Académique Documents
Professionnel Documents
Culture Documents
Presented by
Mervyn Malvar, M.Eng
Department of Civil Engineering
Gokongwei College of Engineering
De La Salle University
Activity Time-Resource Concept
• Activity duration depends on the following:
• Method to be used
• Quantity of the works involved
• Estimating department will be aware of the quantity; however,
project support may have to be consulted to determine the
method to be followed.
Concept of time-cost-trade-off
• Time-cost-trade-off occurs when we would like to accelerate the
construction project
• We attempt to reduce the durations spent on an activity
• Based on the network diagram, each activity’s duration can be
reduced
• However, only activities on critical path can affect the duration.
• Usually recommended/discussed at early stages of the project.
Total Project Cost vs Time Extension
DIRECT COSTS INDIRECT COSTS
• Material Costs • General Preliminaries
• Management and Technical
• Labor Costs
Overhead
• Equipment
• Temporary Facilities
• Can be assigned to individual • General Site Expenses (Safety,
activities Security, Housekeeping)
• Major equipment (including
FOL, maintenance)
• Permits
• Owner’s / Consultant’s / CM’s
Temporary Facilities
• Expats, Travel benefits
• Barging and Shipping Charges
• Design Services / Professional
Fees
Total Project Cost vs Time Extension
INDIRECT COSTS
• Taxes (Contractor’s Tax, VAT, etc)
• Bonds and Insurances (Surety
Bond, Guarantee Bond, CARI, etc)
• Basically the cost of doing business
• Applied to the whole project
Direct Cost
• Cost on each activity in the project network
• BOQ cost per item
• Direct costs increases when duration is shortened
Indirect Cost
• General overhead
• Indirect costs decreases when duration is shortened
Total Cost
• Sum of direct and indirect costs at any point in time
• It is natural for a contractor to perform any project at the
minimum total cost
Calculation of TCTO
G,7
Calculation of TCTO
39000
38500
Minimum Direct
Cost Curve
38000
Cost
37500
Maximum Direct
37000 Cost Curve
36500
36000
35500
24 25 26 27 28 29 30 31
Duration
Method 1.1: Minimum Cost Curve from Normal
Start
• Normal start aims to develop the project’s minimum direct cost
curve from the normal time-cost point
• i.e. Shorten the project duration at the least possible increase in
cost
Method 1.2: Minimum Cost Curve from all Crash
Start
• To reduce the cost downward, the criteria are
• Activities must be non-critical
• Must have the current maximum cost slope
• Activity can be lengthened / extended
• To extend the project duration, the criteria are
• Activities must be critical
• Must have the current maximum slope
• Activity can be lengthened / extended
Method 1.2: Minimum Cost Curve from all Crash
Start
• To reduce the cost downward, the criteria are
• Activities must be non-critical
• Must have the current maximum cost slope
• Activity can be lengthened / extended
• To extend the project duration, the criteria are
• Activities must be critical
• Must have the current maximum slope
• Activity can be lengthened / extended
Assignment No. 4