Foreshore Alienation Process

Foreshore alienation
- If companies need to construct foreshore structures, a foreshore lease need to be
obtained from SLA
- Companies should not commence work on foreshore structures without first obtaining
a foreshore lease, and clearances from URA under Section (3) and SLA under (4) of the
Foreshores Act.

Documents Required for Foreshore Alienation:

1. Completed Form A for consultation with Technical Agencies


2. Provision or Written Permission from URA
3. MPA (Committee for Maritime Projects)s approval
4. 8 copies of key / site / proposal plans
5. 8 copies of Setting Out survey plans certified by Registered Surveyor
6. Cheque for processing fees (addressed to SLA)

S06
pre - application
Company Submit Proposal to Company to seek approval from: URA issues PP / WP
JTC for review
- Include proposal plans - URA (PP / WP, & Section (3) of
MND gives
- Completed Form A Foreshore Act) clearance
(can be sent separately prior to - MPA (committee for maritime URA assess and put
plan submission) projects) up to MND
- SLAs landowners endorsement (may require further
inputs from Clusters &
Clusters, LPD & EPD assess Companies)
proposals If proposal
falls in Category 1 projects:
-EPD & LPD to provide Category 1 LPD collates
- Proposal can be endorsed
additional inputs to Form A (if responses and
necessary) - LPD will send out Form A to send to URA
- EPD to advise on project consult technical agencies
classification
if EPD agreeable
If proposal falls
in Category 2 / 3 Clusters Company
inform - Company carry out limited resubmit
Category 2 & 3 projects:
company scope environmental study / EIA proposal
- PEU rejects the proposal to show that any adverse EPD to assess study and
environmental impact has been project classification
- EPD advise the scope of
addressed
environmental study / EIA if EPD not agreeable,
required company to do
further studies

S06
application stage
Company commence
construction

Company obtains approval from Company obtain URAs


URA & MPA approval for Section (3)
JTC accepts SLAs
of Foreshores Act
forward the offer and pay
documents to Clusters foreshore premium

LPD seek CEOs approval to


accept offer

Cluster collates and submit the


SLA issue offer
full set of documents to LPD:

-URA PP/WP
- MPA approval
- 8 copies of key / site / proposal
plans
- 8 copies of Setting Out survey SLA process the application
LPD submit
plans and obtain approval for
application to SLA
- Cheque for processing fees Section (4) of Foreshores Act

S06