SHORT TERM MINE SEQUENCE DESIGN IN PIT X AT PT.

KALIMANTAN PRIMA PERSADA SABAH VILLAGE


DISTRICTS BUNGUR REGENCY TAPIN
SOUTH KALIMANTAN PROVINCE

FINAL PROJECT PROPOSAL

FITRA DWI KUSUMA


DBD 111 0014

MINISTRY OF RESEARCH, TECHNOLOGY AND EDUCATION


UNIVERSITY OF PALANGKA RAYA
FACULTY OF ENGINEERING
MINING ENGINEERING DEPARTMENT
2016
BACKGROUND
Coal is one of Indonesia's natural resources that are useful for
energy needs and has economic value. Coal spread almost
throughout the major islands in Indonesia.
The island of Borneo is one of the islands that have coal resources
are quite large in Indonesia. One company that is engaged in coal
mining in Kalimantan is PT. Kalimantan Prima Persada. In the open
pit coal mining system begins with land clearing, stripping of top
soil , stripping of overburden, overburden removal and coal getting.
The price of Coal continue to fall down make a direct impact on the
coal industry, so the company must do in order to reduce the cost of
production efficiency such as stripping overburden and coal getting.
To keep production costs then do good planning so that the cost can
be minimized but still achieved the production target, otherwise
poor production planning will make production costs soar and
production targets are not achieved.
Purpose Practical Benefits
The purpose of this final project is to Practical benefits of writing this final
calculate the SR economically with pit project was to determine the design of
limit can be determined which will be the mine sequence at PT Kalimantan
useful in mine sequence design. Prima Persada.

Goal
Determining the pit limit in the pit X at Theoretical Benefits
PT. Kalimantan Prima Persada. Theoretical benefits of writing this
Calculating the value of SR in pt X at final project is expected to apply the
PT. Kalimantan Prima Persada. theory of designing mine sequence,
Can plan the production of daily, especially at PT. Kalimantan Prima
weekly and monthly in the pit X at PT. Persada.
Kalimantan Prima Persada.
FORMULATION AND LIMIT OF
PROBLEM
Formulation of Problem Limit of Problem
How do pit limit in the pit X Design of mine sequence in
at PT. Kalimantan Prima just one month.
Persada? The author does not discuss
How is the value of stripping penyaliran system.
ratio economical in the pit X The author does not address
at PT. Kalimantan Prima the calculation of reserves.
Persada? The author does not discuss
How do production planning the cost used in production
daily, weekly and monthly in activities.
the pit X at PT. Kalimantan
Prima Persada?
BASIC OF THEORY
according to Lee (1984), Definition of mine planning Determination
of the goals and objectives of activities to be achieved.
The preparation process systematically about the activities to be
carried out.
How to accomplish goals and objectives using resources and
capabilities available efficiently and yielding.
Discussion of the issue, the possibilities and opportunities that can
occur that may affect the achievement of objectives.
The determination of the actions to be taken to achieve the
objectives based on an analysis of interest and opportunity.

There are various kinds of planning, among others :


Long-term planning
Medium-term planning
Short-term planning
Alternative planning
BASIC OF THEORY
Stripping Ratio
Stripping Ratio is the ratio between the volume of rock mass
which was dismantled (overburden) with coal that is taken or
it could be referred to the large volume of soil overburden that
must be removed to obtain 1 ton of coal.

Pit Limit
The design of pit limit is part of the mine planning process
relating to the problems of geometry (Arif, 1998). According
to Wright (1990) pit limit is defined as the shape and size of a
mine (open) when mining ended in total.
BASIC OF THEORY
Pushback/Mine sequence
Pushback/Mine sequence are forms of mining (mineable geometric) which
shows how a pit will be mined from the initial entry point to the final form
of the pit.
The main goal of sequence is to divide the whole volume in the pit into
planning units smaller more manageable. Thus, the problem of the mine
design highly complex three-dimensional can be simplified. The time
element can begin to be considered in this design for the mining sequence
each pushback / mine sequence is an important consideration.
BASIC OF THEORY
The steps of making Pushback / mine sequence
The first is to determine the total pit design (ultimate pit limit)
First determine the purpose of sequence pit to be created, it will basically
refer to the Stripping Ratio and production tonnage targets, a trend that is
used are referring to the uniformity of the stripping ratio / target tonnage
or changes irregularly.
Establishment of design push back. The thing to watch is the width of a
minimum working level, slope and elevation levels and the width of the
road. The width of the push back is determined by the size of the
operating unit used. For a small unit push back the minimum width is
80ft while for large units (150-200 ton truck class) wide push back
between 135-150 ft.
LOCATION AND ACCOMPLISHED REGION
Location mining of PT. Kalimantan Prima Persada
administratively located in the District of Bungur, Tapin
District, South Kalimantan.
From Palangkaraya to Banjarmasin with mileage 190 Km by road
within 4 hours using four-wheel vehicles with a paved road conditions.
Then from Banjarmasin proceed to Tapin (up in the mess Bypass KPP)
with a distance of 84 Km by road within 2.5 hours using four-wheel
vehicles with a paved road conditions.
From mess to the office of PT. Kalimantan Prima Persada with a distance
of 5 Km by road within 15 minutes drive buses with the condition of
the dirt road.
From the office to the mining authority Job Site Location PT. Kalimantan
Prima Persada with a distance of 5 Km by road within 15 minutes
drive buses with the condition of the dirt road.
LOCATION AND ACCOMPLISHED REGION
Location mining of PT. Kalimantan Prima Persada
administratively located in the District of Bungur, Tapin
District, South Kalimantan.
From Palangkaraya to Banjarmasin with mileage 190 Km by road
within 4 hours using four-wheel vehicles with a paved road conditions.
Then from Banjarmasin proceed to Tapin (up in the mess Bypass KPP)
with a distance of 84 Km by road within 2.5 hours using four-wheel
vehicles with a paved road conditions.
From mess to the office of PT. Kalimantan Prima Persada with a distance
of 5 Km by road within 15 minutes drive buses with the condition of
the dirt road.
From the office to the mining authority Job Site Location PT. Kalimantan
Prima Persada with a distance of 5 Km by road within 15 minutes
drive buses with the condition of the dirt road.
RESEARCH METHOD
In conducting research in this final project, the author combines several methods, namely
Interviews
Interviews were conducted to obtain accurate data on the mine sequence by way of question and answer
directly to the section office and parts of the field.
Observation
Observation is direct observation of how the process of planning and production in the pit x.
research Library
The study aimed to collect data that supports and is concerned with this thesis theoretical nature by reading
books, journals, and more.
Grouping of data.
Furthermore, the data obtained from interviews, observation and research literature, then grouped into
secondary data and primary data. Secondary data is data supporting researchers obtained from the
Company, agencies involved with the research. Primary data is data taken researchers in the field and
processed researchers.
Data Processing
Data processing is done by doing some calculations and drawings are then presented in the form of
graphs or circuit calculations.
Study
Conduct analysis of the data of research results to obtain a solution to the settlement of the existing
problems.
Conclusions and recommendations
As a recommendation to the company to resolve the problems in the field related to this research.
Mulail

Rumusan masalah:

Bagaimanakah nilai SR di pit X pada PT. Kalimantan Prima Persada?

Bagaimanakah pit limit di pit X pada PT. Kalimantan Prima Persada?

Bagaimanakah perancangan produksi harian, mingguan dan bulanan di pit X pada PT.

Kalimantan Prima Persada?

Studi Literatur

Pengambilan Data

Data Primer Data Sekunder


1. Produktivitas alat gali/muat 1. Target produksi
2. Stripping Ratio (SR)
3. Topografi daerah penelitian
4. Litologi daerah penelitian
5. Rekomendasi geoteknik
6. logbor
7. Spesifikasi Alat Gali/Angkut
8. Face position sebelum dan sesudah produksi

Pengolahan Data dan Analisa Data


1. Mengolah data blok mine sequence dari berbagai data seperti pit limit
dan volume OB
2. Mengolah rencana produksi selama 1 bulan dengan data
Target produksi dan SR
3. Menghitung produktivitas alat gali/muat.

Hasil dan Pembahasan

Kesimpulan dan Saran

Selesai
RESEARCH METHOD
Kegiatan Minggu

I II III IV V VI VII VIII

induction Company

Study in office

Observation field

Data retrieval

Data Processing

Presentation in the office

Presentation evaluation
THANKS FOR ATTENTION