Académique Documents
Professionnel Documents
Culture Documents
Ingredients of Project
The Navy developed this method to evaluate and monitor progress of the
Polaris Missile Program.
The major difference between CPM and PERT is that PERT is a more
probabilistic approach that lends itself to activities for which there is little or
no historical experience, whereas CPM uses historical information for
establishing durations.
Demonstration
A house is to be constructed. The various activities are listed in the following table
with an information on time and predecessors.
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Project Network
Activity-on-node (AON)
nodes represent activities,
and arrows show
precedence relationships
Event Node
completion or beginning
of an activity in a project
1 2 3
Branch
AON Network for House Building Project
2 4
Finish work
2 3
7
Start 1 1
3
Design house 6
and obtain
3
1 5 1
financing
1 Select carpet
Order and receive
materials Select paint
Critical Path
2 4
2 3
7
Start 1 1
3
3 6
1 5 1
1
Start at 5 months
2 4
Finish at 9 months
2 3
7 Finish
Start 1 1
3
3 6
1 5 1
1 Start at 6 months
Start at 3 months
Node Configuration
Earliest finish
1 0 3
3 0 3 Latest finish
Lay foundations
Build house
2 3 5
Start 4 5 8
2
3
1 0 3 7 8 9
3 1
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1
1 5 5 6
Select carpet
Order and receive 1
materials Select pain
Activity Scheduling (cont.)
Latest start time (LS)
Latest time an activity can start without delaying critical path
time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical
path time
LF = minimum LS of immediate predecessors
Backward pass
Determines latest activity times by starting at the end of
CPM/PERT network and working forward
Latest Activity Start and Finish Times
Lay foundations
Build house
2 3 5
Start 4 5 8
2 3 5
3 5 8
1 0 3 7 8 9
3 0 3 1 8 9
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1 7 8
1 4 5 5 5 6
Select carpet
Order and receive 1 6 7
materials Select pain
Activity Slack
ES = LS or EF = LF indicates critical path
Activity LS ES LF EF Slack S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path
Slack Time and Critical Path(s)
Activity LS ES LF EF Slack S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path
Latest Activity Start and Finish Times
Activity 3-5-6 together can
be delayed by 2 months and
not by 3 months.
Lay foundations
Build house
2 3 5
Start 4 5 8
2 3 5
3 5 8
1 0 3 7 8 9
1 0 3 1 8 9
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1 7 8
1 4 5 5 5 6
Select carpet
Order and receive 1 6 7
materials Select pain
EXERCISE # 1
Data
Precedence
Activity Time Relationships
A 3
B 5
C 7 A
D 5 A
E 4 B,C
F 6 B
G 2 E,D
H 3 F
1. Develop a Gantt chart
2. Determine the total project completion time and critical path.
Network Diagram
A D
G
End
Start C
E H
B
Data
Precedence
Activity Time Relationships
A 2
B 5
C 1
D 10 B
E 3 A,D
F 6 C
G 8 E,F
B D
E
Start
A G
F
C
Analysis
Data
Activity Time Precedence Relationships
1 4
2 7
3 8 1
4 3 1
5 9 2
6 5 3
7 2 3
8 6 4 5 6
9 5 2
Gantt Chart
Gantt Chart
7
Activity
0 5 10 15 20 25
Time
Project Scheduling
Schedule
Early Early Late Late
Activity Start Finish Start Finish Slack
1 0 4 0 4 0
2 0 7 1 8 1
3 4 12 4 12 0
4 4 7 14 17 10
5 7 16 8 17 1
6 12 17 12 17 0
7 12 14 21 23 9
8 17 23 17 23 0
9 7 12 18 23 11
Duration 23