Summary of LS2 ECRs

LIU-PSB Scope
T. Birtwistle (EN-ACE-CL)

LIU-PSB meeting 22nd May 2018


Information
• The following slides cover only LIU-PSB scope. However, we
do also require ECRs for other activities where a change
impacts on “Form, Fit or Function”
• Please use the correct template for ECRs, available here:
https://quality.web.cern.ch/templates
• Where relevant, integration studies must be done and
contained within the ECR, in advance of the formal ECR
approval process:
• Please contact the integration team (Jean-Pierre Corso)
• ICL (integration) meeting once every ~2 weeks (Wednesday)
• If you have an LIU-PSB activity that is missing from the lists,
and you think an ECR may be needed, please contact me

2018-05-22
LIU-PSB LS2 ECRs
Multiple Groups
Description Group Responsible ECR Reference ECR Status
TE-ABT
Upgrade of the PS Booster extraction lines
(input from Wolfgang Bartmann Needed
BT, BTM and BTP
others)
SRR’s approved:
Magnet modifications in BT, BTM and BTP
TE-MSC Antony Newborough PSB-LJ-EC-0010
(including BT.BHZ10 and BTM.BHZ10) PSB-LJ-EC-0011
Beam instrumentation modifications in BTP
line (LIU related BTV changes in BT line BE-BI Lars Soby
already covered by a separate ECR)
Installation of new BLMs on the PS Booster
BE-BI Christos Zamantzas
extraction lines
Edouard Grenier-
EN-STI beam stopper in BTP EN-STI
Boley

All related vacuum changes TE-VSC Jose Somoza


Include reference to the ECRs for the BT Line
TE-ABT Wolfgang Bartmann
Septa

Various contributions needed from groups for the overall ECR

2018-05-22
LIU-PSB LS2 ECRs
Multiple Groups
Description Group Responsible ECR Reference ECR Status

Add a new BPM on the BI line (upstream of TE-ABT, Christoph Hessler SRR approved
PSB-LJ-EC-0013 Needed
BI.SMV10) BE-BI Lars Soby

Multiple Groups
Description Group Responsible ECR Reference ECR Status
Modifications to the Booster extraction main TE-MSC,
Antony Newborough
unit and BT1/4.BVT10, BT2/3.DVT10 (upto TE-VSC, Needed
Jose Somoza
the BPMs) BE-BI

2018-05-22
LIU-PSB LS2 ECRs
TE-ABT
Description Group Responsible ECR Reference ECR Status

Replace kicker BT.KFA10 Luc Sermeus, 1955039


TE-ABT Under Approval
(same size, but potential implications on impedance) Wim Weterings PSB-MK-EC-0001

1955075 Under Approval


Replace extraction kicker BEr.KFA14L1 TE-ABT Luc Sermeus (impedance checks
(same size, but potential implications on impedance) PSB-MK-EC-0002 ongoing)

Installation of Upgraded PSB Recombination 1459318


TE-ABT Michael Hourican Released
Septa BT.SMV10 (BT1 and BT4) PSB-MSMIC-EC-0001

Installation of Upgraded PSB Recombination 1459320


TE-ABT Michael Hourican Released
Septum BT.SMV20 PSB-MSMID-EC-0001
1422350
Exchange KSW magnet in 16L1, 1L1 and 2L1 TE-ABT Luis Coralejo Released
PSB-MKKSW-EC-0001
1518483
New distributor BI.DIS10 TE-ABT Wim Weterings Released
PSB-MSMIA-EC-0001
1561343
New Septum BI.SMV10 TE-ABT Michael Hourican Released
PSB-MSMIB-EC-0001
1422358
New injection region in the Booster 1L1 TE-ABT Wim Weterings Released
PSB-L-EC-0001

2018-05-22
LIU-PSB LS2 ECRs
TE-MSC
Description Group Responsible ECR Reference ECR Status
Upgrade of the BHZ Main unit bending
Antony In work
magnets (including injection bending TE-MSC
Newborough (integration needed)
magnet and reference magnet)

Damping Resistors on PSB Bending and Quad Antony 1817987 Under Approval
TE-MSC
Magnets Newborough PSB-M-EC-0001 (studies ongoing)

Booster Injection Transfer Line Magnet Antony 1494503


TE-MSC Released
Upgrades and Consolidation Newborough PSB-LJ-EC-0001
Plus contribution of information for the BT, BTM, BTP Lines

2018-05-22
LIU-PSB LS2 ECRs
TE-EPC
Description Group Responsible ECR Reference ECR Status
Booster extraction septa transformers Jean-Marc S. Pittet confirmed no
TE-EPC
modifications (in tunnel) Cravero change to volume

Upgrade of PS Booster Corrector and 1874665 Under Approval


TE-EPC Louis De Mallac
Quadrupole Power Supplies PSB-R-EC-0005 (ICL approval needed)

Booster Power House (BHP) Converters 1868992 Under Approval


TE-EPC Serge Pittet
Upgrade PSB-R-EC-0003 (integration needed)

Installation of the power converters for Jean-Marc 1887658 Under Approval


TE-EPC
BI.SMV10 magnets for LIU PSB injection Cravero PSB-R-EC-0007 (ICL approval needed)

Installation of new Power Converters for 1821166 Under Approval


TE-EPC Serge Pittet
PSB injection Qstrip, Correctors, Quad. PSB-R-EC-0004 (integration needed)

1643409
New MPS for LIU Booster (POPS-B) TE-EPC Fulvio Boattini Released
PSB-LJ-EC-0008
Consolidation and upgrade of the power 1851780
TE-EPC David Nisbet Released
converters of the LT and LTB lines PSB-R-EC-0006

2018-05-22
LIU-PSB LS2 ECRs
BE-BI
Description Group Responsible ECR Reference ECR Status
New BLMs Installation in the LT, LTB and
BE-BI Christos Zamantzas Needed
BI Lines for H- exchange monitoring

1962159 In work
8 Wire Scanners in the PSB 4L1 and 11L1 BE-BI Raymond Veness
PSB-BWSRA-EC-0001 (integration ongoing)

1572803
Relocation of BI.BTV30 BE-BI Stephane Burger Released
PSB-LJ-EC-0006
Relocation of BT2.BTV10 and BT3.BTV10 1494819
BE-BI Stephane Burger Released
in the PS Booster PSB-LJ-EC-0002

Plus contribution of information for the BT, BTP Line, the new BPM in the BI Line, and extraction line BLMs

BE-RF
Description Group Responsible ECR Reference ECR Status
Approved, but
The New PS Booster RF System (Finemet 1733551
BE-RF Mauro Paoluzzi integration model to
Cavities) PSB-ACWFB-EC-0001
be updated

2018-05-22
LIU-PSB LS2 ECRs
EN-STI
Description Group Responsible ECR Reference ECR Status

Removal of 2 beam stoppers (BI.STPFA and Edouard Grenier- 1835875 In work


EN-STI
BI.STPSW) on the BI line Boley PSB-LJ-EC-0012 (integration needed)
In work
Inigo Lamas (integration and input
New PS Booster Absorber in Period 8 EN-STI Draft only so far
Garcia from some other
groups needed)
Plus contribution of information for the stopper in BTP line
EN-CV
Description Group Responsible ECR Reference ECR Status

Ventilation system in the PS Booster EN-CV Gabor Petrika Needed

Consolidation of the Booster chilled water In work


EN-CV Gabor Petrika Draft only so far
plant (b. 361) (integration needed)

In work
Consolidation of the Booster cooling plant EN-CV Gabor Petrika Draft only so far
(integration needed)

2018-05-22
LIU-PSB LS2 ECRs
EN-ACE
Description Group Responsible ECR Reference ECR Status

1805620 Under Approval


New LBE line plus infrastructure EN-ACE Aurelio Berjillos
CPS-LJ-EC-0005 (integration needed)

Under Approval
(final verification of
1688400
Partial dismantling of Linac2 EN-ACE Aurelio Berjillos equipment
CPS-LJ-EC-0003
responsibilities
ongoing)

Ready, but to be
1688387 approved at the same
Connection of Linac4 to BHZ20 EN-ACE Aurelio Berjillos
CPS-LJ-EC-0002 time as:
CPS-LJ-EC-0003

2018-05-22