Vous êtes sur la page 1sur 16

INDIAN INSTITUTE OF TECHNOLOGY ROORKEE

Hydrological and Hydrodynamic Modelling


for Flood Damage Mitigation in
Budhabalang River Basin, Odisha

Under The Guidance of :-


Dr. S.K.MISHRA, Prof. & Head
Presented by :-
Dept of WRDM & RANJIT KUMAR PANI
Dr. R.D.SINGH, Enroll. No.- 17548027
Visiting Prof. & Former Director, NIH MTech - 2nd Year
OBJECTIVES OF STUDY

• Application of an Event Based Hydrological Rainfall–Runoff


Simulation Model using HEC-HMS for the Budhabalang river
basin and validate at Govindpur outlet.

• Assessment of Design Floods with Different Return Periods at


Govindpur gauging site using Flood Frequency Analysis.

• Real Time Flood Forecasting at Govindpur site.

• Computation of water surface profile in the downstream to


Govindpur site using Unsteady Flow Analysis in HEC-RAS
Platform.

• Development of Flood Inundation Map in the flood plain area for


100-year return period using the output of HEC-RAS.

2
RESEARCH GAP / RATIONALE

• Event based rainfall-runoff modelling for the estimation of


design floods for Budhabalang basin up to Govindpur Site,
Odisha has not been attempted so far.
• HEC-HMS together with HEC-RAS has not been applied
for flood management in Budhabalang Basin.
• Real-time flood forecasting has not been carried out using
the event based rainfall-runoff models for Budhabalang
river at Govindpur Gauging site.
• Flood plain mapping has not been carried out for different
return periods in the downstream of Govindpur gauging
site of Budhabalang river.

3
FLOW DIAGRAM FOR HEC-HMS PROCESS -
DIGITAL TERRAIN PRE-
BASE FLOW
ELEVATION PROCESSING
MODEL (DEM) IN ArcGIS
HEC-GeoHMS INITIAL LOSS
OBSERVED
HOURLY RAIN BASIN
FALL DATA PARAMETERS
HEC -
COMPUTED HMS ROUTING
HOURLY
FLOW DATA TRANSFORMATION

SIMULATED DISCHARGE
AND FLOW HYDROGRAPH

OBSERVED COMPARISON WITH No


DATA OBSERVED VALUES
Yes
CALIBRATION PARAMETERS

MODEL VALIDATION

ACCEPTANCE AND RESULT, TAKEN AS INPUT Cntd.


FOR HYDRODYNAMIC MODELLING
4
FLOW DIAGRAM FOR HEC-RAS PROCESS

START A NEW
HEC-RAS MODELLING
PROJECT

RIVER SCHEMATIC PLAN BY DEM DOWNLOADED AND


RAS MAPPER PROCESSED IN ARC-GIS

RIVER CHARACTERISTICS,
ENTERING
CROSS SECTION & MANNING’S
GEOMETRIC DATA
OBSERVED FLOW ‘n’ VALUE
DATA AS
UP-STREAM UNSTEADY FLOW SIMULATION
BOUNDARY
CONDITION WATER SURFACE PROFILE & FLOW AT
DOWNSTREAM

OBSERVED WATER LEVEL AT NO


COMPARISION
DOWNSTREAM SECTION
YES
CALIBRATION AND FLOOD INUNDATION MAPPING
VALIDATION FOR Oct-2013 (A) FLOOD

SIMULATED FLOW DATA


WATER SURFCE PROFILE & SATELLITE IMAGE OF Oct-
WITH 100 YEAR RETURN
FLOOD INUNDATION MAPPING 2013 (A) FLOOD MAP
PERIOD

FOR STRUCTURAL & NON-STRUCTURAL


PROTECTION MEASURES

5
Works Completed and progress of work
Event based Rainfall-runoff Modelling Real time flood forecasting
Acquisition of Spatial, Meteorological and
Hydrological data Real time flood forecast and forecasting
of water levels in real time
Spatial data processing:- Basin map &
drainage network, DEM model, Thiessen Comparison of observed and
Polygon map computation, LULC and soil forecasted flood hydrograph
Mapping, Isochronal map and time-area
relationship graph Hydraulic modelling
Temporal data processing:- Identification of Geometric Data preparation by
major floods, Rainfall data processing, Stream
RAS-Mapper
flow data processing
Unsteady flow analysis and calibration
Sensitivity analysis, Calibration and using hourly stage and discharge data
validation of Clark, Snyder & SCS transform
models of HEC-HMS and selection of best Development of Inundation Map
transform model.
Generation of flood inundation map for
Design flood Assessment an observed flood event
Estimation of design rainfall hyetographs for Generation of flood inundation map for
100-year return period and computation of 100-years return period flood
100-year flood using Clark Model
Computation of 100-year flood using flood Writing of Dissertation Report
frequency analysis of annual peak flood series
6
Obtained /Expected Results
Rainfall-runoff Model Real time Flood
Generation Forecasting
Calibrated results of five events based on Flood Forecasting based on four hours rainfall
Clark, SCS and Snyder’s transformation and block periods for event Oct-2013(A) obtained
validating the representative parameters with and it closely matches with observed flood
two events. hydrograph
Hydrodynamic
Compared the results of three transformation model Generation
models. Clark’s model is found to be most
suitable (Tc = 29 hours, R = 47 hours) Manning’s n values calibrated as 0.028
for main channel and 0.036 for banks
for the hydraulic model of the river.

Assessment of Design Flood Development of Flood Inundation Map

100-years flood based on rainfall frequency Inundation map with simulated flood
analysis with single and double bell storm hydrograph for event Oct-2013 (A) obtained.
patterns obtained as 4236.18 and 4194.93 cumec. Closely matches with the inundation map
Flood based on frequency analysis of annual created by Disaster Management Support
flood peaks came to 3522.41 cumec Service available on BHUVAN web site.

7
Remaining Work

To be
To be
Sl No Remaining Work Status submitted to
completed
supervisor

Flood inundation map


10th April
1 generation for flood with Under progress 15th April 2019
2019
100-years return period

Writing of Dissertation 20th April


2 Under Progress 25th April 2019
Report 2019

8
THANK YOU

9
Sensitivity Analysis of UH Models

Sensitivity Analysis of Clark UH Model


Variation of Nash-Sutcliffe Efficiency
coefficient (NSE) with variation of parameters
like Storage coefficient, R and Time of
concentration, Tc

VARIATION OF NS EFFICIENCY WITH


LAG TIME FOR SCS UH
0.9
Nash-Sutcliffe Efficiency

0.8
0.7
0.6
0.5
0.4
0.3
Sensitivity Analysis of 0.2
0.1
SCS UH Model 0
Variation of NSE with 1000 1500 2000 2500 3000 3500 4000 4500
Time Lag, Tlag Lag Time in Minutes

10
Results obtained

COMPARISION OF TRANSFORM MODELS IN OCT-2013(A)

4500

Observed discharge
4000
Discharge in cumec

3500 Clark (NSE 0.937)

3000
SCS (NSE 0.536)
2500

Snyder (NSE 0.938)


2000

1500

1000

500

0
0 20 40 60 80 100 120 140 160 180 200 220

Time in hours

Comparison of observed and simulated flood hydrographs of three models for event
Oct-2013(A)
11
Results obtained

Forecasted Flood Hydrograph for event Oct-2013 (A)


4,000

4 Hour 8 Hour
3,500

12 Hour 16 Hour
3,000
Discharge in cumec

2,500
20 Hour 24 Hour

2,000 28 Hour 33 Hours

1,500

1,000

500

-
0 25 50 75 100 125 150 175 200 225 250
Time in hours

Comparison of observed and simulated flood hydrographs of three models


for event Oct-2013(A)
12
Results obtained

100-years
Approach of 100-years
Types of maximum
flood Flood Peak Remarks
storm water level
Estimation (cumec)
(m)

Single Bell 4236.18 10.40


Deterministic
approach
Double Bell 4194.93 10.36

Probabilistic
3522.41 9.59
approach

Comparison of 100-years flood peaks with two approaches

13
Results obtained

Calibrated stage and flow hydrograph for flood event Oct-2013(A)

14
Results obtained

Simulated area of inundation for flood event Oct-2013(A) at 06:00 on 14th Oct.

15
Results obtained

Actual area of inundation for flood event Oct-2013(A) at 06:00 on 14th Oct. as per
Disaster Management Support Service available on Bhuvan web site.
16

Vous aimerez peut-être aussi