• Sometimes it is the requirement of the project to apply different overtime rate in addition to Regular overtime rate to a specific resource on a specific task. • Suppose that you have a work resource who has to work on Task, and his regular rate is $100 per hour, and overtime rate is $200 per hour. • But on this specific Task you what pay same resource $400/H for overtime work, and $100/H for regular work (this regular rate can also be changed, if required). 7B-Assigning and Managing Overtime 1 Create a Work Resource “Ali” using resource sheet in view tab. 2 Standard Rate is $100/Hr and Overtime Rate is $200/Hr. 3 Base is Standard (40 Hrs/Week) 7B-Assigning and Managing Overtime 1 Create two tasks ‘A’ and ‘B’ each of 5 days each in Gantt Chart view. 2 Add ‘Work’, ‘Overtime Work’, ‘Overtime Cost’ and ‘Cost’ columns. 3 Apply dependencies between tasks. 4 Assign Resource ‘Ali’ to both tasks. 7B-Assigning and Managing Overtime 1 To use difference overtime rate, go to View tab, Other Views, More Views and then select “Task Usage” view. 2 Add ‘Work’, ‘Overtime Work’, ‘Overtime Cost’ and ‘Cost’ Columns, if not already displayed. 3 Change Timescale to “Weeks” 7B-Assigning and Managing Overtime 1 Add 8 Hour in “Overtime Work” column to both resources on both tasks in Task Usage view. 2 When there was no overtime, task was completed in 5 days and it costs $ 4,000/-. 3 After addition of 8 Hr overtime task completes in 4 days but costs $ 4,800/-. 4 MS Project add the overtime work to total task work. 7B-Assigning and Managing Overtime 1 In View tab click Resource Sheet, double click resource “Ali”. 2 In the Resource Information click “Cost” tab. 3 In the ‘Cost rate table’, click ‘B’ tab. 4 Add “Overtime” (400/hr) rate different from mentioned in Resource Sheet. 7B-Assigning and Managing Overtime 1 In View tab click Other Views then More Views and select “Task Usage” View. 2 In Task Usage view, double click the task resource whose overtime rate is required to be change. 3 In Assignment information, General Tab, Select Cost Rate table “B” and click OK. 7B-Assigning and Managing Overtime 1 Difference of overtime rate is shown in Overtime Cost column for the Single Resource “Ali” working on two different tasks. 7B-Assigning and Managing Overtime • 10 hours of daily work shown in Resource Usage view – 8 Hr Standard Rate. – 2 Hr Overtime Rate.