Académique Documents
Professionnel Documents
Culture Documents
Of
Column
GROUP 5
Neer Patel(UG180385)
Abhishek Chowatia(UG180034)
Introduction
• ELEMENT: Column Concreting
• OBSERVED LOACTION: Bungalow no. 10
• LEVEL: Ground floor slab top(3150 mm) to first
floor beam bottom(5950 mm)
• OBSERVED COLUMNS: C1,C2,C3,C5
• MIX RATIO: M25 (1:1:2) {Cement:Sand:Aggregate}
• LABOURERS: Skilled(3) Unskilled(18)
• DRAWINGS REFFERED: Column schedule layout
plan , First floor plan
• MATERIAL REQUIRED: Sand,Cement,Aggregate,Water
• TOOLS REQUIRED: Spade, Wooden float, Pan,
Needle vibrator, Concrete
mixer, Wooden mallet
JOB LAYOUT
FLOOR PLAN
LOAD TRANSFER MECHANISM
• STEEL PLATES
• GROUND FLOOR
COLUMN
• GRADE SLAB
• PLINTH BEAM
• PLINTH COLUMN
• FOUNDATION
CHECKILST FOR COLUMN CONRETING
• BEFORE CONCRETING 7. Check the side suppots to
maintain the position &
1. Check line, size, diagonals and verticality of column shuttering.
()
plumb of column shuttering.
8. Check the spacing and lap length
Cross check distances from of reinforcemnet above concrete
adjacent columns as per level.()
working drawing.()
2. Apply deshuttering oil to • AFTER CONCRETING
shuttering material.() 1. Deshuttering is done after 24
3. Mark level up to which hours.()
concreting is to be done.() 2. Finishing of honeycomb
4. Check the reinforcement as per should be done after 1 day.
the strutural drawing.() (if observed)()
5. Make sure that the concrete is 3. Curing of column to be done
filled upto marked level.() with wet hessain (Cotton
Jute) cloth wrapped around
it for 7 to 10 days.()
PROCEDURE
Labourers transport material to mixer and
concrete mix of M25 is prepared.
C1 = 2*0.156 = 0.312 m3
C2 = 5*0.25 = 1.272 m3
C3 = 3*0.25 = 0.76 m3
C5 = 1*0.31 = 0.31 m3