Vous êtes sur la page 1sur 4

Electrical Copper Pipe Sanitary Piping

Block Dry Riser Pipe Hosereel Pipe


Concealed Works Installation (UPVC Pipe)

870A 13th sty in progress 13th sty in progress 13th sty in progress 13th sty in progress 11th sty in progress

871C 13th sty in progress 13th sty in progress 13th sty in progress 13th sty in progress 11th sty in progress

871B 7th sty in progress 8th sty in progress 9th sty in progress 11th sty in progress 11th sty in progress
Block Activity Actual Start Actual Finish Remarks

871C to 871B UPS & UTS 15 Nov 13 6 Dec 13

870A to 871C UPS & UTS 7 Dec 13 22 Jan 14

870A & 870B MH2 to MH7 21 Oct 13 17 Dec 13 To date 80% completed

Beside 871B MH1 Target Start: Oct 14 Target Finish: Dec 14 Ri Dong to complete
(Subject to Ridong (Based on target start) Tampines St 86 and hand
handing over) over to KP. KP will shift the
access over and continue
with MH1 construction
Target of
OUTSTANDING WORKS (AS OF TO DATE)
OUTSTANDING WORKS (AS OF TO DATE)

Vous aimerez peut-être aussi