Académique Documents
Professionnel Documents
Culture Documents
Aeronautical Association
Faculty of Engineering
EEE department
CONTENTS
Introduction .
Problems of economic operation.
Unit commitment.
Operation cost of a thermal plant .
Different constraints in economic load dispatch .
Economic dispatch neglecting losses and no generator limits.
Economic dispatch neglecting losses and including generator limits.
Economic dispatch in power system interconnection .
Conclusion.
Economic Dispatch
Introduction.
Economic Dispatch
Introduction.
Also, In an interconnected power
system, the objective is to find
the real and reactive power
scheduling of each power plant in
such a way as to minimize the
operating cost.
This means that the generator's
real and reactive power are
allowed to vary within certain
limits so as to meet a particular
load demand with minimum fuel
cost. This is called the optimal
power flow (OPF) problem.
Economic
Pag.1 Dispatch
Introduction.
Economic
Pag.1 Dispatch
Introduction.
The cost of operation varies
from generator to generator
based on factors such as the
type of fuel used, efficiency of
the generator and start-up
costs.
Economic
Pag.1 Dispatch
Introduction.
Economic dispatch depend on
the types of the plants in each
system .
Economic
Pag.1 Dispatch
Problems of economic operation.
The economic operation can
be subdivided into two
parts:
Economic
Pag.1 Dispatch
Unit commitment.
The unit commitment problem (UC) in
electrical power production is a large
family of mathematical optimization
problems where the production of a set of
electrical generators is coordinated in
order to achieve some common target,
usually either match the energy demand
at minimum cost or maximize revenues
from energy production. This is necessary
because it is difficult to store electrical
energy on a scale comparable with
normal consumption
Economic
Pag.1 Dispatch
Constraints in unit commitment.
1- Spinning reserve:
It is the total amount of generation available from all unit synchronized on the
system minus the present load and loss being supplied.
Economic
Pag.1 Dispatch
Constraints in unit commitment.
2- Thermal unit constraints:
Minimum up time: once the unit is running , it shouldn't turn off immediately.
Minimum down time: once the unit is de-committed , it cannot be turn on
immediately .
Crew constraint: if a plant consists of two or more units , they cannot be turn on at
the same times since there are not enough crew members to attend both units
while starting up .
3- Hydro-constraints: Unit commitments cannot be completely separated from
scheduling of hydro-units .
4- Must run constraint : some units are given a must-run status during certain
times of the year .
5-Fuel constraint: Some plants cannot be operated due to deficient fuel supply.
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
Also, if the plant is located far from the
load center, transmission losses may be
considerably higher and hence the plant
may be overly uneconomical. Hence, the
problem is to determine the generation
of different plants such that the total
operating cost is minimum.
Power plants consisting of several
generating units are constructed
investing huge amount of money, fuel
cost, staff salary, interest and
depreciation charges and maintenance
cost are some of the components of
operating cost.
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
Fuel cost is the major portion of
operating cost and it can be
controlled. Therefore, we shall
Output
consider the fuel cost alone for
further consideration.
Input G
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
An important characteristic is obtained by
plotting the derivative of the fuel-cost curve
versus the real power. This is known as the
incremental fuel-cost curve () shown in
Figure.
The incremental fuel cost curve is a measure of
how costly it will be to produce the next
increment of power.
The total operating cost includes the fuel cost
and the cost of labor, supplies and
maintenance. These costs are assumed to be a
fixed percentage of the fuel cost and are
generally included in the incremental fuel-cost
curve.
Economic
Pag.1 Dispatch
Operation cost of a thermal plant :
An economic dispatch schedule for assigning loads to each unit in a plant can be
prepared by :
A. Assuming various values of total plant output.
B. Calculating the corresponding incremental fuel cost of the plant.
C. Substituting the value of for (1, 2..) in the equation for the incremental fuel cost
of each unit to calculate its output.
For a plant with two units having no transmission losses operating under economic
load distribution the of the plant equals i of each unit, and so
Economic
Pag.1 Dispatch
Different constraints in economic load dispatch
- Voltage constraints:
- Generator constraints:
KVA loading of generator should not exceed prescribed value :
Economic
Pag.1 Dispatch
Different constraints in economic load dispatch
- Running spare capacity constraints:
This constraints are needed to meet forced
outage of one or more alternators in the
system and also unexpected load on the
system .
- Transmission line constraints:
Flow of power through transmission line
should less than its thermal capacity.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and no generator limits.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and no generator limits.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and no generator limits.
Since :
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and no generator limits.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and no generator limits.
Example : system consists of three plants ,
- The fuel cost functions for three thermal plants in $/h are given by:
= + +. = + +. = + +. ($/h)
=
Power of each plant (MW) Total cost ($/h)
800 15620 15600
691.9 15600
700
600 614.8 600 600 15580
600
493.2 15560
500
15540
400 15520
300 15500 15490
200 15480
100 15460
15440
0
15420
P1 P2 P3
COST1 COST2
without diapatch with dispatch without dispach with dispatach
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and including generator limits.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and including generator limits.
Economic
Pag.1 Dispatch
Economic dispatch neglecting losses and including generator limits.
Example : system consists of three plants ,
- The fuel cost functions for three thermal plants in $/h are given by:
= + . +. 470 P1 600
= + . +.
300 P2 500
= + . +.
= 150 P3 200
Economic
Pag.1 Dispatch
Economic dispatch including transmission losses.
Economic
Pag.1 Dispatch
Economic dispatch including transmission losses.
The associated
mathematical definition
becomes:
Economic
Pag.1 Dispatch
Economic dispatch including transmission losses.
Economic
Pag.1 Dispatch
Economic dispatch including transmission losses.
Example : system consists of three thermal plants ,
- The fuel cost functions for three thermal plants in $/h are given by:
= + . +.
= + . +. = . +. +.
= + . +.
=
Economic
Pag.1 Dispatch
Economic dispatch in a power system interconnection .
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Types of the power interconnection .
3- Energy banking : Energy banking agreement
usually occurs when a predominantly hydro
system is interchange to a predominately
thermal system.
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Types of the power interconnection .
4- Emergency power interconnection : It is
very likely that at some future time a power
system will have in series of generation
failure that requires it to import power.
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
= + +. Area 2
PD=200MW
100 Pi 400
Economic
Pag.1 Dispatch
Economic dispatch in power system interconnection .
Example : Three areas are interconnected
with each other, 100 Pi 400 PD (each area)=200MW TL(limit)=75MW
50 2900
0 2800
P1 P2 P3 cost
without inter with inte. and without TL.limits without inter.and TL.limits withinter. And without TL.limits
Economic
Pag.1 Dispatch
Conclusion.
2- The unit commitment is concerned with determining which units to turn on/off.
5- Interconnection power systems makes the system more reliable and better
economic of operation .
Economic Dispatch
References .
Hadi Saadat, Power system Analysis, Tata McGraw Hill Publishing Company,
New Delhi, 2002.
Economic Dispatch
Contact information:
Eng. Hussein Ali Hussein Eng. Ayad Tahseen Abdul hafedh Eng. Omar Sagban Taghi
Economic Dispatch