Académique Documents
Professionnel Documents
Culture Documents
Prepared By
Planning:
Process of choosing the method and
order of work
Scheduling:
Process of determining the interrelationship
of associated timings of operations.
Activities shown by
Arrows. Relationship
between activities
shown by nodes /
events.
Length of arrows does
not obey any scale.
There is Start-to-finish
relationship between
activities, also called
Predecessor-Successor
Relationship.
Any time units may be allotted to activity durations like days, hours, weeks,
months, shifts, etc.
FORWARD PASS
In Forward Pass through the network, the top two cells, of the
six-celled box at each activity are calculated.
The top two cells give the values of EST & EFT.
Forward Pass is carried out from left to right in the network
The EST of first activity/activities is set to zero or some other
number.
The EFT of the first activity/activities will be 0 + duration of first
activity/activities.
The EST & EFT of subsequent activities are calculated as
BACKWARD PASS
In Backward Pass through the network, the middle two cells, of the
six-celled box at each activity are calculated.
The middle two cells give the values of LST & LFT.
Backward Pass is carried out from right to left in the network
The LFT of last activity/activities is set to maximum EFT of the last
activity/activities or some other number i.e. date of handing over.
The LST of the last activity/activities will be LFT - duration of last
activity/activities.
The LST & LFT of activities progressing backwards in times are then
calculated as
FLOAT CALCULATION
The bottom two cells give the values of Total Float (TF) & Free
Float (FF).