Next Week’s Targets COMPLETION OF EXT CHB LAYING AT 6F Z1 &
02 Aug 5 to 10 ●
Z2
COMPLETION OF FORMS INSTALLATION @ RD
Z1&2
8TH FLR EE RM, WM1&2, 9TH FLR EE RM, WM1 & 2, 9TH FLR EE RM, WM1 & 2, 9TH FLOOR HALLWAY, FE2
GAR., STO.1&2, AUX GAR., STO.1&2, AUX GAR., STO.1&2, AUX & 2ND FE2
FLR LVL HALLWAY EE RM WM 1 GAR. STO1 STO2 AUX WM 2 FE1 FE2 2FE1 2FE2
FINISHING COMPLETED
HANDED OVER AREAS
SOLIHIYA
EXTERIOR 0% 0% 15.957%
CORE 0% 0% 3.793%
SERVICES
FINISHING 0% 0% 2.256%
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
DRYWORKS: 24.597%
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. BUSDUCT AT 3RD FLOOR 1. DONE 1. AWARDED 1. ON GOING FABRICATION
2. PABX AT 3RD FLOOR 2. DONE 2. FOR AWARDING 2. NO WORK YET
3. STRUCTURED CABLING 3. DONE 3. FOR AWARDING 3. NO WORK YET
AT 3RD FLOOR
4. POWER CABLES & WIRES 4. DONE 4. FOR AWARDING 4. NO WORK YET
AT 3RD FLOOR
5. T&B FLOOR TILES AT 3RD 5. DONE 5. DELIVERED 5. NO WORK YET
FLOOR
6. PLUMBING DRAIN AT 6. ADOPT BURI 6. FOR AWARDING 6. NO WORK YET
3RD FLOOR
7. IMC PIPE AT 3RD FLOOR 7. DONE 7. DELIVERED 7. ON GOING 5TH FLOOR
8. HOSE BIBB AT 3RD 8. ADOPT BURI 8. FOR PO 8. NO WORK YET
FLOOR
9. DRYWALL & CEILING 9. ADOPT BURI 9. FOR DELIVERY 9. FRAMING @ 2ND
BOARD AT 3RD FLOOR
10. BALCONY RAILINGS AT 10. ADOPT BURI 10. FOR DP 10. NO WORK YET
2ND FLOOR
11. STAIR RAILINGS AT 3RD 11. ADOPT BURI 11. FOR DP 11. NO WORK YET
FLOOR
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
CORE SERVICES: 3.793 %
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. PANEL BOARDS/ 1. DONE 1. DELIVERED 1. ON GOING @ 5TH
BREAKER AT 2ND FLOOR
2. WATER HAMMER 2. DONE 2. FOR DELIVERY 2. NO WORK YET
ARRESTOR AT 1ST FLOOR
SOLIHIYA
YEAR END PERCENTAGE COMPLETION
FINISHING: 2.256 %
PROCUREMENT
ACTIVITY DESIGN STATUS STATUS OPERATIONS
1. WOOD DOORS AT 2ND 1. DONE 1. FOR 1. NO WORK YET
FLOOR FABRICATION
2. PVC DOORS AT 2ND 2. DONE AS PER BURI 2. FOR PO 2. NO WORK YET
FLOOR
3. WOOD FLOORING AT 3. ON GOING 3. AWAITING 3. NO WORK YET
1ST FLOOR MATERIAL
4. BASEBOARD AT 1ST 4. DONE AS PER BURI SAMPLE FOR 4. NO WORK YET
FLOOR APPROVAL
5. INTERIOR PAINT AT 2ND 5. DONE 4. AWAITING EWF 5. PAINT PREP AT 2ND FLR
FLOOR
5. ON SITE
SOLIHIYA
CONSTRUCTION UPDATE
CONC. WATER-
BEAM & COLUMN PLASTER WALL FLOOR DRY CEILING
LVL CHB TOPPIN PROOFI EXGA
SLAB ING TILES TILES WALL FRAME
G NG
RD 75 12 n/a n/a
9 100 80 75 12
ACTUAL
PLANNED
STRUCTURAL WORKS
CONCRETE POURING
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ROOF DECK
9
8
7
6
5
3
2
1
PODIUM
BASEMENT
LEGEND
ZONE 1 & ZONE 2 ZONE 3 & ZONE 4
ON GOING
FLOOR POURED
PLANNED ACTUAL PLANNED ACTUAL STRIPPED FORMS
SITE PHOTOS
0 0
1 2
Roof deck zone 1 installed slab forms Roof deck zone 2 forms installation
SOLIHIYA
SITE PHOTOS
0 0
3 4
Roof deck zone 1 installed forms for shearwall and PMB forms stripping
slab
STRUCTURAL WORKS
GROCERY LIST SUMMARY
MATERIAL
COMMERCIAL
MATERIALS APPROVAL DELIVERY STATUS DATE NEEDED
STATUS
STATUS
W8 X 35 WIDE FLANGE AS PER BURI NOT YET AWARDED NOT YET DELIVERED NOV 2019
AWARDED TO
ANCHOR BOLTS AS PER BURI DELIVERED AUGUST 2019
SPECIALIZED BOLTS
STEEL PLATES AS PER BURI NOT YET AWARDED NOT YET DELIVERED NOV 2019
AWARDED TO
EVG PANEL AS PER BURI NOT YET DELIVERED JAN 2020
AEDOBE
W8 X 35 WIDE FLANGE AS PER BURI NOT YET AWARDED NOT YET DELIVERED OCTOBER 2019
AWARDED TO COAST
MACTAN STONE AS PER BURI DELIVERED FEB 2020
PACIFIC
STRUCTURAL STYRO AS PER BURI NOT YET AWARDED NOT YET DELIVERED AUGUST 2019
18
ARCHITECTURAL WORKS
MASONRY WORKS
FLR PLANNED ACTUAL PLANNED ACTUAL FLR PLANNED ACTUAL PLANNED ACTUAL
5F Aug 17, 2019 July 15, 2019 Sept 3, 2019 July 30, 2019 2F Sept 17, 2019 Oct 1,2019
3F July 20, 2019 June 15 2019 Aug 3, 2019 July 12, 2019 1F Aug 17, 2019 Sept 3,2019
SOLIHIYA
DRYWALL & CEILING FRAMES AS PER BURI AWARDED TO VIC ON-GOING JUNE 2019
PVC GROOVES & SHADOWLINE AS PER BURI FOR PO FOR DELIVERY JULY 2019
https://docs.google.com/spreadsheets/d/1FYofwPQG1K9mMtlIO_gk-5FGvisS19QNdBtFxcnRG4A/edit#gid=1591526161
21
SOLIHIYA
0
2
0 0
1 3
0
5
0
4
LEGEND
ZONE 1 - ZONE 4
ON GOING WORKS
FLOOR
PLANNED START PLANNED END ACTUAL 50% WATERLINE LAYOUT
6F WETWORKS JULY 19, 2019 MARCH 21, 2019 80% SANITARY LAYOUT
LEGEND
ZONE 1 - ZONE 4
ON GOING WORKS
FLOOR
PLANNED START PLANNED END ACTUAL BALANCE FOR UNITS C,
D2, D3, E, F & L
3F WETWORKS JUNE 6, 2019 DEC 12, 2019 ON GOING DONE FOR BRANCHLINES
LEGEND
ZONE 1 - ZONE 4
ON GOING SLEEVE WORKS
FLOOR
PLANNED START PLANNED END ACTUAL DONE FOR RL/RS &
CDP ONLY
3F WETWORKS JUNE 6, 2019 DEC 12, 2019 ON-GOING
SEPTEMBER,
WATER METER APPROVED AWARDED NO SCHEDULE YET
2020
TARGET AWARDING
SANITARY DRAINS APPROVED NO SCHEDULE YET NOVEMBER 2019
ON JULY 29,2019
WATER HAMMER ARRESTER APPROVED AWARDED NO SCHEDULE YET JULY 30, 2019
SPRINKLERS & VALVES APPROVED FOR AWARDING NO SCHEDULE YET NOVEMBER 2019
EXHAUST FAN FOR APPROVAL FOR AWARDING NO SCHEDULE YET NOVEMBER 2019
28
SOLIHIYA
0
2
0 0
1 3
00
22
00 0
10
1 3
1
ON-GOING PIPE SLEEVING AT 5TH
CROSSMAIN INSTALLED AT 5TH FLOOR
FLOOR ZONE 4
ELECTRICAL & AUXILIARY WORKS
PREVIOUS WEEK ACCOMPLISHMENT
PLANNED ACTUAL VARIANCE
● EE/AUX BOX SETTING @ ● SUB FEEDER/ PULL ● SUB FEEDER/ PULL BOXES
5F UNITS D3/E/M BOXES INSTALLATION @ INSTALLATION AT 5F Z4.
WETWORKS. 5F Z3.
● EE/AUX BOX SETTING @ ● EE/AUXBOX-SETTING AT 5F
● PANEL BOARD INST. @ 5F 5F UNITS A/F/G/H/I/L Z4 WETWORKS.
UNITS A/D3/E/F. WETWORKS.
EE/AUX ● EE/AUX BOX SETTING @ ● EE/AUX BOX-SETTING AT
● SLAB ROUGHING INS @ 3F UNITS A/B/C/D1/D2 3F DRYWORKS
RD Z1. DRYWORKS.
● PANEL BOARD INST. @ 5F ● PANEL BOARD INST. @ 5F
UNITS G/H/I/L. Z4 AND 6F Z1.
● SLAB ROUGHING INS @
RD Z2.
ELECTRICAL & AUXILIARY WORKS
LEGEND:
PLANNED ACTUAL ON GOING, ALMOST 90%
FLOOR
START FINISH START FINISH
DONE FOR WETWORKS
DONE
5F WETWORKS FEB 2019 FEB 2020 FEB 2019 ON GOING
5 ON-GOING
5A 5B 5C 5D1 5D2 5D3 5E 5F 5G 5H 5I 5J 5K 5L 5M PLASTERING GUIDE @
ZONE 3.
LEV
EL RESIDENTIAL UNITS REMARKS
ON GOING DRYWALL
3
3A 3B 3C 3D1 3D2 3D3 3E 3F 3G 3H 3I 3J 3K 3L 3M FRAMING INSTALLATION
@ ZONE 1.
5 Z1 Z2 Z3 Z4 ROOFDECK Z1 Z2 Z3 Z4 ON-GOING
3 Z1 Z2 Z3 Z4
9 Z1 Z2 Z3 Z4
2 Z1 Z2 Z3 Z4
8 Z1 Z2 Z3 Z4
1 Z1 Z2 Z3 Z4
MATERIAL
COMMERCIAL DELIVERY DATE
MATERIALS APPROVAL
STATUS STATUS NEEDED
STATUS
FDAS APPROVED
JAN. 2020
AWAITING FOR BOQ
PARTIAL QTY OF FOR DEVICES
CCTV APPROVED FROM YEK YUE
WIRES ON SITE AND
(AUG. 6, 2019)
EQUIPMENTS
SMS SYSTEM APPROVED
EE/AUX P R O G R E S S
P H O T OS
1
ONGOING EE/AUX SLAB ROUGHING
INS @ ROOF DECK ZONE 1 AND 2. 2 3
ONGOING PANEL BOARD
ONGOING EE/AUX BOX SETTING @
INSTALLATION @ 5TH FLOOR ZONE
5TH FLOOR ZONE 3.
3.
PROCUREMENT
Total Packages:
63
No. Packages Completed: 53
Packages In progress:
12
Planned award for this month
07
Upcoming Packages
1. Exterior Painting
SITE INSTRUCTION
2. Water Proofing
DESIGN
Total Issued RFI / RFA
295
Total Closed RFI / RFA
282
SOLIHIYA
CRITICAL ISSUES
SPECIFIC ISSUE MITIGATION PLAN
01 | Delayed delivery of wide 01 | Conduct a joint reconciliation
flange for the accent roof. for the wide flange quantity to ensure the
total quantity required. The required
quantity shall be requested 3 months prior
to date needed since the materials will be
shipped from Manila.
ROOF DECK
DESIGN ISSUE
1. Location of drains to be approved, Montgear will submit RFA.
2. Verify plans for the light well glass to be installed by Bradphil.
3. Location for SPF and LPF to be approved, RFA to be submitted by Montgear.
COMMERCIAL ISSUE
1. MRF for structural styro submitted last week.
2. Safety railings contractor not yet awarded.
3. Waterproofing contractor not yet awarded.
4. Pipe chase cover and zocalo contractor not yet awarded
OPERATIONS ISSUE
1. Dowels will provided by OMC for the lightwell zocalo
2. OMC to install dowels for the ACCU pads
3. Bare copper wire to pass through vacant pupe chase near the garbage chute.
4. ACCU frame fabrication to be completed by end of August
5. Provide slope at the back of the pipe chase during topping works to avoid ponding
6. Provide CO for the roof deck
7. Installation of accent roof frames will be done after application of waterproofing.
SOLIHIYA
ELEVATOR
DESIGN ISSUE
1. Risk of the elevator Shaft and Separator beams will not align to KONE’s expectations just like in Buri
2. TCX punchlist might persist if the shaft will not be coordinated well
COMMERCIAL ISSUE
1. Risk on unanticipated materials for the shaft preparation
OPERATIONS ISSUE
1. PMT to temporarily use the elevator for construction after the installation completion