING AS WEEKLY,
7 MONTHLY, YEARLY
YEARLY EXCEPTION
Repeat the same procedure. Only the difference will be this time look
up value will have Yes or No option
Similarly we can show the PHASES of the project.
Repeat the procedure , the only difference that it will have lookup values
as Phase1 , Phase2 etc.
9 HOW TO USE FILTER TO THE PROJECT
As you can see there is a filter option in VIEW menu.
NOW JUST
CLICK ON
SAVE.
Filter the Project & show only such Activities that Does not Equal to (test)
VRAJ (value) in the field name RESPONSIBILITY .
As you can see that New Custom filter is
now created.
NOW JUST
CLICK ON
SAVE.
Filter the Project & show only such Activities that Equals to (test)
ISHAN (value) in the field name RESPONSIBILITY .
TWO LINE FILTER
NOW JUST
CLICK ON
SAVE.
Filter the Project & show only such Activities that Equals to (test)
VRAJ (value) in the field name RESPONSIBILITY OR show only such
Activities that Does not Equal to (test) NO (value) in the field
name BILL.
10 HOW TO USE GROUP TO THE PROJECT
In Group By option There are many in-built
groups ready to use.
Nature of
ORDER either
Ascending or
Descending
11 HOW TO ADD WBS TO THE PROJECT
PROJECT
WBS DEFINE CODE
MENU
PROJECT CODE
PROFILE, PROJECT
INITIALS LIKE AM, VS
ETC.
HOW TO CHANGE ALREADY ASSIGNED
12 RESPONSIBILTY IN CURRENT WORKING
PROJECT ( USE OF SWTICH FORMULA)
USE OF SWITCH FORMULA
GENERAL
SWITCH
FORMULA
YOU CAN SEE NOW THAT WE HAVE ADDED THE FORMULA TO OUR NEW
FLIED
BY WHAT VALUE YOU NEED TO
CHANGE THAT FUNCTION
CUSTOM TEXT
RESPONSIBILTY
AS YOU CAN SEE NOW
THAT RESPONSIBILTY
FIELD IS ADDED.
TO DO SO FOLLOW NEXT
SLIDE.
JUST CLICK ON OK.
SEE THAT NOW THE
RESPONSIBILITY HAS CHANGED
FOR ISHAN TO KUSH BUT NOT FOR
VISMAY.
13 ADDING RESOURCES TO THE PROJECT
TYPE OF RESOURCE INITIALS OF RESOURCE NAME STANDARD RATE OF
FOR EX. WORK, FOR EX. L FOR LABOUR RESOURCE IN PER DAY
MATERIAL OR COST OR PER HOUR UNITS.
HERE IN THIS CASE I HAVE ADDED JCB RESOURCE WITH ITS MAXIMUM UNITS AS 2 &
STANDARD RATE AS 700RS/DAY.
YOU CAN ADD MANY RESOURCE OF WORK TYPE AS SHOWN IN NEXT SLIDE.
RESOURCE TYPE : MATERIAL
HERE IN THIS CASE I HAVE ADDED RMC RESOURCE WITH ITS UNITS AS
M3[METERE CUBE] & STANDARD RATE AS 3200RS.
SEE HERE I HAVE ADDED JCB & LABOUR TO THE EXCAVATION ACTIVITY.
IT MAY HAPPEN THAT ANY ACTIVITY CONTAINS MORE THAN 1 UNIT OF A RESOURCE ,
SO TO INCREASE UNITS OF A PARTICULAR RESOURCES , DOUBLE CLICK ON THE
ACTIVITY.
YOU WILL HAVE
A DIALOUGE
BOX AS ABOVE.
GO TO THE
RESOURCE TAB
NOW.
GO TO THE
UNITS COLUMN
AND CHANGE
AS PER YOUR
REQUIREMENTS
NOW CLICK
ON OK.
SEE NOW REINFORCEMENT ACTIVITY HAS 2 RESOURCES WITH MORE
THAN 1 UNIT.
THE EARLIER PROCEDURE IS LITTLE DIFFUCLUT &
TEDIOUS , SO WE HAVE AN ALTERNATE OF IT. GO TO
TASK
GANTT
CHART
MORE VIEWS
YOU WILL HAVE DIALOUGE BOX LIKE THIS.
NOW SELECT TASK DETAILS FORM
BY SELECTING TASK DETAILS FORM YOU WILL HAVE A SCREEN LIKE THIS.
TASK DETAILS FORM WILL SHOW YOU ONE ACTIVITY AT TIME WITH
FOLLOWING DETAILS
1. NAME
2. DURATION
3. START
4. FINISH
5. CONSTRAINT
6. TASK TYPE
7. WBS CODE
8. % COMPLETE
& LAST BUT NOT THE LEAST YOU CAN ADD RESOURCE EASILY.
16 RESOURCE LEVLING
LET US TAKE FOLLOWING EXAMPLE IN ORDER TO UNDERSTAND RESOURCE LEVELING
ACTIVITY DURATION MASONS LABOURS
1-2 (A) 2 1 2
2-3 (B) 3 2 2
2-4 (C) 4 3 2
2-5 (D) 2 1 3
3-10 ( E) 4 2 2
4-6 (F) 2 3 2
4-7 (G) 4 3 3
5-9 (H) 4 5 3
6-8 (I) 2 1 2
7-9 (J) 5 1 3
8-9 (K) 3 0 4
9-11 (L) 2 1 1
10-11 (M) 3 1 2
11-12 (N) 2 1 2
I HAVE DRAFTED & ALLOCATED THE RESOURCES IN NEW MSP FILE.
BY THE CONVENTIONAL METHOD YOU KNOW THAT 13 & 10 IS THE MAXIMUM
UNIT FOR MASON & LABOUR RESPECTIVELY.
The value of work done = 0.25 * planning cost = 20000Rs (this is called BCWP
Budgeted cost for work performance)
Actual work done, on site = 22000Rs. (ACWP Actual cost for work progress)
Cost performance index (CPI) = BCWP / ACWP = 20000/22000 = 0.90
If CPI.
= 1 On schedule
>1 under the Budget
<1 Over the Budget
I HAVE SELECTED 28TH NOV. (3RD DAY FROM THE STARTING DATE OF THE
PROJECT.)
TO SEE THE TABLE OF EARN VALUE GO AS SHOWN IN FIGURE.
SELECT THE EARNED VALUE COST
INDICATORS TABLE
YOU WILL HAVE A SCREEN LIKE ABOVE IMAGE.
RECORD
VIEW MACROS
MACRO
HERE IN THIS CASE I AM RECORDING A MACRO FOR SHOWING CRITICAL ACTIVITY.
IN THIS CASE I AM CREATING THE SWITCH FOR THE CRITICAL & NON
CRITICAL COMMAND.
NOW TO ADD A VISUAL AID TO THE PROJECT GO TO
VISUAL
VIEW MACROS
BASIC
USERFORM
TO DO SO GO TO THE TASK MENU & ON THE VERY LEFT SIDE OF IT, YOU WILL
FIND A BLANK PART.
YES! RIGHT CLICK ON THAT BLANK PART & SELECT THE SECOND LAST OPTION.
YOU WILL HAVE
DIALOUGE BOX LIKE
THIS IN WHICH AT
BOTTOM PART YOU
CAN ADD YOUR NEW
TAB.
I HAVE ADDED
1. CUT
2. INFORMATION
3. SAVE
4. STATUS DATE
JUST CLICK ON OK
DONE!!
Thanks!
Any questions?
You can find me at
Fb.me/vismay30
Shah.vismay.30@gmail.com