a. Add the dummy activities that will eliminate the problem of
activities having the same starting and ending nodes.
1
Network exercise (P2)
b. Add dummy activities that will satisfy the following
immediate predecessor requirements:
Immediate
Activity Predecessor
H B, C
I B, C
G D, E
2
Network exercise with time (P4)
Construct a PERT/CPM network for a project with the
following activities and times:
Activity Immediate Time
Predecessor (months)
A - 4
B - 6
C A 2
D A 6
E C, B 3
F C, B 3
G D, E 5
a) Find the critical path for this project network.
b) This project must be complete in 1 1/2 years; do you
anticipate difficulty in meeting the deadline? Explain.
3
Consider the following network (P6)
(times are in weeks)
2 C 5
7
A F
D H
5 3
6 8
1 G
4 6
B 10
E
3
3 7