Académique Documents
Professionnel Documents
Culture Documents
MANAGEMENT
By ENGR.(MRS) OBANLA
What is a Project?
2
Start B
A 1 C 3
D
4
Example
Represent the following activities on network
diagram
Activity Dependency
A -
B A
C A
D A
E B,D
F C
solution
4
D
2
B E
A
1
F
C
3
N.B:
is called Dummy Activity. It is denoted by broken line
Example
Represent the following activities on network diagram
Activity Dependency
A -
B -
C A
D A
E B
F C, E
G C, E
H F
I G, D
J H, I
Solution
Exercise
Represent the following activities on network diagram
Activity Dependency
A -
B -
C A, B
D A
E C, D
F E
G E
H C, D
I F, G
J H, I
Exercise
Represent the following activities on network diagram
Activity Duration Dependency
A 7 -
B 3 -
C 6 A
D 3 B
E 3 D, F
F 2 B
G 3 C
H 2 E, G
Critical Tasks
E L E L
Start of activity Y End of activity Y
P = Event,
E = Earliest Finish Time (EFT)
L = Latest Finish Time (LFT)
EFT is the time duration to finish an event.
EFT for one event indicates the EST (earliest start time) for the
next activity.
LFT is the time each event must be reached if the project is to
be completed by the end of EFT. It is obtained through
backward calculation
Identifying Critical Path
The critical path can be identified by determining the
following four parameters for each activity:
• EST - earliest start time: the earliest time at which the
activity can start given that its precedent activities
must be completed first.
• EFT - earliest finish time, equal to the earliest start
time for the activity plus the time required to
complete the activity.
• LFT - latest finish time: the latest time at which the
activity can be completed without delaying the
project.
• LST - latest start time, equal to the latest finish time
minus the time required to complete the activity.
Identifying Critical Path
• Slack time for an activity is the time between its earliest
and latest start time, or between its earliest and latest
finish time.
• Slack is the amount of time that an activity can be
delayed past its earliest start or earliest finish without
delaying the project.
• The critical path is the path through the project
network in which none of the activities have slack, that
is, the path for which EFT = LFT for all activities in the
path.
• A delay in the critical path delays the project. Similarly,
to accelerate the project it is necessary to reduce the
total time required for the activities in the critical path.
Example
Establish the critical path of the network diagram obtained from the table below
Activity Time Taken (days) Preceding Activity
A 3 -
B 6 A
C 4 A
D 10 B, C
E 5 D
F 10 D
G 1 E, F
H 5 E
I 8 E
J 15 G, H, I
K 5 J
L 2 J
M 10 K
N 2 L, M
Exercise
Establish the critical path of the network diagram obtained from the
table below
Activity Time Taken Preceding Activity
A 2 -
B 20 A
C 15 -
D 5 -
E 15 D
F 5 B, E
G 15 F
H 5 G
I 5 B, C
J 5 H, I
Exercise
Establish the critical path of the network diagram obtained from the
table below
Activity Time Taken Preceding Activity
A 9 -
B 2 -
C 12 A
D 10 A
E 12 B
F 6 C, E
G 7 C,E
H 14 F
I 8 G, D
J 3 H, I
Exercise
Establish the critical path of the network diagram obtained from the
table below
Activity Time Taken Preceding Activity
A 10 -
B 2 -
C 3 A, B
D 12 A
E 5 C, D
F 3 E
G 5 E
H 9 C, D
I 16 F, G
J 2 H, I
Exercise
Establish the critical path of the network diagram obtained from the
table below
Activity Time Taken Preceding Activity
A 2 -
B 10 -
C 4 A
D 2 B
E 3 A, D
F 3 B
G 8 C, E, F
H 2 G
I 2 G
J 4 H
K 2 I, J
Exercise
Establish the critical path of the network diagram obtained from the
table below
Activity Time Taken Preceding Activity
A 7 -
B 13 A
C 3 B
D 9 C
E 19 C
F 6 G
G 7 E
H 10 G
I 10.5 E
J 5 D, F, H, I
K 8 L
L 3.5 D, I
M 2 J, K