SITE MANAGEMENT AND WORK AREA

Location of the work include Terminal Flowchart illustration


Building, Ground Service Equiptment, START
Animal Cargo, Quarantine Building, Fire
Rescue Building, and Main Power House EXCAVATION
No

Q
Yes
Terminal Building SUBGRADE COMPACTING
No
Q
Yes

EMBANKMENT
No
Q
Yes
LEAN CONCRETE
No
Q
Yes

INSTALL REBAR
No
Q
Yes

FORMWORK
No
GSE Building Q
Yes

CONCRETING
No
Q
Yes

REMOVE FORMWORK
No

Yes
Q
EMBANKMENT WITH
COMPACTING

FINISH

Spirit of Innovation
Animal Cargo Building

Quarantine Building

Spirit of Innovation
RFFS Building

MPH Building

Spirit of Innovation
Terminal Building

SQUANCE 01 SQUANCE 03 SQUANCE 02

Note:
Start of Work
Finish of Work

Ground Service Area

Note:
Start of Work
Finish of Work
Direction of Work

Spirit of Innovation
Animal Cargo

Note:
Start of Work
Finish of Work
Direction of Work

Quarantine

Note:
Start of Work
Finish of Work
Direction of Work

Spirit of Innovation
Main Power House

Note:
Start of Work
Finish of Work
Direction of Work

RFFS

Note:
Start of Work
Finish of Work
Direction of Work

Spirit of Innovation
METHOD
Equipments
• Bulldozer : 1 unit
• Excavator : 2 unit
• Dump Truck : 4 unit
• Screen : 2 unit
• Motor Grader : 1 unit
• Vibro Roller : 2 unit
• Water Tank : 2 unit

Resources
• Operator :2
• Driver :4
• Surveyor :1
• Asisstant Surveyor :1
• Helper :2
• Supervisor :1
• Safety Officer :1

1) Excavation
Excavation work using excavator and dump truck. The excavation shall be
carried out in accordance with the drawings and to the slopes, levels,
depths, widths and to heights shown thereon.

Excavator

Spirit of Innovation
METHOD

2) Embankment

The embankment will excecute on 1 layer with maks 20 cm thickness of


gradatio 100mm and 150mm. To obtain the elevation plan of selected
embankment using a motor grader. The material will be spreaded and
levelled by motor grader until we get the thickness plan of layer in loose
soil. As mentioned in spesification, The materials shall be laid in layers not
greater than 250 mm loose depth. But it may be changed by considering
of compaction trials result.

Compacting the layer with vibro roller with a several passes (number of
passes depend on the trial test) then followed by watering with a water
tank. After compaction work, the surveyor will check the thickness of layer.

The layer density field tested and witnessed by consultant. If it takes the
requirement, the work continue to the next step.

Spirit of Innovation
METHOD

3) Lean Concrete
After the work has been selected in the compact embankment and
according with the drawing, next is lean concrete work

4) Install Rebar

After the lean concrete got harden, we will install the rebar according
working drawings.

Spirit of Innovation
METHOD

5) Formwork
After the rebar have installed, we will instal the foot plat formwork

6) Concreting

After the formwork installed, then we will do the foot plat foundation
concrete casting using concrete K=350 Kg/cm² quality.

Spirit of Innovation
METHOD

7) Remove Formwork
After the concrete ages have reach 24 hours, we will remove the
formwork.

8) Embankment with Compacting

Fill the excavated foundation pit with the dumped gradation, and then
finishing with compact

Spirit of Innovation
SAFETY AND ENVIRONMENT

1. Each personnel using general safety equipment's (mask,


glasses, safety boot, gloves, etc.)
2. Provide flagman to control traffic circulation
3. Provide warning sign
4. Provide working border area
5. Periodic safety patrol control
6. Tool box meeting before and after work
7. Provide safety officer

Standart safety equipments :