BRICK CALCULATION
• Modular brick=19x9x9
• Mortar thickness=10mm
• =1CM
• Ratio Mortar=Cement+Sand

• 1:6

• 1m3 brick Volume=0.20x0.10x0.10


• =0.002m3
• No.of brick in 1 m3=1/0.002
• =500
• Volume of brick without mortar=19x9x9
• =0.001539m3
• Volume covered by 500 no. of brick(1m3)=500x0.001539
=0.7695m3
Cost of brick=No.of brick*500

• Volume of mortar in 1m3=1-0.7695


• =0.2305m3 (wet Volume)
• 33% increase dry volume=0.2305*1.33
• =0.306m3
CEMENT ESTIMATION
• Cement (1:6)
• =(Dry Volumex1/Range)

• =0.306x1/7

• =0.043m3
Density of cement=1440
• (0.306x1)/7x1440
• =62kg
• 1Bag=50Kg
• No.of Bag=62/50
=1.24 Bags
Cost of Cement=300 per bag
SAND ESTIMATION
• Density of sand=1450

• 0.306X6/7=0.262M3
=0.262X1450(Density of sand)
=379kg
(1brass=4528kg)
379=0.0837brass
1brass sand cost=7300 Rupee
379kg sand cost=0.0837x7300
=611.01 Rupee