U p d a te As of July 29, 2019


REPORT
This Week’s SUMMARY:
Target for ConcreteWEEKLY UPDATE
Pouring (June 24 to 28)

Buri Handover Completion ● BURI COMMON AREAS HANDOVER COMPLETION


01 Solihiya Construction ●

% COMPLETION OF CHB LAYING AT 6F
ROOF DECK FORMS INSTALLATION
Accomplishment


Next Week’s Targets COMPLETION OF EXT CHB LAYING AT 6F Z1 &
02 Aug 5 to 10 ●
Z2
COMPLETION OF FORMS INSTALLATION @ RD
Z1&2

Critical Items/Issues for ● MATERIALS FOR FIREPRO


03 Discussion


ROOF DECK
ELEVATOR

Docs Con & SIs ● RFA AND RFC WEEKLY SCORECARD


04 Weekly Report ● SITE INSTRUCTION WEEKLY SCORECARD
BURI HANDOVER CLOSE OUT
2. COMMON AREAS
ACCOMPLISHMENT: 90%
ACCOMPLISHED ON-GOING WORKS TARGET (THIS WEEK) LOOK AHEAD (NEXT WEEK)
(LAST WEEK) (THIS WEEK)

8TH FLR EE RM, WM1&2, 9TH FLR EE RM, WM1 & 2, 9TH FLR EE RM, WM1 & 2, 9TH FLOOR HALLWAY, FE2
GAR., STO.1&2, AUX GAR., STO.1&2, AUX GAR., STO.1&2, AUX & 2ND FE2

FLR LVL HALLWAY EE RM WM 1 GAR. STO1 STO2 AUX WM 2 FE1 FE2 2FE1 2FE2

ROOFDECK JULY 30, 2019 ACCU, ACCENT ROOF, EQUIPMENTS N/A

9 LEAK RECTIFIED - FOR RI 7/30/2019


7/29/2019

8 DONE DONE DONE DONE DONE DONE DONE DONE

7 DONE DONE DONE DONE DONE DONE DONE DONE

6 DONE DONE DONE DONE DONE DONE DONE DONE RC -


July RC - July
27
30 27 30
5 DONE DONE DONE DONE DONE DONE DONE DONE

3 DONE DONE DONE DONE DONE DONE DONE DONE

2 DONE DONE DONE DONE DONE DONE DONE DONE

1 DONE DONE DONE DONE DONE DONE DONE DONE

PODIUM PARKING AREA (DONE)

BASEMENT PARKING AREA (DONE)

FINISHING COMPLETED
HANDED OVER AREAS
SOLIHIYA

LAST WEEK’S OVERALL PROGRESS ACCOMPLISHMENT


29.313% 31.467% +2.155%
20 DAYS
Plan Actual Variance

YEAR END TARGET PROGRESS ACCOMPLISHMENT


TRADE ACTUAL PLANNED WEEK END MONTH END YEAR END

STRUCTURAL 85.000 % 88.572 % 90.103 % 90.868% 100.000%

MASONRY 38.300 % 17.016 % 18.434 % 19.143% 66.809%

WET WORKS 24.101 % 24.101% 26.372 % 27.373% 71.205%

EXTERIOR 0% 0% 15.957%

DRY WORKS 0% 0% 24.597%

CORE 0% 0% 3.793%
SERVICES

FINISHING 0% 0% 2.256%
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
DRYWORKS: 24.597%
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. BUSDUCT AT 3RD FLOOR 1. DONE 1. AWARDED 1. ON GOING FABRICATION
2. PABX AT 3RD FLOOR 2. DONE 2. FOR AWARDING 2. NO WORK YET
3. STRUCTURED CABLING 3. DONE 3. FOR AWARDING 3. NO WORK YET
AT 3RD FLOOR
4. POWER CABLES & WIRES 4. DONE 4. FOR AWARDING 4. NO WORK YET
AT 3RD FLOOR
5. T&B FLOOR TILES AT 3RD 5. DONE 5. DELIVERED 5. NO WORK YET
FLOOR
6. PLUMBING DRAIN AT 6. ADOPT BURI 6. FOR AWARDING 6. NO WORK YET
3RD FLOOR
7. IMC PIPE AT 3RD FLOOR 7. DONE 7. DELIVERED 7. ON GOING 5TH FLOOR
8. HOSE BIBB AT 3RD 8. ADOPT BURI 8. FOR PO 8. NO WORK YET
FLOOR
9. DRYWALL & CEILING 9. ADOPT BURI 9. FOR DELIVERY 9. FRAMING @ 2ND
BOARD AT 3RD FLOOR
10. BALCONY RAILINGS AT 10. ADOPT BURI 10. FOR DP 10. NO WORK YET
2ND FLOOR
11. STAIR RAILINGS AT 3RD 11. ADOPT BURI 11. FOR DP 11. NO WORK YET
FLOOR
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
CORE SERVICES: 3.793 %
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. PANEL BOARDS/ 1. DONE 1. DELIVERED 1. ON GOING @ 5TH
BREAKER AT 2ND FLOOR
2. WATER HAMMER 2. DONE 2. FOR DELIVERY 2. NO WORK YET
ARRESTOR AT 1ST FLOOR
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
FINISHING: 2.256 %
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. WOOD DOORS AT 2ND 1. DONE 1. FOR 1. NO WORK YET
FLOOR FABRICATION
2. PVC DOORS AT 2ND 2. DONE AS PER BURI 2. FOR PO 2. NO WORK YET
FLOOR
3. WOOD FLOORING AT 3. ON GOING 3. AWAITING 3. NO WORK YET
1ST FLOOR MATERIAL
4. BASEBOARD AT 1ST 4. DONE AS PER BURI SAMPLE FOR 4. NO WORK YET
FLOOR APPROVAL
5. INTERIOR PAINT AT 2ND 5. DONE 4. AWAITING EWF 5. PAINT PREP AT 2ND FLR
FLOOR
5. ON SITE
SOLIHIYA

CONSTRUCTION UPDATE
CONC. WATER-
BEAM & COLUMN PLASTER WALL FLOOR DRY CEILING
LVL CHB TOPPIN PROOFI EXGA
SLAB ING TILES TILES WALL FRAME
G NG

RD 75 12 n/a n/a

9 100 80 75 12

8 100 100 100 100

7 100 100 100 100

6 100 100 100 100 40

5 100 100 100 100 40 100

3 100 100 100 100 100 100 5

2 100 100 100 100 100 100 40 50

1 100 100 100 100 100 100 0 85 0 80

POD. 100 100 100 100 0 100 0 60 0 60

BSMT 100 100 100 100 0 100 0 60 0 60

ACTUAL
PLANNED
STRUCTURAL WORKS
CONCRETE POURING
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT

LEGEND
ZONE 1 & ZONE 2 ZONE 3 & ZONE 4
ON GOING
FLOOR POURED
PLANNED ACTUAL PLANNED ACTUAL STRIPPED FORMS

UPPER ROOF DECK 8/27/19 9/05/19

ROOF DECK 8/12/19 8/20/19


STRUCTURAL WORKS
WEEKLY TARGET ACCOMPLISHMENT

ACCOMPLISHED ON GOING SCHEDULED NEXT WEEK


WORKS (LAST WORKS COMPLETION (THIS LOOK AHEAD
WEEK) (THIS WEEK) WEEK)
●Beam and slab forms ●Beam and slab rebars ● Beam and bottom ● Completion of slab
installation roof deck installation roof deck bars slab forms and beam forms
zone 1 zone 1 installation at zone 1 installation at zone 2
●Column forms ●Beam and slab forms ●Installation of beam
installation roof deck installation roof deck and slab rebars zone
zone 2 zone 2 2
●Column and shear wall ●column forms
rebars installation roof installation roof deck
deck zone 3 zone 3
●forms stripping at zone
3 and 4
SOLIHIYA

SITE PHOTOS

0 0
1 2

Roof deck zone 1 installed slab forms Roof deck zone 2 forms installation
SOLIHIYA

SITE PHOTOS

0 0
3 4

Roof deck zone 1 installed forms for shearwall and PMB forms stripping
slab
STRUCTURAL WORKS
GROCERY LIST SUMMARY
MATERIAL
COMMERCIAL
MATERIALS APPROVAL DELIVERY STATUS DATE NEEDED
STATUS
STATUS

CHB 6” AS PER BURI AWARDED TO FBL ON-GOING MAY 2019

MASONRY CEMENT AS PER BURI AWARDED TO VIC ON-GOING JUNE 2019

W8 X 35 WIDE FLANGE AS PER BURI NOT YET AWARDED NOT YET DELIVERED NOV 2019

AWARDED TO
ANCHOR BOLTS AS PER BURI DELIVERED AUGUST 2019
SPECIALIZED BOLTS

STEEL PLATES AS PER BURI NOT YET AWARDED NOT YET DELIVERED NOV 2019

AWARDED TO
EVG PANEL AS PER BURI NOT YET DELIVERED JAN 2020
AEDOBE

W8 X 35 WIDE FLANGE AS PER BURI NOT YET AWARDED NOT YET DELIVERED OCTOBER 2019

AWARDED TO COAST
MACTAN STONE AS PER BURI DELIVERED FEB 2020
PACIFIC

ROOF DECK SEPTEMBER


AS PER BURI FOR AWARDING NOT YET DELIVERED
WATERPROOFING 2019

STRUCTURAL STYRO AS PER BURI NOT YET AWARDED NOT YET DELIVERED AUGUST 2019
18
ARCHITECTURAL WORKS
MASONRY WORKS

CHB INSTALLATION PLASTERING


Z1&Z2 Z3&Z4 Z1&Z2 Z3&Z4

FLR PLANNED ACTUAL PLANNED ACTUAL FLR PLANNED ACTUAL PLANNED ACTUAL

3F Oct 15 2019 Oct 29, 2019


6F Sept 17, 2019 Oct 1, 2019

5F Aug 17, 2019 July 15, 2019 Sept 3, 2019 July 30, 2019 2F Sept 17, 2019 Oct 1,2019

3F July 20, 2019 June 15 2019 Aug 3, 2019 July 12, 2019 1F Aug 17, 2019 Sept 3,2019
SOLIHIYA

WEEKLY TARGET ACCOMPLISHMENT


SCHEDULED SCHEDULED
ACCOMPLISHED ON GOING WORKS COMPLETION COMPLETION
WORKS
(LAST WEEK)
- 3 LAYERS CHB FOR 6F Z3 - 3 LAYERS CHB FOR 6F Z3 - CHB (3 LAYERS) AT 6F
- 3 LAYERS FOR 6F Z1 TO 2 - PLASTERING OF Z1&2 3F - PLASTERING OF Z1&2 3F Z3
- ZOCALO FORMS AT 6F Z4 - CHB PLASTERING AT 3F - CHB PLASTERING AT 3F - CONC. TOPPING AT 2F
- CHB (FULL HT) AT 5F Z4 - DRY AREA CONC. TOPPING - DRY AREA CONC. TOPPING Z1 & Z2
- PLASTERING AT 2F AT 2F Z1 AT 2F Z1 - PAINT PREPARATION AT
- PLASTERING GUIDEAT 2A - DRYWALL AT 3F - DRYWALL AT 3F 2F Z2
- DRY AREA CONC. TOPPING - PAINTING PREPARATION - PAINTING PREPARATION - DRYWALL FRAME AT 3F
AT 1F AT 2F Z2 AT 2F Z2
- PAINTING PREP. AT 2F Z1
ARCHITECTURAL WORKS
GROCERY LIST SUMMARY
MATERIAL
DELIVERY
MATERIALS APPROVAL COMMERCIAL STATUS DATE NEEDED
STATUS
STATUS

CHB 4” AS PER BURI AWARDED TO FBL ON-GOING MAY 2019

MASONRY CEMENT AS PER BURI AWARDED TO VIC ON-GOING JUNE 2019

DRYWALL & CEILING FRAMES AS PER BURI AWARDED TO VIC ON-GOING JUNE 2019

FLOOR & WALL TILES APPROVED AWARDED TO CEBU


ON-GOING JULY 22, 2019
SAMPLE OVERSEA

NATURAL STONE APPROVED FOR AWARDING NOT YET


OCTOBER 2019
SAMPLES AWARDED

FIRE SEALANT AS PER BURI W/ PO DELIVERED JULY 2019

PVC GROOVES & SHADOWLINE AS PER BURI FOR PO FOR DELIVERY JULY 2019

METAL DOORS AS PER BURI FOR AWARDING TO NOT YET


OCTOBER 2019
RAPID OR PRIME AWARDED

GROCERY LIST FULL

https://docs.google.com/spreadsheets/d/1FYofwPQG1K9mMtlIO_gk-5FGvisS19QNdBtFxcnRG4A/edit#gid=1591526161
21
SOLIHIYA

ARCHITECTURAL WORKS SITE PHOTOS

FLOOR TOPPING PREPARATION AT 2F ZONE 2

0
2

0 0
1 3

CHB INSTALLATION at 6F MAKING GOOD AT 2ND FLOOR ZONE 4


SOLIHIYA

ARCHITECTURAL WORKS SITE PHOTOS


INSTALLATION OF ZOCALO FORMS AT 7TH
FLOOR Z1 & Z2

0
5

0
4

WALL TILE INSTALLATION AT 1F Z1


MPF ACCOMPLISHMENT
PREVIOUS WEEK ACCOMPLISHMENT
PLANNED ACTUAL VARIANCE

9.27% 9.14% - 0.13% or 1 day delayed

THIS WEEK’S ACCOMPLISHMENT


PLANNED ACTUAL VARIANCE

9.77% 9.68% - 0.09% or 1 day delayed

SYSTEM PREVIOUS ACCOMPLISHMENT ON GOING ACTIVITIES TARGET FOR NEXT WEEK

● Waterline loop at 1st Floor ● Waterline loop at 1st


Zone 2 Floor Zone 2 & 3 ● Waterline loop at 1st Floor
● Waterline at 5th Floor Unit B, ● Waterline at 5th Floor Zone 3 & 4
PLUMBING
D1, D2 & G Zone 2 ● Waterline at 5th Floor 3
● Drain Collectors at Podium ● Drain Collectors at ● Drain Collectors at Podium
Zone 3 & 4 Podium Zone 1 & 2

● Crossmain Layout at 3rd and ● Crossmain Layout at


● Crossmain at 6th Floor
5th Floor Basement Zone 2
FIRE PRO ● Crossmain Layout at
● Crossmain Layout at ● Clearing of Sleeves at
Basement Zone 3
Basement Zone 1 Stair 1 & 2

● Refrigerant Pipes at 3rd Floor


● Refrigerant Pipes at 3rd Floor ● Sleeve works at 5th Zone 2
MECHANICAL
Zone 1 Floor Zone 3 & 4 ● CDP Pipes at 3rd Floor Zone
1
MPF WETWORKS
PLUMBING
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT

LEGEND
ZONE 1 - ZONE 4
ON GOING WORKS
FLOOR
PLANNED START PLANNED END ACTUAL 50% WATERLINE LAYOUT

6F WETWORKS JULY 19, 2019 MARCH 21, 2019 80% SANITARY LAYOUT

5F WETWORKS JULY 5, 2019 FEB 17, 2019 ON GOING

3F WETWORKS JUNE 6, 2019 DEC 12, 2019 ON GOING


MPF WETWORKS
FIREPRO
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT

LEGEND
ZONE 1 - ZONE 4
ON GOING WORKS
FLOOR
PLANNED START PLANNED END ACTUAL BALANCE FOR UNITS C,
D2, D3, E, F & L
3F WETWORKS JUNE 6, 2019 DEC 12, 2019 ON GOING DONE FOR BRANCHLINES

DONE FOR CROSSMAIN


2F WETWORKS MAY 9, 2019 OCT 22, 2019 ON GOING

1F WETWORKS APRIL 5, 2019 SEPT 19, 2019 ON GOING


MPF WETWORKS
MECHANICAL
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT

LEGEND
ZONE 1 - ZONE 4
ON GOING SLEEVE WORKS
FLOOR
PLANNED START PLANNED END ACTUAL DONE FOR RL/RS &
CDP ONLY
3F WETWORKS JUNE 6, 2019 DEC 12, 2019 ON-GOING

2F WETWORKS MAY 9, 2019 NOV 09, 2019

1F WETWORKS APRIL 5, 2019 OCT 05, 2019


MPF OSM STATUS
GROCERY LIST SUMMARY
MATERIAL COMMERCIAL
MATERIALS DELIVER / STATUS DATE NEEDED
APPROVAL STATUS STATUS

HOSE BIBB APPROVED AWARDED NO SCHEDULE YET NOVEMBER 2019

SEPTEMBER,
WATER METER APPROVED AWARDED NO SCHEDULE YET
2020

TARGET AWARDING
SANITARY DRAINS APPROVED NO SCHEDULE YET NOVEMBER 2019
ON JULY 29,2019

PLUMBING FIXTURES AND TARGET AWARDING


FOR APPROVAL NO SCHEDULE YET FEBRUARY 2020
ACCESSORIES ON JULY 29,2019

WATER HAMMER ARRESTER APPROVED AWARDED NO SCHEDULE YET JULY 30, 2019

SPRINKLERS & VALVES APPROVED FOR AWARDING NO SCHEDULE YET NOVEMBER 2019

MECHANICAL DUCTS FOR APPROVAL AWARDED AUG 3, 2019 JULY 2019

FCU/ACCU APPROVED AWARDED DECEMBER 2019 DECEMBER 2019

RANGE HOOD AND


APPROVED AWARDED NO SCHEDULE YET FEBRUARY 2020
COOKTOP

ELEVATORS APPROVED AWARDED NO SCHEDULE YET DECEMBER 2019

EXHAUST FAN FOR APPROVAL FOR AWARDING NO SCHEDULE YET NOVEMBER 2019
28
SOLIHIYA

MPF PROGRESS PHOTOS


WATERLINE INSTALLATION AT 1ST
FLOOR HALLWAY ZONE 2 & 3

0
2

0 0
1 3

WATERLINE INSTALLATION AT 5TH FIRE PRO LAYOUT AT BASEMENT


FLOOR ZONE 2 HIGH ZONE 1
SOLIHIYA

MPF PROGRESS PHOTOS


RL/RS PIPE INSTALLATION AT 3RD
FLOOR ZONE 1

00
22

00 0
10
1 3
1
ON-GOING PIPE SLEEVING AT 5TH
CROSSMAIN INSTALLED AT 5TH FLOOR
FLOOR ZONE 4
ELECTRICAL & AUXILIARY WORKS
PREVIOUS WEEK ACCOMPLISHMENT
PLANNED ACTUAL VARIANCE

22.07% 24.45% +2.38% (13 days ahead)

THIS WEEK ACCOMPLISHMENT


PLANNED ACTUAL VARIANCE

22.94% 24.62% +1.68% (9 days ahead)

ONGOING / TARGET FOR THIS


SYSTEM PREVIOUS ACCOMPLISHED NEXT WEEK TARGET
WEEK

● EE/AUX BOX SETTING @ ● SUB FEEDER/ PULL ● SUB FEEDER/ PULL BOXES
5F UNITS D3/E/M BOXES INSTALLATION @ INSTALLATION AT 5F Z4.
WETWORKS. 5F Z3.
● EE/AUX BOX SETTING @ ● EE/AUXBOX-SETTING AT 5F
● PANEL BOARD INST. @ 5F 5F UNITS A/F/G/H/I/L Z4 WETWORKS.
UNITS A/D3/E/F. WETWORKS.
EE/AUX ● EE/AUX BOX SETTING @ ● EE/AUX BOX-SETTING AT
● SLAB ROUGHING INS @ 3F UNITS A/B/C/D1/D2 3F DRYWORKS
RD Z1. DRYWORKS.
● PANEL BOARD INST. @ 5F ● PANEL BOARD INST. @ 5F
UNITS G/H/I/L. Z4 AND 6F Z1.
● SLAB ROUGHING INS @
RD Z2.
ELECTRICAL & AUXILIARY WORKS

ZONE 1 ZONE 2 ZONE 3 ZONE 4


ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT

LEGEND:
PLANNED ACTUAL ON GOING, ALMOST 90%
FLOOR
START FINISH START FINISH
DONE FOR WETWORKS
DONE
5F WETWORKS FEB 2019 FEB 2020 FEB 2019 ON GOING

3F WETWORKS DEC 2018 FEB 2020 DEC 2018 ON GOING


ELECTRICAL & AUXILIARY WORKS
EE/AUX WETWORKS INSTALLATION

LEV RESIDENTIAL UNITS


EL REMARKS

9 9A 9B 9C 9D1 9D2 9D3 9E 9F 9G 9H 9I 9J 9K 9L 9M

8 8A 8B 8C 8D1 8D2 8D3 8E 8F 8G 8H 8I 8J 8K 8L 8M

7 7A 7B 7C 7D1 7D2 7D3 7E 7F 7G 7H 7I 7J 7K 7L 7M

6 6A 6B 6C 6D1 6D2 6D3 6E 6F 6G 6H 6I 6J 6K 6L 6M

5 ON-GOING
5A 5B 5C 5D1 5D2 5D3 5E 5F 5G 5H 5I 5J 5K 5L 5M PLASTERING GUIDE @
ZONE 3.

3 3A 3B 3C 3D1 3D2 3D3 3E 3F 3G 3H 3I 3J 3K 3L 3M

2 2A 2B 2C 2D1 2D2 2D3 2E 2F 2G 2H 2I 2J 2K 2L 2M

1 1A 1B 1C 1D1 1D2 1D3 1E 1F 1G 1H 1I 1J 1K 1L 1M

ONGOING/ TARGET FOR THIS WEEK


DONE
ACCOMPLISHMENT LAST WEEK
ELECTRICAL & AUXILIARY WORKS
EE/AUX DRYWORKS INSTALLATION

LEV
EL RESIDENTIAL UNITS REMARKS

9 9A 9B 9C 9D1 9D2 9D3 9E 9F 9G 9H 9I 9J 9K 9L 9M

8 8A 8B 8C 8D1 8D2 8D3 8E 8F 8G 8H 8I 8J 8K 8L 8M

7 7A 7B 7C 7D1 7D2 7D3 7E 7F 7G 7H 7I 7J 7K 7L 7M

6 6A 6B 6C 6D1 6D2 6D3 6E 6F 6G 6H 6I 6J 6K 6L 6M

5 5A 5B 5C 5D1 5D2 5D3 5E 5F 5G 5H 5I 5J 5K 5L 5M

ON GOING DRYWALL
3
3A 3B 3C 3D1 3D2 3D3 3E 3F 3G 3H 3I 3J 3K 3L 3M FRAMING INSTALLATION
@ ZONE 1.

UNIT A AWAITING FOR


2 2A 2B 2C 2D1 2D2 2D3 2E 2F 2G 2H 2I 2J 2K 2L 2M DRYWALL FRAMING
INSTALLATION.

1 1A 1B 1C 1D1 1D2 1D3 1E 1F 1G 1H 1I 1J 1K 1L 1M

ONGOING/ TARGET FOR THIS WEEK


DONE
ACCOMPLISHMENT LAST WEEK
ELECTRICAL & AUXILIARY WORKS
PANEL BOARD INSTALLATION

LVL RESIDENTIAL UNITS REMARKS

5 5A 5B 5C 5D1 5D2 5D3 5E 5F 5G 5H 5I 5J 5K 5L 5M ON-GOING

3 3A 3B 3C 3D1 3D2 3D3 3E 3F 3G 3H 3I 3J 3K 3L 3M


UNIT I WAITING FOR
MPF TURN OVER AND
2 2A 2B 2C 2D1 2D2 2D3 2E 2F 2G 2H 2I 2J 2K 2L 2M WALL PLASTERING
WORKS.

1 1A 1B 1C 1D1 1D2 1D3 1E 1F 1G 1H 1I 1J 1K 1L 1M

SUB FEEDER INSTALLATION SLAB WORKS ROUGHING-INS

LEVEL RESIDENTIAL UNITS LEVEL RESIDENTIAL UNITS REMARKS

5 Z1 Z2 Z3 Z4 ROOFDECK Z1 Z2 Z3 Z4 ON-GOING

3 Z1 Z2 Z3 Z4
9 Z1 Z2 Z3 Z4

2 Z1 Z2 Z3 Z4
8 Z1 Z2 Z3 Z4

1 Z1 Z2 Z3 Z4

ONGOING/ TARGET FOR THIS WEEK


DONE
ACCOMPLISHMENT LAST WEEK
ELECTRICAL & AUXILIARY WORKS
EE/AUX GROCERY LIST STATUS

MATERIAL
COMMERCIAL DELIVERY DATE
MATERIALS APPROVAL
STATUS STATUS NEEDED
STATUS

FDAS APPROVED
JAN. 2020
AWAITING FOR BOQ
PARTIAL QTY OF FOR DEVICES
CCTV APPROVED FROM YEK YUE
WIRES ON SITE AND
(AUG. 6, 2019)
EQUIPMENTS
SMS SYSTEM APPROVED

RG6 COAXIAL CABLE APPROVED FOR AWARDING AUG. 20, 2019


SOLIHIYA

EE/AUX P R O G R E S S
P H O T OS

1
ONGOING EE/AUX SLAB ROUGHING
INS @ ROOF DECK ZONE 1 AND 2. 2 3
ONGOING PANEL BOARD
ONGOING EE/AUX BOX SETTING @
INSTALLATION @ 5TH FLOOR ZONE
5TH FLOOR ZONE 3.
3.
PROCUREMENT
Total Packages:
63
No. Packages Completed: 53
Packages In progress:
12
Planned award for this month
07

Upcoming Packages
1. Exterior Painting
SITE INSTRUCTION
2. Water Proofing

Number of SIs for the week 0


Total Number of SIs:
78
Total Number of Closed SIs: 51

DESIGN
Total Issued RFI / RFA
295
Total Closed RFI / RFA
282
SOLIHIYA

CRITICAL ISSUES
SPECIFIC ISSUE MITIGATION PLAN
01 | Delayed delivery of wide 01 | Conduct a joint reconciliation
flange for the accent roof. for the wide flange quantity to ensure the
total quantity required. The required
quantity shall be requested 3 months prior
to date needed since the materials will be
shipped from Manila.

02 | Delayed delivery of 02 | Supplier (ABSS) to deliver the


Mechanical Ducting for Toilet and Kitchen total P.O.ed quantity thru Air Shipment in
Exhausts. order for the contractor to catch up with
the delayed activity and proceed for the
NTP of ceiling enclosure.
SOLIHIYA

ROOF DECK
DESIGN ISSUE
1. Location of drains to be approved, Montgear will submit RFA.
2. Verify plans for the light well glass to be installed by Bradphil.
3. Location for SPF and LPF to be approved, RFA to be submitted by Montgear.

COMMERCIAL ISSUE
1. MRF for structural styro submitted last week.
2. Safety railings contractor not yet awarded.
3. Waterproofing contractor not yet awarded.
4. Pipe chase cover and zocalo contractor not yet awarded

OPERATIONS ISSUE
1. Dowels will provided by OMC for the lightwell zocalo
2. OMC to install dowels for the ACCU pads
3. Bare copper wire to pass through vacant pupe chase near the garbage chute.
4. ACCU frame fabrication to be completed by end of August
5. Provide slope at the back of the pipe chase during topping works to avoid ponding
6. Provide CO for the roof deck
7. Installation of accent roof frames will be done after application of waterproofing.
SOLIHIYA

ELEVATOR
DESIGN ISSUE
1. Risk of the elevator Shaft and Separator beams will not align to KONE’s expectations just like in Buri
2. TCX punchlist might persist if the shaft will not be coordinated well

COMMERCIAL ISSUE
1. Risk on unanticipated materials for the shaft preparation

OPERATIONS ISSUE
1. PMT to temporarily use the elevator for construction after the installation completion