Académique Documents
Professionnel Documents
Culture Documents
INFRASTRUCTURE
PROJECTS
(An Overview)
Presented by:
17 February 2015
DpwhPs-ppd
Presentation Outline
Project Identification
Project Preparation
Project Implementation
Project Operation and Evaluation
DpwhPs-ppd
What is a Project ?
DpwhPs-ppd
DPWH PROJECT DEVELOPMENT CYCLE
PROJECT
IDENTIFICATION
MAINTENANCE,
PREPARATION
EVALUATION
OPERATION,
PROJECT
PROJECT
IMPLEMENTATION
DpwhPs-ppd
1. Project Identification
Project is usually identified and prioritized from PMS and
BMS outputs, area development surveys, master plans
and regional development plan, sector and industry
studies, etc. – undertaken by the DPWH and other
concerned entities such as National Economic and
Development Authority (NEDA), Regional Development
Council (RDCs), etc.
DpwhPs-ppd
2. Project Preparation
a) Project Feasibility Study
Once project is identified, a feasibility study is undertaken.
DpwhPs-ppd
2. Project Preparation
a) Project Feasibility Study (Cont.)
Meets conventional feasibility criteria – i.e. appropriate engineering
design and estimates with +/-20% accuracy, and an economic internal
rate of return (EIRR) of at least 15%
DpwhPs-ppd
2. Project Preparation
DpwhPs-ppd
2. Project Preparation
DpwhPs-ppd
2. Project Preparation
g) Detailed Engineering
DpwhPs-ppd
2. Project Preparation
g) Detailed Engineering
DpwhPs-ppd
3. Project Implementation
a. Fund Releases
b. Right-of-Way (ROW) Acquisition (Note: often
frontloaded during detailed engineering stage)
c. Bidding and Contracting
d. Construction
e. Completion and Acceptance
DpwhPs-ppd
4. Project Operation and Evaluation
DpwhPs-ppd
Project Development Cycle
Project
Identification
Ex-Post Project
Evaluation
Project
Preparation
Post-Investment Pre-Investment
Phase Phase
Project
Operation and
Maintenance
Project
Appraisal and
Investment Financing
Phase
Project
Implementation
Detailed
Project
Engineering
DpwhPs-ppd
Project Identification and Development Process
ENVIRONMENTAL
BOTTOM UP CLEARANCE
PLANNING CERTIFICATE
PROCESS
NEDA/INVESTMENT
AREA COORDINATING
DEVELOPMENT COM APPROVAL
STUDIES
SECTOR/ NEGOTIATING
MASTER PLAN APPRAISAL
STUDIES
PROJECT
IDENTIFICATION FEASIBILITY STUDY
OTHER
DETAILED
OPPORTUNITY
ENGINEERING
STUDIES
PHYSICAL PROJECT
INFRA PLAN APPRAISAL IMPLEMENTATION
DpwhPs-ppd
II. FEASIBILITY STUDY FOR
INFRASTRUCTURE PROJECTS
DpwhPs-ppd
Why do we do feasibility studies?
DpwhPs-ppd
Project Categories
independent projects
complementary projects
integrated area development projects
DpwhPs-ppd
Levels of Feasibility Analysis
Pre-feasibility Study
Feasibility Study
the two are similar differing mainly in the
degree of detail and accuracy involved.
DpwhPs-ppd
Pre-feasibility Level
DpwhPs-ppd
Feasibility Study Level
DpwhPs-ppd
Feasibility Study Team Composition
Team Leader
Economists
General
Transport
Agricultural/Development
Engineers
Highway
Bridge/Structural/Drainage
Materials
Traffic
Cost Estimator
Environmentalist / Sociologist
DpwhPs-ppd
MAIN ACTIVITIES IN A FEASIBILITY STUDY
DATA FRAMEWORK
TRAFFIC SURVEYS
HIGHWAY INVENTORY
BEFORE-AFTER GENERATED TRAFFIC
IMPROVEMENT AND
ECONOMIC EVALUATION
MAINTENANCE COST REDUCTIONS
flooded areas,etc…..
Topographic Surveys
topographic maps
Structure Requirements
Construction Cost
POW
RROW
Salvage Value
Maintenance Cost
Implementation Schedule
DpwhPs-ppd
ECONOMIC EVALUATION
COSTS BENEFITS
EVALUATION
ANALYSIS
RESULTS
RECOMMENDATIONS
ENVIRONMENTAL
ASPECTS
DpwhPs-ppd
Project Benefits
Consumer Surplus Benefits
Normal Traffic Benefits
Diverted Traffic Benefits
Generated Traffic Benefits
Other Benefits
DpwhPs-ppd
Traffic Categories
Transfer
Network Traffic Assignment Cost
W/O W/ Adjustment
OD Volume Project Case Project Case
Shadow
VOC (wo) VOC (w)
TTC (wo) TTC (w) Wage Rate
EVALUATION
DpwhPs-ppd
EVALUATION CRITERIA AND
INVESTMENT DECISIONS
1. Net Present Value:
NPV = (B1- C1) + (B2- C2) + ….. (Bn- Cn)
(1 + r) (1 + r)2 (1 + r )n
4000
2000
NPV = 0 at 15% Internal Rate
Discount Rate
of Reurn
0
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0%
-2000
-4000
Discount Rate (%)
EVALUATION CRITERIA AND
INVESTMENT DECISIONS
3. Benefit/Cost Ratio
B0 +. . . + Bn
(1 + i)0 (1 + i)n
B/C =
C0 +. . . + Cn
(1 + i)0 (1 + i)n
EVALUATION CRITERIA AND
INVESTMENT DECISIONS
DpwhPs-ppd
Questions and Decisions 1.
DpwhPs-ppd