Académique Documents
Professionnel Documents
Culture Documents
MANAGEMENT
CHAPTER 5: PROJECT STAGES
3
Project Stages
Overall Design and Construction Process
Occupancy
Concept (Pre- and Post- Utilization
(Designer) Occupancy (End User)
Evaluation)
5
(Jackson, 2010)
Project Stages
7
Design and Construction Process
Design
Pre-construction
Procurement
Construction
Post-Construction
Occupancy
9
(Jackson, 2010)
DESIGN STAGE
10
Design Stage
Involves an intensive study
and a lot of considerations.
12
(Jackson, 2010)
Design Stage
Is about function and
layout.
(Jackson, 2010) 14
Design Process: Programming and Feasibility
16
(Jackson, 2010)
Design Process: Programming and Feasibility
17
(Jackson, 2010)
Design Process: Schematic Design
Rough Sketches
23
(Jackson, 2010)
Design
Process:
Design
Development
27
CODES AND COMPLIANCE ISSUES
Contractor is usually
not involved until after
the final design stage.
30
(Jackson, 2010)
CODES AND
COMPLIANCE ISSUES
Obtain the building permits.
33
BIDDING STAGE
37
(Jackson, 2010)
PRE-CONSTRUCTION PHASE
38
PRE-CONSTRUCTION PHASE
A typical construction
project will have:
1. a project manager
2. contract administrator
3. general superintendent
4. assistant superintendent
5. At least one field engineer.
44
(Jackson, 2010)
ASSIGNING THE
PROJECT TEAM
On-site project team is
supported by the office
management team in
the form of:
1. estimating
2. contract administration
3. accounting
4. job costing
5. payroll.
45
(Jackson, 2010)
TEAM MEMBERS AND THEIR ROLES
46
PROJECT
MANAGER (PM)
- “Captain” of the team.
- Has extensive experience in
construction
- broad background in all
aspects of the management
process
- size of the company and the
size of the project ultimately
influence the specific duties
of the PM
47
(Jackson, 2010)
PROJECT MANAGER (PM)
57
DUE DILIGENCE
62
SOIL TESTING AND
ENGINEERING
Reliable practice.
Eliminates surprises associated
with subsurface conditions.
Owners should insist upon these
tests.
Designers should ensure that the
reports are made part of the
supplemental conditions to the
contract.
(Jackson, 2010) 63
VALUE ENGINEERING
64
VALUE
ENGINEERING
A thorough analysis is
conducted of the design,
whether the proposed design
solutions are really the best
solutions relative to their cost.
purpose of value engineering is
to optimize resources to
achieve the greatest value for
the money being spent. 65
(Jackson, 2010)
VALUE ENGINEERING
67
PERMITTING AND INSPECTION PROCESS
69
(Jackson, 2010)
PROCUREMENT
STAGE
70
PROCUREMENT
STAGE
To procure means to buy or obtain.
Often referred to as “buying out”
the job.
Two primary instruments associated
are subcontracts and purchase
orders.
Can be a major department or
division within the construction
company whereby purchases are
made on a regional or national
level. 71
(Jackson, 2010)
SUBCONTRACTS
72
SUBCONTRACTS
General contractors buy trade
labor through subcontracts.
During the bidding process,
various trade contractors offer up
bids for various sections of work.
No contract between the general
contractor and the trade
contractor.
Is just an offer of services
(sometimes including materials) at
a specified price.
73
(Jackson, 2010)
SUBCONTRACTS
75
PURCHASE ORDER
An agreement
between a vendor and
a customer to provide
certain products that
meet a particular
specification for a
specified price.
76
(Jackson, 2010)
PURCHASE ORD
78
CONSTRUCTION
STAGE
Need to establish an
environment of trust and
cooperation right up front.
Good superintendents
know that they must spend
almost as much time
building relationships as
they spend building the
facility. (Jackson, 2010) 79
MOBILIZATION
80
MOBILIZATION
Is all about setting up and
getting ready to start
construction.
Construction cannot begin
until all of the proper
personnel, materials, and
equipment are in place.
Sets the stage for all that is
to follow 81
(Jackson, 2010)
REFERENCES
84
(Jackson, 2010)
END OF PRESENTATION
85