Académique Documents
Professionnel Documents
Culture Documents
MANAGEMENT PHASES
1
CHAPTER 8
PHASE II:
PLANNING THE PROJECT- PART 4
PROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT
2
Consensus Method – This method uses the pooled experience of senior or middle
managers to estimate total project duration and cost. This typically involves a meeting
where experts discuss, argue and ultimately reach a consensus as to their best
guesstimate.
Ratio Method – These are surrogates which are used to estimate project costs and
times. Examples: Number of square meters x cost per square meter = project cost of
building a factory warehouse; cost of a thermal power generating station = power
generating capacity (in MW) x average industry cost per 1 MW power generation
Apportion Method – Extension of the Ratio Method. Money is
“Apportioned” out for segments of project work on the basis of historical
7
project-related data. Example: The design phase of an aircraft prototype is
apportioned 40% of total project cost, the production and testing phase 45%,
and the marketing phase 15%.
Work Packages – Considered the most reliable project cost and time
estimating method. Work Package Mangers provide the requisite
information. In case there is uncertainty with regard to expectation of times
involved in completing a work package or activity, varying estimates can be
taken and then averaged out.
9
A HYBRID: PHASE ESTIMATING
10
Phase Estimating is a cost estimating technique that utilizes both the macro
and micro approaches. This technique is used especially when the project in
question is characterized by an especially high level of uncertainty and
estimating costs and times becomes very difficult
In Phase Estimating, initially a macro estimate for the project is made and
this estimate is subsequently refined as the project phases are implemented.
Typical projects in which Phase Estimating is used are in the aerospace
industry, IT projects, new technology products and some construction
projects.
MACRO ESTIMATE
11
DETAILED ESTIMATE
14
EVM Formulas
If CPI =1:the planned and actual costs are the same; <1: over budget;
>1: under budget
If SPI =1: on schedule; <1 behind schedule; >1 ahead of schedule
15