Terminal Building SUBGRADE COMPACTING
No
Q
Yes
EMBANKMENT
No
Q
Yes
LEAN CONCRETE
No
Q
Yes
INSTALL REBAR
No
Q
Yes
FORMWORK
No
GSE Building Q
Yes
CONCRETING
No
Q
Yes
REMOVE FORMWORK
No
Yes
Q
EMBANKMENT WITH
COMPACTING
FINISH
Spirit of Innovation
Animal Cargo Building
Quarantine Building
Spirit of Innovation
RFFS Building
MPH Building
Spirit of Innovation
Terminal Building
Note:
Start of Work
Finish of Work
Note:
Start of Work
Finish of Work
Direction of Work
Spirit of Innovation
Animal Cargo
Note:
Start of Work
Finish of Work
Direction of Work
Quarantine
Note:
Start of Work
Finish of Work
Direction of Work
Spirit of Innovation
Main Power House
Note:
Start of Work
Finish of Work
Direction of Work
RFFS
Note:
Start of Work
Finish of Work
Direction of Work
Spirit of Innovation
METHOD
Equipments
• Bulldozer : 1 unit
• Excavator : 2 unit
• Dump Truck : 4 unit
• Screen : 2 unit
• Motor Grader : 1 unit
• Vibro Roller : 2 unit
• Water Tank : 2 unit
Resources
• Operator :2
• Driver :4
• Surveyor :1
• Asisstant Surveyor :1
• Helper :2
• Supervisor :1
• Safety Officer :1
1) Excavation
Excavation work using excavator and dump truck. The excavation shall be
carried out in accordance with the drawings and to the slopes, levels,
depths, widths and to heights shown thereon.
Excavator
Spirit of Innovation
METHOD
2) Embankment
Compacting the layer with vibro roller with a several passes (number of
passes depend on the trial test) then followed by watering with a water
tank. After compaction work, the surveyor will check the thickness of layer.
The layer density field tested and witnessed by consultant. If it takes the
requirement, the work continue to the next step.
Spirit of Innovation
METHOD
3) Lean Concrete
After the work has been selected in the compact embankment and
according with the drawing, next is lean concrete work
4) Install Rebar
After the lean concrete got harden, we will install the rebar according
working drawings.
Spirit of Innovation
METHOD
5) Formwork
After the rebar have installed, we will instal the foot plat formwork
6) Concreting
After the formwork installed, then we will do the foot plat foundation
concrete casting using concrete K=350 Kg/cm² quality.
Spirit of Innovation
METHOD
7) Remove Formwork
After the concrete ages have reach 24 hours, we will remove the
formwork.
Fill the excavated foundation pit with the dumped gradation, and then
finishing with compact