PROJECT
• Cranes
• Lorries
• Locomotives
• TBM (with TGS software)
WORK TO BE DONE BY SNABLOVA
• Electrical Substation
• Power lines to tunnel
• Locomotives, cranes and lorries will be used to move spoil excavated from both shaft
and tunnel
• Time for removal = time for tunnel excavation + 4wks
• Will be done over the course of the project
• Spoil taken to ex-mining town
• ZRGreen
RESOURCE ALLOCATION
SCHEDULE
• Starts on 1/12/17 and ends on 10/9/18
• Gantt Chart Created in MS Project has 2
calendars – Standard and 24-hr.
• 24-hr calendar counts as 3 8-hr shifts (3 days in
1)
• Total project duration = 202 days
• Refer to Gantt Chart in MS Project file provided
for better visual of schedule
• Certain Tasks have to be done within a certain
timeframe
• Most time-consuming tasks are tunnelling,
implementing all systems into the tunnel and
spoil removal.
• Tunnel excavated at 100m/wk (140 days) all
systems take just as long to implement (ideally)
• Spoil removal is time for excavation + 4wks