Changing of Bogie Bolster

Spring in the Washing Pit Line


Stepwise activities
1. Putting wooden wedge both side of the wheel.
(Time consumption: negligible)
Stepwise activities
2. Isolate the Trolley and release the coach
manually. (Time consumption: negligible)
Stepwise activities
3A. Open the Nut – bolt of shock absorber.
(Time consumption: 02 minutes)
Stepwise activities
3B. Remove the shock absorber from bolts.
(Time consumption: 02 minutes)
Stepwise activities
4. Open the safety strap of equalizing stay. (Time
consumption: 02 minutes)

5. Open Safety strap of Bolster. (Time consumption :


02 Minutes)
Stepwise activities
6. Open any Pin of Equalizing stay of affected side with the
help of special gadget of Equalizing stay and remove Eq.
Stay from one side. (Time Consumption: 05 minutes)
Stepwise activities
7. Place the “C” shaped special gadget between Bolster lug
and bogie frame. (Time Consumption: 02 minutes)
Stepwise activities
8. Place the small jack below lower spring beam and lift to
free the BSS hangers. (Time Consumption: 05 minutes)
Stepwise activities
9. Place the special gadget for lifting and lowering the spring beam
between bogie frame and Lower spring beam and remove the
small jack by lowering. (Time Consumption: 03 minutes)
Stepwise activities
10. Lower the spring beam from one side with the help
of gadget. (Time Consumption: 03 minutes)
Stepwise activities
11. Remove the spring from its seat. (Time
Consumption: 02 minutes)
Stepwise activities
12. Place the New spring on the seat. (Time
Consumption: 02 minutes)
Stepwise activities
13. Lift the spring beam with the help of gadget. Place small jack
below the spring beam. (Time Consumption: 05 minutes)
Stepwise activities
14. Lift the small jack. Make the spring beam gadget free to be
removed. Place the BSS hangers at its position. (Time
Consumption: 05 minutes)
Stepwise activities
15. . Remove the “C” shape special gadget. Fit the BSS hanger
properly. Remove the small Jack. (Time Consumption: 03
minutes)
Stepwise activities
16. Fit the Bolster Safety Strap. (Time
Consumption: 02 Minutes)
17. Place special gadget of Eq. Stay. Fit the
Equalizing Stay. (Time Consumption: 05
Minutes)
18. Fit the safety strap of Eq. Stay (Time
Consumption: 02 Minutes)
19. Fit the shock absorber. (Time Consumption: 02
Minutes)
20. Remove the wooden wedges from the wheel
and reset the isolating cock in its original
position.
Total time consumption for changing
Bogie Bolster spring after reaching on
site:

Approx.
60 Minutes
Tools used for changing Bolster spring.
Bolster Spring change in last one year
(Sep-10 to Aug-11)
• Sep-10 - 04 • May-11 – 01
• Oct-10 – 05 • June-11 – 02
• Nov-10 – 04 • July-11 – 01
• Dec-10 – 03 • Aug-11 – 01
• Jan-11 – 06 • Total – 31
• Feb-11 – 02
• All the springs
• Mar-11 – 01
• Apr-11 – 01
changed in pit
line.
Changing of Dashpot Spring
in the Washing Pit Line
Stepwise activities
1. Putting wooden wedge both side of the wheel.
(Time consumption: negligible)
Stepwise activities
2. Isolate the Trolley and release the coach
manually. (Time consumption: negligible)
3. Open the Dashpot safety strap of
affected wheel completely and make
adjacent wheel free from safety strap.
(Time consumption: 04 Minutes)
4.Place the jack between Dashpot and
bolster below trolley frame and lift the
trolley. (Time consumption: 07 Minutes)
5. After lifting remove the broken spring and Place
the new spring. (Time consumption: 05 Minutes)
6. Lower the Trolley frame by lowering the
Jack. (Time consumption: 04 Minutes)
7. Check the both spring height to ensure
proper setting of spring. (Time
consumption: 01 Minutes)
8.Remove the jack and fit the safety
straps. (Time consumption: 05 Minutes)

9. Remove the wooden wedges from the


wheel and reset the isolating cock in its
original position. (Time consumption:
Negligible)
Total time consumption for changing
Dashpot spring after reaching on site:

Approx.
30 Minutes
Dashpot Spring change in last one year
(Sep-10 to Aug-11)
• Sep-10 - 01 • May-11 – 00
• Oct-10 – 04 • June-11 – 00
• Nov-10 – 03 • July-11 – 01
• Dec-10 – 02 • Aug-11 – 00
• Jan-11 – 00 • Total – 14
• Feb-11 – 00
• All the springs
• Mar-11 – 01
• Apr-11 – 03
changed in pit
line.
Tools used to
change the
Dashpot Spring.
Helping Hands
Thanks