Académique Documents
Professionnel Documents
Culture Documents
2
Purpose of Protection System:
The protective relaying system senses the abnormal condition of power
system and gives an alarm or isolates the defective system from the
healthy system.
A fault in an electrical system is defined as a defect in its electrical
circuit due to which the current is diverted from the intended path.
Faults are generally caused by breaking of conductors or failure of
insulation. Some other causes of fault conditions include:
Mechanical failure
Environment disturbances
Excessive internal & external stresses
Operating error
Equipment malfunctions
The fault impedance being low, the fault current are relatively very
high and flows towards the fault.
3
Requirements of Protection system:
4
Types of Protective equipment
FUSES
PROTECTIVE RELAYS
5
FUSES
A Fuse is a short piece of metal,
inserted in the circuit, which melts
when excessive current flows
through the circuit and thus breaks
the faulty circuit.
The fuse element is generally made of material having low
of low melting point, high conductivity and least
deterioration due to oxidation, e.g. silver, copper etc. it is
inserted in series in the circuit to be protected.
6
Classification of Fuses:
i. Low-voltage fuses
• Semi-enclosed rewirable fuse
• High rupturing capacity (HRC) cartridge fuse
• HRC fuse with tripping device
7
Miniature Circuit Breakers (MCBs)
8
Protection Relay
A protection relay is a device that detects the fault and
initiates the operation of the circuit breaker to isolate the
defective system from the rest of the healthy system.
The relay detects the abnormal condition by constantly
measuring the electrical quantities e.g. – voltage, current,
frequency, phase angle, status of circuit breakers , etc.
In changes of one or more quantities, the relay senses the
faults, its type and location of the fault.
9
10
Essential Requirements of Protective
System:-
1. Current Transformers or CT :-
CT,s are required to scale down the
primery current to suitable level so that
relay can use it. CT,s can be single core
or multi core. Each core can be single
ratio or multi-ratio. Separate cores are
needed for metering or protection
purposes. Normally secondary current is
1A or 5A as per requirement.
11
2. Potential Transformers or Voltage
Transformers or PT/ VT,s :-
12
3-Auxiliary AC or DC Supply:-
13
4. Circuit Breakers:
Circuit breakers or CB,s are very much needed to
operate the electrical circuits in all the operating
conditions i.e. on no-Load, on Full-load.
CB are also required to isolate the faulty system
from healthy system on receipt of command from
the protective system in the shortest possible
time.
CB status is also available to the protective system
to properly take the decision of the fault.
14
5.Precautions while developing/ studying
schematics:
- All the schematics are made without
any ac/dc supplies,
- All the pressure switches are in zero
pressure state,
- All relays are in non-operating state and
their contacts are in normal state,
- No current/ voltage from CT/ PT is
available.
15
Various types of Relays according to principle
of operation are as follows:
1) Electromagnetic Attraction Relay
i. Attracted armature type
ii. Solenoid type
iii. Balanced beam type
18
STATIC RELAY
19
MICROPROCESSOR based Numerical Relays:
In 1980s, programmable static relays incorporating
Microprocessor have been introduced.
A programmable protection & control system has a
Microprocessor or Microcomputer in its circuit. With
the help of the logic and the Microprocessor, the
integrated system can perform several functions of
Data acquisition, Data processing, Data transmission,
protection & control.
Earlier for each of these functions, separate
Electromagnetic or Static units were used along with
complex inter module wiring.
20
Block Diagram of a simple Microprocessor based Digital Static Relay
CB
CT
VT Trip coil
Input Unit
Data Logger
21
Relay Based on actuating parameters
-Over-current Relays,
-Under/ Over voltage relays,
-Over/ under frequency relays,
-Power directional relays,
-Over-fluxing relays etc.
22
Relays based on Operating
Characteristics:-
-Instantaneous Relays,
-Definite time delay relays,
-Inverse definite minimum time delay
relays (IDMT),
-Voltage restraint over current relay,
23
Relays based on their uses:
1-Differential Protection Relay
2.Restricted E/F Relay,
3.Distance Protection Relay,
4. Negative Phase Sequence Relay,
5. Neutral Over-current Relay,
6. Neutral Voltage Displacement Relay,
7. Over Fluxing Relay,
24
8. Over/ under voltage Relay,
9. Over-current Relay,
10. Bus-bar Protection Relay,
11. Breaker Failure Relay,
12.Direction O/C & Directional E/F
Relays
13.Over/ Under Frequency Relay,
25
Other type devices used as Relays:
- Oil Temperature Relays,
- Winding Temperature Relays,
- Oil surge Relays (OSR),
- Buchholtz Gas Relay,
- Pressure Relief valves (PRV),
- Pressure Switches,
- Level Gauges,
- Flow meters, etc
26
27
The Protection scheme of Vishnuprayag
Hydro Power Project(4x100MW) is
classified as :
Generator Protection
Generator Transformer Protection
Bus-bar Protection
Bus Coupler protection
Transmission Line Protection
Shunt Reactor protection
28
Generator/ Unit Protections
Relay : Model-REG216, Make-ABB
Main-I (GRP-1) Protection comprising :
i. Generator Differential
ii. Under Impedance
iii. Negative Phase Sequence
iv. Gen. Over Current (Inst. & IDMT type)
v. 100% Stator Earth Fault
vi. Reverse Power
vii. Over Voltage
viii. Loss of Excitation
ix. Balance Voltage
x. Gen. Thermal Protection
29
Main-II (GRP-2) Protection comprising :
30
Single Line Diagram of Protection scheme of
Generator Unit
31
Single Line Diagram of Protection scheme of
Generator Unit
32
Trip Logic of Protection scheme of GRP-1 (Main-I)
33
LED Indications provided on GRP-1 (Main-I)
34
Details of LED Indications provided on GRP-1 (Main-I)
35
Trip Logic of Protection scheme of GRP-2 (Main-II)
36
LED Indications provided on GRP-2 (Main-II)
37
Details of LED Indications provided on GRP-2 (Main-II)
38
Unit Protection Settings
Sl.No LED
Protection Function Curve/Setting Time Delay
. No.
41
Bus-Bar Protection & Breaker
failure Protection :
Relay : Model-REB500, Make-ABB
43
Single Line Diagram of Protection scheme of Bus Bar
44
45
Bus-Coupler Protection
Relay : Model-SPAJ140C, Make-ABB
46
Single Line Diagram of Protection scheme of Bus Coupler
47
Trip Logic of Protection scheme of Bus Coupler
48
Transmission Line Protections
49
Single Line Diagram of Protection scheme of Transmission Lines
50
Trip Logic of Protection scheme of Transmission Lines
51
Setting Criterion of Line Protection:
1. Zone-1: 80% of Principal Line Section;
52
3. Zone-3: 1.2 x (100% of Principal Line
Section + 100% of the Adjoining
longest Line )
53
Shunt Reactor Protection
Relay : Model-REG316, Make-ABB
i. Differential Protection
ii. Restricted Earth Fault
iii. Back-up Impedance Protection,
iv. Winding Temperature High
v. Oil Temperature High
vi. Buchholz Gas Relay protection
vii. Pressure Relief Valve
54
Some Additional Features/ Schemes
Used in Protective Circuits:
55
3.Pole discrepancy scheme : In single
pole circuit breakers, If due to any
reason, one or two poles of the CB
trips, the remaining pole trips after a
short time delay. Normally it is of the
order of 0.8 to 1.0 sec. It may be with
CB schematic or outside.
4. Auto-reclosing Scheme: On tripping of
Line CB on Temporary line fault, the
scheme provides auto Reclosure of Line
CB after a pre-set short time delay.
56
The scheme may be single phase auto-
reclosing or three phase auto-reclosing
or both.
Normally single phase auto-reclosing
scheme are employed. Three phase
auto-reclosing scheme are best suited
for radial lines.
57
5. Carrier Inter-tripping Schemes :-
Normally 80% of Principal Line Section is
covered by Zone-1 of the Line
protection, the rest of the 20% is
covered by Zone-2 protection with a
minimum delay of 0.4 sec.
58
A. Permissive Under-reach carrier inter
tripping Scheme,
B. Permissive Over-reach carrier inter
tripping Scheme,
C. Carrier Blocking Scheme,
D. Carrier Acceleration Scheme
59
Testing of Protective
Relays schemes
&
Associated Equipments.
60
Testing of Current Transformers :
- Insulation Test
1. Primary winding to Earth by 5kV
megger
2. Secondary winding to Earth (For
each core) by 250V or 500 V megger,
3. Primary winding to all the secondary
winding by 5kV megger,
4. Core to core of secondary windings
by 250V or 500 V megger,
61
- Ratio Test of each core by Primary
injection,
- Polarity Test of cores,
- Magnetizing Characteristics or knee
point voltage test for identifying
metering/ Protection cores
62
Testing of Potential Transformers:
- Insulation Test
1. Primary winding to Earth by 5kV
megger after isolating from earth
2. Secondary winding to Earth (For
each core) by 250V or 500 V megger,
3. Primary winding to all the secondary
winding by 5kV megger,
4. Core to core of secondary windings
by 250V or 500 V megger,
63
- Ratio Test of each core by injecting
voltage on Primary terminal and
measuring voltages on secondary cores,
- Polarity Test of cores with reference to
Primary Terminal,
64
Primary Injection of CT,s:
65
- During Primary injection we have to
ensure that the current in metering circuit
is flowing from the metering core only and
current in protection circuit is flowing from
the protection core only otherwise the
protection is likely fail during fault
conditions.
66
Secondary Injection Of PT,s:
- Injection of Potential circuit is carried
out with the help of Secondary Injection
Test Kits or with the help of Single
phase variac, Rheostat etc. The voltage
is measured in all voltage circuits of all
the phases one by one to ensure that
during actual operation voltage will flow
in the correct phase only and not
otherwise,
67
Checking of DC Schemes:
69
Power System Simulator (DOBLE Test Kit)
70
Power System Simulator (DOBLE Test Kit)
71
72
Closing/ Opening operation of Circuit
Breakers:
73
Checking of Alarm & Indications:
- All the alarms & Indications are
actuated one by one and their
operation is checked/ ensured on the
panels.
Checking of Stability of Relays :
- Check for the stability of Differential
Relays, Restricted Earth Fault Relays,
Bus-bar protection Relays etc.
74
On load checking the system:
After the system is energized, the
following checks are required to be
carried out :-
- Checking of DC auxiliary supply at
various points in the panels,
- Checking of CT/ PT supplies to relays,
meters etc.,
- Checking of healthiness of relays
- Checking of proper operation of
voltmeter/ Ampere meter in all the
phases 75
- Operation of MW meter, PF meter,
Energy meter etc and their running in
proper direction,
- Trip circuit supervision in healthy state,
- Relays are measuring correct voltage &
currents as per load condition.
76
Testing Of Transformers
Following Tests are performed to Check
the healthiness of Transformers:-
1.Insulation Resistance- HV-E, LV-E, HV-
LV by 5KV/ 10KV Megger.
2. Turn ratio Test
3. Open circuit Test from HV & LV side,
4. Short Circuit Test from HV to LV,
5. Magnetic Balance Test from Star side
6. Checking proper operation of OLTC.
77
Testing Of Reactors:
Following Tests are performed to Check
the healthiness of Reactors:-
1. Insulation Resistance- HV-E by 5KV/
10KV Megger.
2. Open circuit Test from HV,
78
THANK YOU
79