Accidents in Steel Gas Pipe Line
Cause : Pipe Line was hit during laying of
sever line by MTBM( Micro tunnel Boring
Machine)
Information was not provided.
No. of CNG Stations affected:3
No. of DTC Depot affected :2
No. of R.O affected :3
No. of FRS affected :0
Date: 2th Jan 2014 at 15.00 hrs
Location : NH-24 CNG Station
Diameter: 4"
Affected Length: 6.4 km
Total Hours of interruption: 20
Reason : Damage by Puncture of dielectric
material of Insulating Joint at NH-24 CNG
station due to electric surge.
There was a fire at CNG station.
High pressure leakage occurred.
No. of CNG Stations affected:0
No. of DTC Depot affected :2
No. of R.O affected :3
No. of FRS affected :1
Date: 3th Feb 2014 at 17.50 hrs
Location : Burari chawk
Diameter: 4"
Affected section of pipe line :Burari chawk To
Sai R.O.
Affected Length: 0.6 km
Reason :Operational error (by PWD during
construction of Mukarba Wazirabad elevated
road)
Cause : Wrong offsets in drawing and locator
couldn’t locate because of its depth(13 m)
according to drawing, offset of line was 11
m, clearance was provided to the contractor
17 m, piling activity was done at 23 m.
No. of CNG Stations affected:0
No. of DTC Depot affected:0
No. of R.O affected :2
No. of FRS affected :0
Findings : locator can’t locate below 5 m
Following are the reasons for the Damages:
3rd Party damage due to excavation by DTL,
DDA, PWD, DJB etc.
Operational Errors like improper working of
locator, not to check drawings etc.
Un controlled errors / time independent like
puncture of dielectric material, due to
electric surge.
Total no. of Damages : 14
No. Of Damages by 3rd Party Damage : 8
No. Of Damages due to Operational errors : 4
No. Of damages due to un controlled/time
independent :2
14%
3rd Party Damage
uncontrolled/time
independent
To Rectify operational errors
Calibration of the equipments to be done on
timely basis.( not followed till now)
Check the certificates of HDD operator and
Tracker.
All pipeline fittings and accessories should
be checked and operational life time of all
should be decided.
Check drawings and locator both during the
construction work.
Drawings should be properly checked by
zonal in charge after laying of steel line by
contractor.
The hydrostatically tested pipes should be
retested by nitrogen gas before charging the
line.
Protective measures from Electric installation(
Neoprene sheets, RCC blocks, Minimum
distance should be maintained).