WELCOME TO :

KEPONG II WATER TREATMENT PLANT,


SYARIKAT AIR TERENGGANU SDN BHD
TEREGGANU DARUL IMAN
INTRODUCTION

SYARIKAT AIR TERENGGANU SDN BHD

OVERVIEW:
~NAME~
KEPONG II WATER TREATMENT PLANT

~LOCATION~
KAMPUNG KEPONG, 20050 KUALA TERENGGANU

~BASE AREA~
17.792 ACRE

~YEARS OF CONSTRUCTION~
PHASE 3 : 1999
PHASE 4 : 2005

~OPERATION START~
PHASE 3 : 2004
PHASE 4 : 2006
ORGANIZATION CHART FOR KEPONG II WATER TREATMENT
PLANT
CHIEF EXECUTIVE OFFICER

Ir. HAJI ATEMIN BIN SULONG

SENIOR MANAGER OF PRODUCTION AND


ENGINEERING SERVICES

Ir. HAJI FAKHRURAZI BIN ISMAIL


MANAGER OF SAFETY AND HEALTH

CHIEF TECHNICAL OFFICER OF KUALA AFIQ AISOR BIN DATO A RAHMAN


TERENGGANU

AHMAD MUAZ BIN MUHAMAD

TECHNICAL OFFICER

AZEMI BIN MUSTAFA

KEPONG II OPERATOR
PRODUCTION ASSISTANT OFFICER
ALIAS BIN JOHARI
GHAZALI BIN JUSOH
HANAFIAH BIN MOHAMAD
HASHIM BIN AWANG
MOHD FAISAL BIN AHMAD
MOHD HILMI BIN KAMAL ARIFFIN
MOHD HAFIS BIN YUSOF
ZAMRI BIN MOHD
MOHD KHAIRUDDIN BIN MIRANG

MOHD MUHAYIDI BIN JUSOH

SYED SHARDY BIN SYED HASSAN


24-hour security
control by a
private security
control company

The plant area


Gazetted as a is covered by a
restricted area 8-foot chain link
by national fence and a 2-
security foot barbed
council wire
Disinfection
Raw Water
Filtration and pH
from Intake
correction

Clear Water
Inlet Tower Sedimentation
Tank

Coagulation /
Aeration
Flocculation
INLET TOWER

Raw Water from Serada


Pre-lime dosing (adjust
pH)
AERATION TANK
Dosing of Potassium
Permanganate (Manganese
Level)

Increase O2 level
Reduce odor of raw water
COAGULATION / FLOCCULATION

Aluminium
Sulphate -
Form solid
dense floc
SEDIMENTATION

Lamella System
Separate floc
Sludge traps at clarifier
and settle to
sedimentation tank
FILTRATION

Polishing steps (Remove small floc / precipitated particles)


Hydraulic Backwashing Wash dirty filters every 72 hours or
less
CLEAR WATER TANK

Dosing of chlorine and hydrated lime takes place


Pumping House Station has 16 treated water pump with different capacities
based on the size of the pump
Type of pump : Horizontal Split Casing
The rate of motor pump : 400kW

LOCATION OF PUMP DISTRIBUTION

Kuala Terengganu
- 4 pump was sent to Bukit Panji tank
- 4 pump was sent to Bukit Berangan tank

Marang
- 4 pump was sent to Bukit Gondang tank
- 4 pump was sent to MIEL tank
PRODUCTION CAPACITY
Design Capacity
- 180 million liter per day or 39.6 million gallon per day

Daily Production
- 150 million liter per day or 33.0 million gallon per day
PRODUCTION OF KEPONG II
Production 150 mld
The daily production of
Loji Kepong II in total
was 150(MLD) that
involving 2 district that
cover 55% of distribution
system for Kuala
Kuala
Terengganu district and Terengganu
Marang
66.2% of distribution
system for Marang 102 ( MLD )
48 ( MLD )
district.
DISTRIBUTION SYSTEM OF KEPONG II
The distribution system of Kepong II was covered 7 balance tanks in Kuala Terengganu
district and 2 balance tank in Marang district.
The tanks in Kuala Terengganu was Bukit Berangan tank ( 3 tanks ) and Bukit Panji ( 4
tanks ). Meanwhile the balance tanks in Marang was MIEL tank and Gondang tank.

Berangan Tank
1,2 & 3
1200mm dia. ( 60 mld )

Panji Tank
1,2,3 & 4
800mm dia. ( 42 mld )
Pump House
Loji Kepong II MIEL Tank
800mm dia. ( 31 mld )

Gondang Tank
600mm dia. ( 17 mld )