Foreshore alienation
- If companies need to construct foreshore structures, a foreshore lease need to be
obtained from SLA
- Companies should not commence work on foreshore structures without first obtaining
a foreshore lease, and clearances from URA under Section (3) and SLA under (4) of the
Foreshores Act.
S06
pre - application
Company Submit Proposal to Company to seek approval from: URA issues PP / WP
JTC for review
- Include proposal plans - URA (PP / WP, & Section (3) of
MND gives
- Completed Form A Foreshore Act) clearance
(can be sent separately prior to - MPA (committee for maritime URA assess and put
plan submission) projects) up to MND
- SLAs landowners endorsement (may require further
inputs from Clusters &
Clusters, LPD & EPD assess Companies)
proposals If proposal
falls in Category 1 projects:
-EPD & LPD to provide Category 1 LPD collates
- Proposal can be endorsed
additional inputs to Form A (if responses and
necessary) - LPD will send out Form A to send to URA
- EPD to advise on project consult technical agencies
classification
if EPD agreeable
If proposal falls
in Category 2 / 3 Clusters Company
inform - Company carry out limited resubmit
Category 2 & 3 projects:
company scope environmental study / EIA proposal
- PEU rejects the proposal to show that any adverse EPD to assess study and
environmental impact has been project classification
- EPD advise the scope of
addressed
environmental study / EIA if EPD not agreeable,
required company to do
further studies
S06
application stage
Company commence
construction
-URA PP/WP
- MPA approval
- 8 copies of key / site / proposal
plans
- 8 copies of Setting Out survey SLA process the application
LPD submit
plans and obtain approval for
application to SLA
- Cheque for processing fees Section (4) of Foreshores Act
S06