Network exercise (P2)

Consider the PERT/CPM network shown below.

2 D 3
A
E F
B
1 4 G 6 J 7
H
C
I
5
a. Add the dummy activities that will eliminate the problem of
activities having the same starting and ending nodes.
1
Network exercise (P2)
b. Add dummy activities that will satisfy the following
immediate predecessor requirements:

Immediate
Activity Predecessor
H B, C
I B, C
G D, E

2
Network exercise with time (P4)
Construct a PERT/CPM network for a project with the
following activities and times:
Activity Immediate Time
Predecessor (months)
A - 4
B - 6
C A 2
D A 6
E C, B 3
F C, B 3
G D, E 5
a) Find the critical path for this project network.
b) This project must be complete in 1 1/2 years; do you
anticipate difficulty in meeting the deadline? Explain.
3
Consider the following network (P6)
(times are in weeks)

2 C 5
7
A F
D H
5 3
6 8
1 G
4 6
B 10
E
3
3 7

a. Identify the critical path.


b. How long will it take to complete this project?
c. Can activity D be delayed without delaying the entire project?
How about activity C? If so, how many weeks?
d. What is the schedule for activity E?
4
Network exercise with time (P7)
A project involving the installation of a computer system consists
of eight activities. The immediate predecessor and activity time in
weeks are shown below:
Activity Immediate Time
Predecessor (weeks)
A - 3
B - 6
C A 2
D B,C 5
E D 4
F E 3
G B,C 9
H F,G 3
a. Draw the PERT/CPM network for this project.
b. What are the critical path activities?
c. What is the expected project completion time?