g Power Systems Energy Services Technology

9FA(9311) DLN 2.0 EL (Extended


Life) Combustion System
Product Introduction Proposal
g Energy Services Technology GT Contractual & Services Programs

CTQ
• Extend the 9FA DLN-2.0 combustion system inspection intervals
• Maintain or improve the 400 fired start combustion inspection interval
requirement

Approach
Combine field experience and analysis to identify components which
Inhibit extended life and upgrade those components from the baseline product
• Super B TBC/APS bond coat - Liner & TP
• Improved cloth seals for TP
• Improved TP life with integral mount and scoops
• Fuel Nozzle wear coatings
• Thimbled Flow Sleeve
• Optimized 2Cool Aft-end liner
• Structural reinforcements to zipper strip
• Improved End Cover design
• Diffusion start fuel nozzles

5/29/2019 GE Proprietary Information 2


g Energy Services Technology GT Contractual & Services Programs

System Design Overview – Apply common design for PG9311 and PG9351 EL where possible:
End Cover Cap: Stellite 6 Wear Coatings
- Lifing Analysis -Same as 12K design - Cap and Liner Hula Seals
- 1st Quarter 02 -12K/110 start validation - Forward TP mount (Bullhorn)
incorporation at Azko Dolesto (2000) w/ FSX-414 H-blocks
of Braze Leak Liner:
RCA Redesign - Same as 9351 design
- Super B TBC
- Hast-X to Nimonic 263
- Eliminate aft weld
- 2-Cool ™ aft end
- Double Hula Seal
Transition Piece:
-same as 9351
-Integral Mount
-Cloth Seals
-Super B TBC
Fuel Nozzles
-Oil/Water Cartridge
tip wear improvements
-New Diffusion Start tip
-Cast Fared Gas nozzles
(same casting as 7241) Flowsleeve Assy:
- Same as 9351
- Profile changed for better
Liner Cooling.
- Cross Fire Retainer Clips (Baseline 9311 shown)
Redesigned.
5/29/2019 GE Proprietary Information 3
g Energy Services Technology GT Contractual & Services Programs

7.1 Transition Piece Design:

4
3

“IS” 119E1997G001 - 9FA ELIntegral Mount TP “WAS” 103E3620G024 - Baseline 9FA 9311/9351 TP

design
Feature Description IS - 9FA EL Integral Mount TP WAS - Baseline (current 8k ci)
change
1 AFT MOUNTING SYSTEM Integral Aft Frame and mounting Lugs "Tractor Seat" Welded to TP Body
2 IMP SLEEVE SCOOPS Side Panel Scoops No Scoops
3 TP AFT SEALS (not shown) Cloth Seals - L605 cloth / cloth couple Hard Seals
4 FORWARD MOUNT FSX-414 H-block w/ Stellite 6 coated Bullhorn Hast-X H-block / uncoated 304L Bullhorn
5 IMP SLEEVE INNER MOUNT Welded Gussett Bolted to aft frame tab Imp Sleeve bolted to TP body spool spacer
6 IMP SLEEVE OUTER MOUNT Large Gussett joining left and right mount brackets
Gussetts attached to tractor seat/TP body
7 IMP SLV INNER/OUTER SEAL STRIPS Optimized welding process & configuration Zipper Strip

Tom Amond 11/00


5/29/2019 GE Proprietary Information 4
g Energy Services Technology GT Contractual & Services Programs

Customer Impact
 Improved hardware capability with components designed for
Extended Life capability
 Instrumented field test at Prototype unit startup
 Validate design analyses
 Establish optimum unit operating configuration
 Fleet Leader Inspection plan to verify extended inspection intervals
and component replacement lives
 Up to 8 CI’s eliminated over course of 12 year contract

Current 8K 16K 24K 32K 40K 48K 56K 64K 72K 80K 88K 96K
CI schedule

Extended 8K 16K 24K 32K 40K 48K 56K 64K 72K 80K 88K 96K
Life
CI schedule

5/29/2019 GE Proprietary Information 5


g Energy Services Technology GT Contractual & Services Programs

Field Validation
PG 9311 EL Combustor Characterization
Objective:
Validate critical component Temperatures and Gas Turbine
operability of the Extended life Combustion System.

Test team: Tom Amond (Combustion Design - Test Director)


Brad Crawley (Combustion Design)
Test Coordinator (TBD)
Test Engineer (TBD)
GE DLN TA (TBD)
Test specialists (2-3 people)

5/29/2019 GE Proprietary Information 6


g Energy Services Technology GT Contractual & Services Programs

Field Validation Site Provisions


 Site location for test trailer, power supply, etc.
 Communicate requirements for storage of equipment,
site training etc.
 <I> processor to the test trailer to capture control
system data
 GE DLN TA to establish baseline tuning prior to testing

5/29/2019 GE Proprietary Information 7


g Energy Services Technology GT Contractual & Services Programs

Field Test Schedule


• Customer Commitment to perform testing – go ahead to ship hardware &
equipment - 6 mth lead time:
• All Combustion Hardware to Arrive on Site. Test Engineering Team arrives to begin site
preparation – 2 weeks prior to outage
• GE DLN TA to baseline the dynamics and emissions on unit (pre-test)
(test points to be provided by Combustion Design Engineering) – 2 days prior to outage
Outage Begins

Day 3: Remove Existing Combustion System & complete modifications to Test


Chamber Casings (supplied by GE) as per 114E5631 sheet 2.
Day 5: Install EL Combustion System
Day 8: Fire Unit with EL Hardware and Conduct Characterization Test (see 372A1629)
Day 13: Testing Complete, Unit turned over to Customer
Test Crew to pack-up test equipment

5/29/2019 GE Proprietary Information 8


g Energy Services Technology GT Contractual & Services Programs

Fleet Leader Inspection Requirements


Fired Hours /
Inspection Requirements Impact
Fired Starts
Mini inspection limited to removal of the
Successful inspection will be indicated by the
combustion liners.
non-existence of any infant mortality issues
The inspection will entail a general
and a preliminary indication of the hardware’s
1000-1500 / review of the combustion hardware for
capability to satisfy extended CI intervals.
25 infant mortality issues including wear
This successful inspection will also initiate the
indications, TBC spallation, cracks etc.
introduction of the 9FA EL design into
Outage time is estimated to not exceed 3 production.
days.
Full Combustion Inspection to include
removal of all combustion liners & TP’s.
Successful inspection will be determined by
8000 / The hardware review will be conducted in
an engineering assessment evaluating
the format of a typical combustion
130 hardware capability to achieve the extended
inspection with the outage time estimated
interval.
as the normal duration for an MS9FA
combustion inspection.
Full Combustion Inspection to include Successful inspection will be determined by
removal of all combustion liners & TP’s. an engineering assessment evaluating
The hardware review will be conducted in hardware capability to achieve extended CI
16000-18000 /
the format of a typical combustion interval.
270 inspection with the outage time estimated This successful inspection will initiate the
as the normal duration for an MS9FA ‘Approval to Apply’ review with extended CI
combustion inspection. quoting levels.
Full Combustion Inspection to include
Successful inspection will be determined by
removal of all combustion liners & TP’s.
an engineering assessment evaluating
The hardware review will be conducted in
24000 / hardware capability to achieve extended CI
the format of a typical combustion
400 intervals.
inspection with the outage time estimated
This successful inspection serves as the final
as the normal duration for an MS9FA
validation point for the Extended Life product.
combustion inspection.

Unsuccessful inspections will result in engineering recommendations to utilize


optional product offerings or suggest redesigns to satisfy customer requirements

5/29/2019 GE Proprietary Information 9


g Energy Services Technology GT Contractual & Services Programs

Mini-Inspection Plan
Proposed Schedule for Mini-Inspection @ 1,000 – 1,500 Fired hours (dates estimated only):
Day 1: Begin Outage on Unit
Day 2: Remove instrumented hardware - replace with new EL components
Plug Instrumentation ports in manhole covers as required
Detailed inspection of Instrumented Caps, Liners, and TP’s
Full Borescope Inspection of all other chambers (2 through 17)
Day 4: Assuming no issues are encountered, restart unit
Perform normal tuning split checks up to base-load
Day 6: After tuning has been verified, Combustion team departs site