Académique Documents
Professionnel Documents
Culture Documents
Management
Chapter 1
Attributes of a Project
• A non-routine endeavor with a limited life
• Objective: complete a series of
interdependent tasks:
– requiring coordinated effort
– within resource constraints
– within time constraints
– within budget constraints
– to the customer’s satisfaction
– in an environment of uncertainty & risk
Examples
• Consulting firms servicing a client
• Marketing campaigns
• Planning a wedding or hosting a big party
• Designing & implementing a new production
process
• Launching a new business
• Executing an environmental clean-up of a
contaminated site
• Performing a series of surgeries on an accident
victim
The Age of Project Management
Drivers of Change
• Scope
– Customer satisfaction
• Time
• Cost
– Other resources (labor, capacity, etc.)
Uncertainty & Risk
• Satisfied customers
• Additional business
• Expansion of career opportunities
• Satisfaction of being on a winning team
• Improved knowledge and skills
Integrated Management of Projects
- Execution of Strategy -
Capability Maturity Model (CMM)
-Project Mgt as a Core Competency -
Best Practice?
Alternative Frameworks
• Critical Path Method
– CPM
– PERT
– Critical Chain
• Waterfall
• Agile/Scrum
• Lean/Six Sigma
– DMAIC
– DFSS
… many others
Alignment of Projects with
Organization Strategy
Chapter 2
Strategic Management Process
Implementation Gap
• Classification of projects:
– Compliance & emergency (must do)
– Strategic
– Operational
Major Project Proposal
• Open door?
• Formal process:
– Problem definition
– Goal definition (faster, better, cheaper?)
– Financial (projected investment, savings, cash
flow, ..)
• Risk
Project Screening Process
Project Selection
• Develop a set of criteria against which
each opportunity will be evaluated
• List assumptions
• Gather data and information on each
proposed project
• Evaluate each proposal against the criteria
• Select the biggest bang for the buck
Nonnumeric Models
• The sacred cow
– Senior managers say so
• Operating necessity
– Immediate threat
• Competitive necessity
– Market driven
• Product line extensions
– Fill a gap
• Comparative benefit model
– United Way, peer review
Project Screening Matrix
Example: Driehaus Seminars
• Clear academic focus
• Nexus: country & focus
• Nexus: faculty & country/focus
• Geographic diverse portfolio of seminars
• Perceived student interest
• Past performance of faculty
• Novice faculty & nurturing ongoing relationship
• 12 month before return to same country
Numeric Models
• Payback period
– Cost/(annual revenue)
• Average rate of return
– (annual revenue)/ cost
• Net present value
– Discount cash flows using a hurdle rate
• Internal rate of return
– The discount rate that equates the cash inflows &
cash outflows
Payback Method
Investment
Payback Period
Annual Net Savings
Chapter 3
PM Structures
• Very flexible
• Low overhead
• Seek out low cost provider
• Seek out high expertise
• No termination issues
Network Disadvantages
• Coordination issues
• Building trust & learning to communicate
can be slow - misunderstandings
• Loss of control
• Must amend contracts for unforeseen
events (e.g.: change orders)
Organizational Culture
• Risk tolerance
• Reward seniority or performance
• Tolerance of conflict & criticism
• Means or ends orientation
• Internal or external orientation
Typical “Projectized” Culture
Mechanisms for Sustaining
Organizational Culture
Anthropology
Chapter 5
Why estimation is important
• Repetitive tasks:
– Multiply cost per unit?
– Learning curves?
• Templates:
– Based on past projects
– Adjust for scope changes, inflation, …
• Uncertainty of durations:
– Program Evaluation & Review Technique
• Excessive detail is costly:
– Fosters sub-optimization (“can’t see the forest
for the trees”)
– Creates unproductive bureaucracy
• Insufficient detail is costly:
– Lack of focus
– Wasted effort
Implications for
Knowledge Management
Developing Budgets
• Direct costs:
– From WBS analysis
• Direct Overhead Costs:
– Directly attributable to the project
• General Overhead Costs:
– Often a % of project costs
Time-Phase Costs = Budget
Chapter 6
Gantt Charts
• Precedence diagramming
• Critical path method (CPM)
• Program evaluation and review technique
(PERT)
• Graphical evaluation and review technique
(GERT)
Options
B 2 3
A C 1 4 5
D 6 7
Oops!
Preparing the Network Diagram
• Ask the following questions regarding
each activity:
– Which activities must be finished immediately
before this activity can be started?
– Which activities can be done concurrently with
this activity?
– Which activities cannot be started until this
activity is finished?
Preparing the Network Diagram
• Finish to Start:
– Most common
– Almost always the only one used
• Others (often using lags):
– Start to Start
– Finish to Finish
Example: Hammock Activity
CPM example:
D, 2
A, 2 B, 1 C, 1 F, 5 G, 1
E, 5
Concurrent Activities
Laddering
E, 5
Start time depends on when
predecessors finish
ES=4
EF=6
A, 2 B, 1 C, 1 F, 5 G, 1
ES=4
EF=9
E, 5
Duration = 15 weeks
Latest Start and Finish Times
• Latest finish time (LF) is the latest time an
activity must be finished in order for the entire
project to be completed by its completion time.
• Latest start time (LS) is the latest time an activity
must be started in order for the entire project to
be completed by its completion time.
• LS = LF – Duration Estimate
Backward Pass Rule
LS=4
LF=9
When do successor tasks need to
start?
Don’t delay the project!
ES=4
EF=6
LS=4
LF=9
Total Slack, Defined
LS=4
LF=9
Quick & dirty method:
D, 2
A, 2 B, 1 C, 1 F, 5 G, 1
ABCDFG 12
E, 5
ABCEFG 15
15 - 12 = 3
Computer Software
Uncertainty & Task Duration
to 4t m t p
te
6
• Expected error (the variance):
t p to
2
2
6
Path Probabilities
• However, the probability distribution of any given
path is a normal probability distribution:
– Based on sampling from multiple distributions & the
Central Limit Theorem
• We estimate the path variance by summing the
variances of the individual activities:
– Again, this is statistically questionable, but seems to
work in practice
Bell-Shaped Curves
Example
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Immediate Expected
Expected Task
A
Predecesors
None
Time
7
Times B
C
None
A
5.333
14
D A 5
E C 11
F D 7
G B 11
H E,F 4
a 4m b I G,H 18
te
6
Duration = 54 Days
C, 14 E, 11
A, 7 H, 4
D, 5 F, 7
I, 18
B G, 11
5.3
ACEHI 54
ADFHI 41
BGI 34.3
Calculating Probability
TS - TE
Z=
2
te
99.7%
TE
t
=54 TS=55
TS - TE
Z=
2
te
ba
2
2
6
Task Optimistic Most Likely Pessimistic Variance
A 3 6 15 4
B 2 4 14
C 6 12 30 16
D 2 5 8
E 5 11 17 4
F 3 6 15
G 3 9 27
H 1 4 7 1
I 4 19 28 16
2
(sum the variance along the critical path) te
= 41
TE = 54
TS=55 time
TS - TE 55 - 54
Z= = = .156
2
te
41
t
TE = 54 TS=56
TS - TE 56 - 54
Z= = = .313
te
2
41
Solution (continued)
TS - TE TS - 54
= =Z
te
2
41
Find Z, then D
TS - 54
= - 0.67
41
Solution
TS - 54
= - 0.67
41
TS - 54 6.4(- 0.67)
TS 54 - 4.3
TS 49.7
• A contract giving you a bonus for completion
within 50 days would give you a little more than
25% chance of receiving the bonus.
CPM & PERT assumptions
• Project activities can be identified (there is
a clear beginning and ending point for
each activity.)
• Sequence (predecessor-successor)
relationships can be specified
• Project control should focus on the critical
path (beware of “near” critical paths).
Additional PERT assumptions
C, 14 E, 11
A, 7 H, 4
D, 5 F, 7
B
G, 11 ACEHI 54
5.3
ADFHI 41
BGI 34.3
Managing Risk
Risk
Doing Business in the USA 2018
Project Risk
• A potential threat that might negatively impact
the project’s objectives:
– Timescale
– Cost
– Quality
– Scope
• Flipside: an opportunity
No Risk, No Reward
Typical Risk Categories
• Scope creep:
– Unstable requirements
• Technical risks:
– Unproven technology
• Schedule risks:
– Delays, acts of God, poor estimation
• Financial risks:
– Increasing costs & pulled funding
Guidelines for Managing Risk
• Risk management starts when the project
starts
• Dual goals:
– Reduce the likelihood of threats
– Increase the likelihood of opportunities
• Focus on the big ones, but don’t forget the
others (Pareto 80:20 rule)
• Develop contingency plans
The Risk Management Process
• Identify
• Assess
• Anticipate:
– Avoid/reduce
during planning
– Contingency plan
• Trip wire
• Responsibility
• Respond
Caveats
• Most people are naturally optimistic
• Risk cannot be eliminated:
– Risk management is not infallible
– Driving risk underground is dangerous
• Risk is part of the project’s scope:
– Sponsor should have full knowledge & accept the
potential consequences
• Likelihood of risks & opportunities generally
declines as the project is executed
– Highest likelihood is at the start!
Risk Event Graph
Options
• Prevention
• Mitigation (reduce likelihood or severity)
• Transfer to third party (insurance)
• Pursue alternate path (decision tree)
• Share the risk
• Acceptance
Generic Alternatives
• More detailed planning & analysis
• Select alternative approaches
• Adopt enhanced design
• Procedural changes
• Require permits & specific authorization
• Add protection & safety systems
• Preventative maintenance
• Separate or relocate tasks or resources
• Operational reviews
• Regular inspection & compliance audits
• Training & skill enhancement
• Implement formal processes & quality assurance procedures
• Install structural barriers
• Negotiate contract terms & conditions
• Adopt crisis management & disaster recovery plans
Pre-Planning Risk Management
• Use project team to brainstorm:
– Risks under the control of the team:
• poorly defined scope, competency, technical issues,…
– Risks outside the team’s direct control:
• Competitors’ acts, economic climate, regulatory changes, …
• Estimate the likelihood of each & likely severity:
– High, Medium, Low?
– Exponential sequence (2, 4, 9, 16, 25, …)
– Fibonacci sequence (0, 1, 1, 2, 3, 5, 8, 13, 21, 34, …)
Risk Assessment
Risk Severity Matrix
Pre-Planning Exercise
• Uncritical brainstorming
– Capture on Post-It Notes & display
• Cluster similar items
• Rationalize the clusters
• Evaluate:
– Likelihood & severity of each risk
– Are any themes developing?
– Is a particular aspect of the project troublesome?
• Consider options & develop contingency plan
• Assign responsibility for each risk
Response Plan
Analogy: Failure Mode Effect Analysis
Additional Considerations
• If risk is from insufficient information, build
investigative action into the project plan:
– Market analysis, proof of concept, prototypes, pilot
projects
• Bring risky activities forward in the schedule:
– Easier to pull the plug or catch up lost ground
• Modify the project scope to reduce of eliminate
risk:
– Low tech, proven solutions
Formal Contingencies
• Budget reserves
• Management reserves
• Time buffers
Other Exercises
• Brainstorm using the work breakdown structure:
– Evaluate the potential risks & opportunities relevant to
each work package
• Sensitivity analysis:
– Identify assumptions (customer demand, usage,
repeat purchases, plant efficiency, inflation, operating
costs, timing, …)
– Rework the business model with a range of optimistic,
most likely & pessimistic estimates
– Identify the assumptions that have the most impact
Other Exercises
• Scenario analysis:
– Many times assumptions are linked (e.g.:
sales & cost of goods sold)
– Investigate optimistic, most likely &
pessimistic scenarios
• Monte Carlo simulations
• Decision trees
Track Changes
Systematic Control
Chapter 15
Environmental Factors
Legal & Political
• Political stability
• Bureaucracy & regulation
• Labor unrest
• Repatriation of capital
• Equal treatment for domestic & foreign
firms
• Currency Fluctuations
Site Selection Evaluation
Security
Physical & Business Interests
• Terrorism
• Crime
• Corruption
• Agent self-dealing
• Proprietary information
• Trade secrets (including business methods)
• Privacy regulations
Geography
Source:
World Shipping Council
2014
Infrastructure
Yangshan Deep Water Port
One Road One Belt
Infrastructure Evaluation
Cultural Differences
• Customs & language:
– Translators & guides?
• Values & personal philosophies
– Religious sensibilities
– Value of time
– Attitude toward social networks
• Universalism:
– USA most “universalist” society
Examples
• Business etiquette
• Time orientation (e.g.: deadlines, NPV)
• Guanxi
• Wasta
• Saving face
Cultural References
• Power Distance:
– Attitude toward power inequality
• Individualism:
– Self image as “I” or “we”
• Masculinity:
– Motivated by competition or
collaboration
Hofstede’s Dimensions
• Uncertainty Avoidance:
– Attitude toward ambiguity & risk
• Long Term Orientation:
– Attitude toward “time-honored” traditions
• Indulgence:
– Control over desires & impulses
NAFTA
Asia
Europe
South America
Cross-Regional
Expatriate Managers
Burn out
Cultural Training
• Work through case studies
• Communication skills:
– Repeat instructions in another medium
• Greeting protocols:
– Business cards & handshakes
– Small talk versus business first
• Business dining protocols:
– Cleaning your plate?
– Utensils & which hand to use
Leading with Limited Experience