UTILIZATION RATIO:
UTILIZATION RATIO:
utilization is a measure of time spent working.
The numerator includes either all or a subset of time put
on a timesheet.
The denominator is all or a subset of hours that could
have been worked
RESOURCE UTILIZATION
Resource utilization measures the time your resources spend
working on useful projects and tasks.
Resource utilization measures the allocation of a resource on a
specific set of work, including client and internal work, and tends
to ignore on-the-bench time during which the resource is
neither working on billable nor non-billable work.
BILLABLE UTILIZATION
The next level is billable utilization, which measures
the time your resources spend working on billable
projects and tasks.
The time spent on internal projects or business
development is not included, since this time is not
billed to the client.
Billable utilization is almost always less than resource
utilization, which includes hours spent on internal
projects and business development.
REALIZATION
Realization measures how much of a companys
revenue capacity was captured during a given project
or period of time.
The goal of this calculation method is to determine how
much of the time the resource spent on billable work
was actually billed back to the client.
DENOMINATOR FOR CALCULATION?
2,080 hours (40 hours per week * 52 weeks)
2,080 hours less company holidays
2,080 hours less company holidays and personal
vacations
A more arbitrary number, such as 70% of 2,080 hours.
CASE SCENARIO
A company has 10 days (80 hours) of company holidays and two
levels of vacation time.
Employees with less than 10 years of tenure earn two weeks of
vacation (80 hours) per year, while employees with 10 or more
years receive four weeks of vacation (160 hours) per year.
Consultant A has one year of tenure, while Consultant B has ten
years of tenure.
Finally, to make the math simple, assume utilized time is time
worked on billable client projects, including all travel and other
downtime.
All time spent by Consultants A and B is spent on billable client
projects.
In a given year, Consultant A works 1,920 utilized hours while
Consultant B works 1,840 utilized hours since she has two more
weeks of vacation than Consultant A.
SCENARIO 1
Baseline is 2,080 hours.