Atmospheric Pressure
• Minimum pressure: 740mm(Hg)
Humidity
Average annual relative humidity: 80%
Average monthly humidity (maximum): 87%
Average monthly humidity (minimum): 65%
Design Basis
HVAC Condition
• Limestone
• Correcting Materials(Sand,Clay,Bauxite,Laterite)
C3A (3CaO.Al2O3) 10
Dry Process
80% of world production is obtained by dry process
4.Separating 4.Packaging
Process Block Diagram (PBD)
PROCESS FLOW DIAGRAM
Process Description
Unit Input Output
Grinding Mill Raw Mixture, 19385 t/day Preheater feed, 19288 t/day
Loss in ESP(.5%), 97 t/day
Preheater Preheater feed , 19288 t/day Kiln feed( 600°C), 19288 t/day
Coal+ Air Exhaust Gas
Process Description
Unit Input Output