Introduction and
About Bosch
Product
Description
• Introduction
• working Principle
Project work • Observations
• Conclusion
Conclusion
Bosch
is German multinational engineering and technology company
headquartered in Germany. The company was founded
by Robert Bosch in 1886.
• Bosch entered India in 1922.
• In 1951, Bosch set up its first manufacturing plant
in Bangalore, India.
• Jaipur Plant is the fourth manufacturing of Bosch Ltd. started
in 1999.
https://www.indiamart.com/proddet https://www.boschautoparts.com/e
ail/bosch-distributor-pumps-ve- n/auto/diesel-parts/nozzles
18437648712.html
Introduction to Nozzle Holder Assembly (NHA)
A fuel injector injects high pressure
atomized fuel in combustion chamber of
engine at required amount.
NR-Nut Visual
Preassembly Pre-setting 1 Pre-setting2 FTB test OUT
torqueing inspection test
figure_assembly_L4_captured
1. PRE-ASSEMBLY:-The Nozzle Holder Body, Shim, spring,
Pressure Bolt, Distance Piece Are Assembled Loosely.
2. PRE-SETING:-on pre-setting work station , get
knowledge of pressure of pre-given basic shim.
3. NR-NUT TORQUING:-tight the NR-Nut 40-50 N-m and
send it for FTB test.
4. FUNCTIONAL TEST BENCH (FTB):-this test done for
1. Opening pressure.
2. Tightness
5. VISUAL INSPECTION TEST:-Inspect the part that
1. Proper rolling or not
2. Part damage or not
3. Part number
4. Go test and no-go test.
• On L4 various parts are run per day or per shift or per weak
and No of part get rejected at pre-setting.
• Various part get have issues of shim and some part get
rejected at FTB
• And very few part get rejected at visual inspection
workstation.
Procedure for finding which type of injector has
lowest FPY or highest rework+ scrap:-
• On excel fill the type of injector and their total good
part, total part, scrap+ rework
• Finding month wise data
• See month wise rework+ scrap %
• Analyze which part has highest rework on pareto chart
• After that finding month wise _part wise analysis
There are last 6 months analysis of different part:-
Feb’19
Apr’19
Trolley
OCM Quality
Trigo having FG store
printer checking
parts
Solution:-
Made a sticker (Q) when the parts will be taken under QMM
inspection it would be there on the trolley showing that the
parts are under QMM inspection so that the person who prints
OCM would not get confused.
Fig. Quality audit sticker implemented
LEARNING GAINS
Exposure to Industrial Environment.
Importance Of Teamwork.
Safety is first priority.
Quality is never compromised.
Co-ordination between different
departments.
References
www.bosch.in
www.boschindia.in
https://www.bosch.in/careers/
https://en.wikipedia.org/wiki/Robert_Bosch_GmbH
https://www.semanticscholar.org/paper/Application-
of-six-sigma