Concreting

Of
Column

GROUP 5
Neer Patel(UG180385)
Abhishek Chowatia(UG180034)
Introduction
• ELEMENT: Column Concreting
• OBSERVED LOACTION: Bungalow no. 10
• LEVEL: Ground floor slab top(3150 mm) to first
floor beam bottom(5950 mm)
• OBSERVED COLUMNS: C1,C2,C3,C5
• MIX RATIO: M25 (1:1:2) {Cement:Sand:Aggregate}
• LABOURERS: Skilled(3) Unskilled(18)
• DRAWINGS REFFERED: Column schedule layout
plan , First floor plan
• MATERIAL REQUIRED: Sand,Cement,Aggregate,Water
• TOOLS REQUIRED: Spade, Wooden float, Pan,
Needle vibrator, Concrete
mixer, Wooden mallet
JOB LAYOUT
FLOOR PLAN
LOAD TRANSFER MECHANISM
• STEEL PLATES

• GROUND FLOOR
COLUMN

• GRADE SLAB

• PLINTH BEAM

• PLINTH COLUMN

• FOUNDATION
CHECKILST FOR COLUMN CONRETING
• BEFORE CONCRETING 7. Check the side suppots to
maintain the position &
1. Check line, size, diagonals and verticality of column shuttering.
()
plumb of column shuttering.
8. Check the spacing and lap length
Cross check distances from of reinforcemnet above concrete
adjacent columns as per level.()
working drawing.()
2. Apply deshuttering oil to • AFTER CONCRETING
shuttering material.() 1. Deshuttering is done after 24
3. Mark level up to which hours.()
concreting is to be done.() 2. Finishing of honeycomb
4. Check the reinforcement as per should be done after 1 day.
the strutural drawing.() (if observed)()
5. Make sure that the concrete is 3. Curing of column to be done
filled upto marked level.() with wet hessain (Cotton
Jute) cloth wrapped around
it for 7 to 10 days.()
PROCEDURE
Labourers transport material to mixer and
concrete mix of M25 is prepared.

Concreting is done (76 mm) less than


adjoining wall, rebars having (76 mm) depth
marked is used for checking the levels.

After pouring , compaction is done with the


help of needle vibrator.

After completion formwork is checked and


support is provided if needed.

After deshuttering curing is done for 7 days.


PROCEDURE SKETCH

Addition of cement Addition of Compaction using a


slurry. prepared M25 needle vibrator.
cement mortar.
LABOUR DISTRIBUTION
ACTIVITY SKILLED UNSKILLED
Transportation of materials - 6
Mixing of concrete 1 -
Loading of concrete in pan - 2
Transportation of concrete to - 10
required location
Pouring of concrete 1 -
Compaction 1 -
TOTAL 3 18

TOTAL LABOUR COST

UNSKILLED = RS300/Labour = 5400 Rs


SKILLED = RS 600/ Labour = 1800 Rs
MATERIAL QUANTITY
COLUMN LENGHT BREADTH HEIGHT VOLUME
TYPE (M) (M) (M) (M3)
C1 0.23 0.23 2.950 0.156

C2 0.375 0.23 2.950 0.2544

C3 0.375 0.23 2.950 0.2544

C5 0.450 0.23 2.950 0.31

C1 = 2*0.156 = 0.312 m3
C2 = 5*0.25 = 1.272 m3
C3 = 3*0.25 = 0.76 m3
C5 = 1*0.31 = 0.31 m3

TOTAL VOLUME = 2.64 m3


MATERIAL COST
MATERIAL VOLUME COST/UNIT MATERIAL TOTAL
(M3) CONSUMPTION COST
Cement 0.6618 270/Bag 19.06 Kg 5146 Rs
Sand 0.6618 450/Ton 1.0588 Ton 476.5 Rs
Aggregate 1.32 500/Ton 2.376 Ton 1188 Rs

MATERIAL COST = CEMENT + SAND + AGGREGATE


= 5146 + 476.5 + 1188
= 6810.5 Rs

TOTAL ACTIVITY COST


= LABOUR COST + MATERIAL COST
= 7200 Rs + 6810.5 Rs
= 14010.5 Rs