Virtual Construction

OASIS AUTOCITY
OASIS AUTOCITY

INTRODUCTION
OASIS AUTOCITY
PROJECT DESCRIPTION
CADANGAN UNTUK MEMBANGUNKAN BLOK KOMERSIAL YANG MENGANDUNGI:
FASA 1: 6 BLOK BANGUNAN KOMERSIL 7 TINGKAT BESERTA 1 ARAS SUB-BESMEN DAN 1 ARAS TEMPAT-TEMPAT LETAK KERETA BAWAH TANAH
FASA 2: BLOK BANGUNAN PEJABAT 12 TINGKAT
DI ATAS LOT PT.12 DAN PT.13 JALAN PJU 1A/7 MUKIM DAMANSARA, DAERAH PETALING, SELANGOR DARUL EHSAN
UNTUK TETUAN SIME DARBY BRUNSFIELD DAMANSARA SDN. BHD.

CLIENT : SIME DARBY BRUNSFIELD DAMANSARA SDN BHD


MAIN CONTRATOR : BRUNSFIELD CONSTRUCTION SDN BHD
BLOCK 1 : BMW / MINI COOPER
ARCHITECT : GRA ARCHITECTS SDN BHD
BLOCK 2 : FORD
STRUCTURAL ENGINEER : TYL PERUNDING SDN BHD BLOCK 3 : HYUNDAI
BBR CONSTRUCTION SYSTEM(M) SDN BHD
BLOCK 4 : JAGUAR
M&E ENGINEER : PERUNDING HASHIM AND NEH SDN BHD
BLOCK 5 : PORSCHE
CIVIL ENGINEER : PERUNDING BARAM SDN BHD
BLOCK 6 : MCLAREN
LANDSCAPE ARCHITECT : ECO DESIGN COLLABORATION SDN BHD

LAND SURVEYOR : JURUKUR RESOURCES SDN BHD

QUANTITY SURVEYOR : BASAR & HARUN SDN BHD


OASIS AUTOCITY
PROJECT INFORMATION

(1) Land Area = 8.700 acres or 35207.7 m2


(2) 6 Blocks 7 Storey with 2 Basement
(3) 2 Tower 12 Storey
(4) Car-Park = 2100 nos, Motorcycle Parking = 500 nos
(5) 42 Lift pits and 2 TNB Sub-Stations
(6) Earthwork Quantity = 2400m3
(7) Piling Works = 4072 Points (RC Piles)
OASIS AUTOCITY
SITE LOCATION

JALAN PJU 1A/5

OASIS Autocity Site Project


JALAN PJU 1A/9
OASIS AUTOCITY
PROJECT ORGANIZATION CHART

PROJECT DIRECTOR
NG TICK CHIEW

SENIOR PROJECT MANAGER


HO KAM YIN

DOCUMENT CONTROLLER - SHARIFAH MAISARA SYED ISMAIL

EXT-INFRA LANDSCAPE HSSE/QA/QA


P&M MANAGER CCC-MANAGER M&E MANAGER S/LAND SURVEYOR
ASSISTANT SITE ENGINEER MANAGER MANAGER MANAGER
(GAN THIAN TICK) (LIM KENG HENG) (DALBIR SINGH) (MICHAEL TAN)
*THURAI SARASAIDY (STEVEN LIM) (TONG WENG THUEN) (AZLINA)
*MUHAMAD FIKRI

SAFETY OFFICER
P&M ASSISTANCE QS SYUHADA SHAKIRN
MANAGER NGU SING WEI M&E ENGINEER
THONG WENG HONG *VIJI MARIAH
*MAVIRNESH
SITE SUPERVISOR *NASRUL ISMAN SAFETY SUPERVISOR
*CHOONG WEE KOK *FIRDAUS FITRI
*MOHD FADZLY *MOHD ZIKRY
OASIS AUTOCITY

SITE LOGISTICS
& TOWER CRANE
LOCATION
OASIS AUTOCITY

JALAN PJU 1A/5


OASIS Autocity Site Project

JALAN PJU 1A/9


OASIS AUTOCITY

GUARD
HOUSE

TOWER
CRANE
TOWER
CRANE TOWER
CRANE

SIDE GATE IN/OUT


PORTABLE
TOILET
GUARD
HOUSE

WORKER REST
AREA
BIN AREA
RUBBISH

FIRST AID WASH THROUGH


ROOM
SITE OFFICE
STAFF PARKING SUBCON
4 NOS OF WORKER
TOILET PARKING
OASIS AUTOCITY

TOWER
CRANE
TOWER TOWER
CRANE CRANE

60m
60m
70m
OASIS AUTOCITY

MASTER IMPLEMENTATION
PLAN
(MIP)
OASIS AUTOCITY

DATE OF COMMENCEMENT:
28th FEBRUARY 2014

DATE OF COMPLETION:
30th MAY 2016

CONTRACTUAL DURATION :
27 MONTHS
OASIS AUTOCITY
OASIS AUTOCITY
OASIS AUTOCITY
OASIS AUTOCITY
OASIS AUTOCITY
OASIS AUTOCITY
SUMMARY OF WORK
START DATE FINISH DATE DURATION

SUBSTRUCTURE 5/8/2014 27/6/2015 10.5 MONTHS

SUPERSTRUCTURE 30/5/2015 9/3/2016 10 MONTHS

ARCHITECTURE 4/6/2015 20/8/2016 10.5 MONTHS

M&E 13/9/2014 11/5/2016 20 MONTHS

FACADE 1/6/2015 18/7/2016 12.5 MONTHS

CIVIL WORKS 28/4/2016 23/8/2016 4 MONTHS

COMPLETION : 33 MONTHS
OASIS AUTOCITY

CONSTRUCTION
METHODOLOGY
OASIS AUTOCITY
1. To prepare road base for access during site mobilization, to Site Office
Cabins and to provide parking space for Site staff and storage place for
materials.

2. Piling works need to start and piling points for tower crane foundation
need to complete before the commencement of pile cap works.

3. Formwork for pile caps to use conventional formwork.

4. Column formworks to be combination of Aluminium form and timber-


plywood formwork
OASIS AUTOCITY

5. For substructure work divided by 3 subcontracors.

6. Basement 2 slab (600mm thickeness) to use conventional formwork, reuse


for lift pit wall and retaining wall.

7. Basement 1 and Ground Floor slab consist of post- tensional and


conventional formwork.

8. For superstructure work divided by 4 subcontractors.


OASIS AUTOCITY
9. Architectural works to start after the R.C. Structural works already
completed 3 floors, additional gang may require to start for superstructural to
speed up the finishing works internally and externally

10. All reinforcement bars to use cut & bend bars, BRC mesh cut to size.

11. To prepare shop drawings for typical unit walls and slab to incorporate with
the architectural finishes and M&E services. Mock up unit to provide to
confirm the final schedule of finishes and the standard of workmanship
required
OASIS AUTOCITY

12. M&E shop drawings, cordination and routing of M&E services at walls,
soffit of slab and ceiling level to prepare and to approve before
commencement of works.

13. To produce the external infra works and services coordination drawings
and sequence of works for planning purpose.
OASIS AUTOCITY

CONSTRUCTION
SEQUENCE
OASIS AUTOCITY
FORMWORK QUANTITY (BLOCK 1 & BLOCK 6)
SUMMARY OF FORMWORK PER LEVEL
BLOCK 1 (TOWER) BLOCK 6 (TOWER)
BLOCK
BEAM / COLUMN SLAB BEAM / COLUMN SLAB
LEVEL AREA AREA AREA AREA
(2 ) (2 ) (2 ) (2 )
LEVEL 1 3681.44 2853.28 2274.63 970.02

LEVEL 2 4583.05 4635.07 2629.94 1843.51

LEVEL 3 4763.78 3962.43 2628.84 1830.28

LEVEL 4 4686.38 4718.24 2650.96 1850.27

LEVEL 5 4509.86 4660.48 1915.28 2067.6

LEVEL 6 1217.02 1204.95 450.83 467.31


OASIS AUTOCITY
FORMWORK QUANTITY (BLOCK 2, BLOCK 3, BLOCK 4 & BLOCK 5)
SUMMARY OF FORMWORK PER LEVEL
BLOCK BLOCK 2 BLOCK 3 BLOCK 4
SHEAR WALL SLAB SHEAR WALL SLAB SHEAR WALL SLAB
AREA AREA AREA AREA AREA AREA
LEVEL (2 ) (2 ) (2 ) (2 ) (2 ) (2 )
LEVEL 1

LEVEL 2

LEVEL 3

LEVEL 4

LEVEL 5

LEVEL 6
OASIS AUTOCITY

VIRTUAL
CONSTRUCTION