on
Cut to ship & order
to ship ratio and
WIP & Throughput
Time
Contents:
1. Normally, factories those make export orders, cut extra garments than the
actual order quantity. In the garment making process, there are possibilities of
garment damage and rejection. So to ensure that 100% order quantity is shipped
to buyer after discarding damaged garment, factories cut extra garments.
Garment exporters generally cut 2-5% extra garment than order quantity. Extra
percentage of cut quantity is planned by merchandiser or other authorized
person.
2.
There are few other reasons for cutting extra garments than order quantity.
Like, few buyers accept extra garments than order quantity up to certain
percentage with same FOB, in such cases factories try to sell more garments to
increase sales turnover. Secondly to utilize maximum fabric that are sourced for
a specific order. Percentage figure of extra garment cutting varies depending on
fabric types and number of processes involved in conversion process from fabric
to finished garment.
Reasons for measuring cut to ship ratio and order to
ship ratio of orders.
Some of reasons for measuring cut to ship ratio and order to ship
ratio are…..
1.If throughput time is less that means materials are making money
quickly. That means material waiting time are reducing and WIP &
inventory are decreasing .
Throughput = WIP x Cycle Time
•lead time is the time between the initiation and delivery of a work item.
•cycle time is the time between two successive deliveries
•throughput is the rate at which items are passing through the system.
•WIP – Work in progress; the number of work items in the system. Work
that has been started, but not yet completed
If throughput is more
1.Need more space to cover WIP
2.Increase wastes motion of operator to manage big
bundle
3.Mistake bundle size because of different size of the
line.
4.Unnecessary transportation of bundle back and fro in
the line.
5.Effective combo packing to the next operation or
order(required color matching for packing bundle.
6.Working time increase and excess overtime to finish
WIP(lack of team concept).
7.Operator focus to finish the large WIP not focus on
quality. Quality at the source not focus, It increases
alter%, reject%. its totally waste.