Académique Documents
Professionnel Documents
Culture Documents
BOF
PROCESS FLOW DIAGRAM OF SMS COMPLEX TO
PRODUCE 2.5 MILLION TONNES
GCP
caster
2 DESULPHURISATION BAY
(JIB CRANE) 5 2
3 SCRAP BAY 30 2
4 CONVERTER BAY
(HM CHARGING CRANE) 180 + 50 2
(SCRAP CHARGING : SEMI PORTAL) 40 + 40 1
5 LADLE PREPARATION BAY
(LADLE CRANE) 75 + 15 2
(CANTILEVER CRANE) 5 3
6 SLAG BAY 100 / 20 2
HOT METAL MIXER: 1300T X 2
HMDS (HOT METAL DESULPHURIZATION
PLANT)
CALCIUM
Initial sul = 0.04% TO 0.06%
CARBIDE & Target sul = 0.015% TO 0.01%
MAGNESIUM
SULPHER
RICH SLAG Cycle time (total) matching t/t time = 22 mins
Temp
TRANSFER LADLE
At Slag
C% Si% Mn% P% S% HMDS Vol
0.13
0.035
Avg/
0.5- 0.18- Avg/ 1290- 1% of
3.9- 0.20
0.8 0.30 0.05 1320 OC HM
4.3 max
max.
.
HMDS SAFETY POINTS
OXYGEN LANCE
TAPHOLE
SLAG
OXYGEN JET
STEEL BATH
• SCRAP HANDLING
• HOT METAL HANDLING
• FLUX & ADDITIVES HANDLING
• GAS CLEANING PLANT
• STEEL LADLE MANAGEMENT
CROSS SECTION OF CONVERTER
STEPS FOR PREHEATING OF
CONVERTER
1. Converter bottom should be inspected.
2. Four to Five Tons of coke is added inside the empty converter using scrap
box.
3. Tilt the converter towards tapping side and fix the thermo couple.
4. Throw the lighted torch inside converter.
5. Make the converter vertical.
6. Lower the Oxygen blowing lance to about 2M height.
7. Set oxygen flow to 50-60 NM3/Min.
8. Adjust the flow rate and lance height so as to follow the temperature rise
pattern as per the standard graph.
9. Soak the converter for about ½ hour.
10.Tilt the converter towards tapping side and take out thermocouple.
11.Burn the left over coke if any.
12.Charge the converter with Hot Metal only.
13.Do the Lance calibration to determine the Bath Level.
PREHEATING OF CONVERTER
Pre Heating Graph
1200
1100 1100
1000
Temperature In Deg. C
800 800
700
600 600
500
400 400
300
200
0
0.5 1 1.5 2 2.5 3 3.5 4
Time In Hours
SCRAP CHARGING
2.6
2.2
Lance height, m
1.8
1.6
2 4 5 9 13 17
2. Lance water flow temp inlet outlet difference ΔT > 20°C (trip)
• GCP Ready
• Converter vertical
• Lance is coaxial
EMERGENCY LIFT INTERLOCKS
• Drives ready
• Lubrication healthy
WET ESP
SPRAY NOZZLE
WATER FROM
STAGE 2 MANUALLY ADJUSTABLE
QUENCHER THROAT
CONVERTER 3-WAY
DIRECTIONAL
ADJUSTABLE DAMPER DRY GAS
DAMPER
ANALYSER
STAGE 2 VENTURI SCRUBBER
WITH WHIRL
VANE SEPARATOR
ID FAN WATER SEAL
CHECK VALVE
FLARE STACK
STEEL LADLE 130T
METAL ZONE
CASTABLE
MAIN PIPE
TILLTER
BELL CRANCK
FLEXIBLE PIPE
PURGING SYSTEM WITH BOTTEM POROUS POURING SYSTEM WITH SLIDE GATE M/C
PLUG
INERT GAS BOTTOM PURGING SYSTEM IN STEEL
LADLE USED IN SECONDARY TREATMENT
SEATING BLOCK
INSERT
PURGING PLUG
SPACER RING
SLEEVE
PACKING MATTERIAL
ADOPTER DRUM
I - BOLT
MINIMUM LADLE REQUIREMENT
FOR TAPPING
Argon
bubbles
Wire injection
feeders
Addition hole
• No hood leakage
CCP
CONTINUOUS CASTING PLANT (CCP)
4 Slab caster
2 Bloom Caster
DIAMOLD Tube Mold Design
Hydraulic Oscillator
Slab
FEATURES OF BLOOM & SLAB
CASTERS
Sequence index 10 -
(average)
Restranding Time 912 hours (38 days) -
SLAB CASTER 6
Product Features
Slab Width 1100 mm Minimum
1800 mm Maximum
Inlet Outlet