Many people appreciate and understand the delicate balance between the natural &
man-made home. A daring temple of a house in inescapably powerful, savage and
mesmerizing landscape holding little appeal to the faint hearted. Dry, rocky exposed
to forced winds, this is a challenging, risky, yet breath takingly rewarding landscape
and structure in many way. This is designed for a person or people seeking for a
private retreat from their public lives, the building is cleverly sited to be almost
“invisible” upon approach tucked under a ridge for protection from strong winds
and summer without harming the nature. Materials throughout have been carefully
selected to enhance the sense of place and belonging with necessary distractions.
Overall, a building neither dwarfed by, nor in competition with setting, simply
belonging with a respect, authenticity, ease and rawness in keeping with rural
Philippines.
The research intends to offer solution to the following problems:
1. Provision of the facilities for transaction of business, for meeting and conference, for
recreation and entertainment.
2. As an important employer of labour
3. Development of local economy of the area it is located due to being an attraction for
visitors
The scope of this research is to focus on the main problematic aspects Guest House
design. These are:
In India, a tremendous growth can be seen in the guest house business especially in
Delhi-NCR (national capital region) where progress in IT sector and Commonwealth
Games 2010 were two most influential factor. Nowadays guest house accommodation
sector has improved itself a lot. Even a home converted guest house is also offering 3
stars equivalent facilities to its guests.
Personnel No. Of Personnel Salary/Day
Contractor 1 Contractual
Equipment Operators 3
Electricians 1
Plumber 1
Mechanical 1
Work Schedule Work To Be Done Responsibility Percentage Of June 26 Concrete Casting of Construction 18%
Worker,
Work ground beams, Backfilling Construction
Supervisor/
June 3 - 14 Permit Construction 3% & Compaction of Construction
Supervisor/ Manager,
Construction Subgrade soil in layers of
Manager, Architect
300mm to 95%
Architect
June 15 - 17 Break Ground and Construction 5% June 27 - 28 Ground Floor Slab – Mesh Construction 23%
Worker, Worker,
Excavation Construction
y6@250mm c/c Construction
Supervisor/ Supervisor/
Reinforcements Construction
Construction
Manager, Manager,
Architect Architect
Civil
Civil
Engineer
Engineer
June 29 Casting of Ground Floor Construction 25%
June 18 - 20 Footing Reinforcements, Construction 10%
Worker,
Worker, Slab – 100mm Construction
Starter Column Construction
Supervisor/
Supervisor/
Reinforcements, Concrete Construction
Construction
Manager,
Manager,
Casting of the Footing
Architect
Architect
July 1 - 2 Column Reinforcements Construction 28%
Civil
Worker,
Engineer 8y12 Construction
June 21 - 22 Reinforcement of the Construction 13%
Supervisor/
Worker, Construction
ground beams Construction Manager,
Supervisor/
Construction Architect
Manager, Civil
Engineer
Architect July 3 - 4 Column Form Works, Construction 30%
Civil Worker,
Engineer Column Concrete Casting Construction
June 24 - 25 Sewer, Electrical, Water Construction 15% Supervisor/
Worker, 300mm x 300mm (2/3 of Construction
(Utilities) Construction Manager,
Supervisor/ Column Height)
Construction
July 5 - 6 Laying of 200mm Construction 35% July 23 Installation of Doors and Construction 60%
Worker, Worker,
Concrete Blocks, Doors Construction Windows Construction
Supervisor/ Supervisor/
and Windows Framing Construction Construction
Manager, Manager,
Architect Architect
July 8 - 9 Roof Beam Construction 38% July 24 Wall Finishing Construction 70%
Worker, Worker,
Reinforcement 6y12, Construction Construction
Supervisor/ Supervisor/
Beam Form Works Construction Construction
Manager, Manager,
Architect Architect
July 10 Concrete Casting of Construction 40% July 24 - 25 Cabinets, Shelving Construction 80%
Worker, Worker,
Roof Beams 350mm x Construction Construction
Supervisor/ Supervisor/
200mm and 1/3 of Construction Construction
Manager, Manager,
Column height
Architect Architect
July 11 - 13 Roof Framing Construction 43% July 26 Finish Plumbing Construction 85%
Worker, Worker,
Construction Construction
Supervisor/ Supervisor/
Construction Construction
Manager, Manager,
Architect Architect
July 15 - 18 Installation of Insulation Construction 45% July 26 - 27 Finish Electrical and Construction 90%
Worker, Worker,
and Roofing Construction Lighting Construction
Supervisor/ Supervisor/
Construction Construction
Manager, Manager,
Architect Architect
July 19 - 20 Wall Plastering Construction 48% July 29 Certificate of Construction 95%
Worker, Supervisor/
Construction Occupancy Construction
Supervisor/ Manager
Construction
July 5 - 6 Laying of 200mm Construction 35% July 22 - 23 Flooring, Tiling Construction 50%
Worker, Worker,
Concrete Blocks, Doors Construction Construction
Supervisor/ Supervisor/
and Windows Framing Construction Construction
Manager, Manager,
Architect Architect
July 8 - 9 Roof Beam Reinforcement Construction 38% July 23 Installation of Doors and Construction 60%
Worker, Worker,
6y12, Beam Form Works Construction Windows Construction
Supervisor/ Supervisor/
Construction Construction
Manager, Manager,
Architect Architect
July 10 Concrete Casting of Roof Construction 40% July 24 Wall Finishing Construction 70%
Worker, Worker,
Beams 350mm x 200mm Construction Construction
Supervisor/ Supervisor/
and 1/3 of Column height Construction Construction
Manager, Manager,
Architect Architect
July 11 - 13 Roof Framing Construction 43% July 24 - 25 Cabinets, Shelving Construction 80%
Worker, Worker,
Construction Construction
Supervisor/ Supervisor/
Construction Construction
Manager, Manager,
Architect Architect
July 15 - 18 Installation of Insulation Construction 45% July 26 Finish Plumbing Construction 85%
Worker, Worker,
and Roofing Construction Construction
Supervisor/ Supervisor/
Construction Construction
Manager, Manager,
Architect Architect
July 19 - 20 Wall Plastering Construction 48% July 26 - 27 Finish Electrical and Construction 90%
Worker, Worker,
Construction Lighting Construction
Supervisor/ Supervisor/
Construction Construction
A. FLOOR FINISHES
a. Living, Dining, Kitchen Area 300mm x 300mm Floor tiles
b. Toilets and Bath 300mm x 300mm Floor tiles
c. All Bedrooms 300mm x 300mm Floor tiles
d. Master's Bedroom/Stairs Floor planks (Owner supplied)
e. Foyer/Porch Area 300mm x 300mm Floor tiles
B. WALL FINISHES
a. Exterior Walls 6” CHB Plaster & Painted Finish with plaster mouldings on
appropriate location
b. Exterior Walls on window openings With concrete ledge (where appropriate)
c. Interior Walls on T&B enclosures 4” CHB Plaster & Painted Finish
c. Toilets and Bath 6 layers of 300mm x 300mm
C. CEILING FINISHES
a. Exterior Eaves ¼” thk. Flexboard (painted) on
aluminum T-runner Eaves Vent (slats) shall be
made of 1” x1” wood with screen
a. Earthfill All floor area shall be earth-filled (compacted) to the approved structure level
CONCRETE
REINFORCEMENTS
a. Cabinets, Closets & 1/2” thk. Marine plywood with wood edging &
Cupboards effective framing when needed. Handles, catches & locks shall be of approved type.