BITUMINOUS(asphalt) ROAD

SUMMER INTERSHIP PROJECT PPT


2017

Submitted to- Submitted by-


Department of CIVIL ENGINEERING MAHENDRA SINGH
SEC-RTU
CONTENTS:-

1. Introduction of road
2. Laboratory test
a) Aggregate test
b) Concrete test
3. Pavement composition
4. Coating of bituminous
1.INTRODUCTION:-
Name of work:-

construction of urban gaurav path kamli ghat to kailashpuri


Chouraya deogarh (ch 2/000 to 3/500) up to charniya deogarh dist.
Rajsamand

Scope of work :-

Widening of existing 5.50m carriage way by 5.50 m wide each up&down lane with provision of
1.00 m Median and 1.50 m hard shoulders also be included in this project.Widening of existing
C D work &P wall also including in this project Road Design and Specification.

Formation of road:-

The formation width of road has been widen from exiating average width 10.0 m to 20.0 m
width.

Over earth work 210 mm thick GSB of grading III material has been proposed on widen
porsion soaked CBR of soil has been found as 5.00%
Road Furnishing:-

RCC M15 grade Kilometer Stones & 200 Mtr Stones of standard design as per IRC : 8
shall be provided as per Technical Specifications Clause 1703.

Providing and fixing of retro reflective cautionary, mandatory and informatory sign
board as per IRC:67 made of 1.5 mm thick MS Sheet as per Specifications

Testing of Aggregates:-

PARTICLE SIZE / GRADING ANALYSIS

To determine the % of weight passing of a certain particle size present in a particular


material/aggregates.

Apparatus
Tray 75cmx75cmx5cm, sample containers 30cmx15cmx15cm, spade,
shovels, digital balance with accuracy 0.5gm, IS sieve size 90,63, 53, 45, 40, 37.5, 26.5,
25, 22.4, 20, 19, 16, 13.2, 10, 9.5, 4.75, 2.36, 1.18, 0.6, 0.3, 0.15, 0.075 mm
Fig:-Partical size Distribution

AGGREGATES IMPACT VALUE:-


the aggregates impact value, which is a measure of resistance to a sudden shock or
impact of loads.

Apparatus:-
Tray 75cmx75cmx30cm, sample containers 30cmx15cmx15cm, spade, shovels,
IS sieve size 12.5mm, 10mm, 2.36mm, digital balance with accuracy 0.5gm, cylindrical
metal measure, cylindrical steel cup, straight metal tamping rod, impact testing
machine.
Fig:-aggregate Impact Value

TESTING OF CONCRETE

CUBES COMPRESSIVE STRENGTH:-

Objective
the strength of concrete mixes according to desired ages of concretes (Normal
age would be (168+/-2 (7days), and 672+/-4hrs(28 days)). , where the strength would
be used for quality controls purposes.
Apparatus:-

Shovel, containers 30cmx15cmx15cm, big tray, slump rod, standard casting mould 15x15x15cm
dimension, vibrating hammer, needle vibrator size 2inches dia, compressive testing machine.

Fig:-Cube Testing Mshine


PAVEMENT

PAVEMENT COMPOSITION:-

Pavement is constructed using “Typical Cross-section” and “Plan and Profile”


Drawings.
Types of Pavement:-

Rigid Pavement:-
A rigid pavement is constructed from cement concrete or reinforced concrete slabs. Grouted
concrete roads are in the category of semi-rigid pavements.

Fig:-Pavement
Flexible Pavement:-

Flexible pavement can be defined as the one consisting of a mixture of asphaltic or bituminous
material and aggregates placed on a bed of compacted granular material of appropriate quality in
layers over the subgrade. Water bound macadam roads and stabilized soil roads with or without
asphaltic toppings are examples of flexible pavements.

Fig:-Flexible pavement
COATING OF BITUMINOUS:-

a) Prime coating :-
A prime coat is an application of a low viscosity asphalt to a granular
base in preparation for an initial layer (or surface course layer) of asphalt. The purpose of
the prime coat is; to coat and bond loose material particles on the surface of the base, to
harden or toughen the base surface to provide a work platform for construction
equipment, to plug capillary voids in the base course surface to prevent migration of
moisture, and to provide adhesion between the base course and succeeding asphalt
course. After applying the prime coat, it must cure for a minimum of 48-72 hours before
asphalt is placed, with no rain in the forecast.

b).Tack coating:-
Tack coats are a vital component of an asphalt pavement's structural
system as they bond the multiple asphalt lifts into one monolithic layer. Poor tack coat
application results in poor bonding of the asphalt layers

C).Seal coat:-
a final coat of bituminous material applied during construction to a
bituminous macadam or concrete for sealing the surface of the pavement.
THE END