Académique Documents
Professionnel Documents
Culture Documents
AN OVERVIEW
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
Bid parameter – NPV of (Bid Project Cost + 1st year O&M Cost*)
Easier debt servicing by concessionaires during the initial years of project compared to BOT
(Toll) projects
Advantages
Reduced equity investments by developers
Opportunities for IDFs and InvITs for long term investments in the sector post construction
completion with reduced risk perception
Key Highlights
Interactions happened between banks and NHAI regarding few issues in the model with respective
suggestions, which are discussed in later part of the presentation
Project Milestones
II 400th day from Appointed Date* 44% (>= 70% on physical works) 44%
• COD
• Date on which completion/Provisional Certificate is issued
• Provisional Certificate shall be issued after completion of construction works for land given within 180 days of Appointed
Date
• Bonus on early completion
• COD > SCOD by 30 days, Authority pays bonus equal to 0.5% of 60% of Bid Project Cost for every month by which COD
precedes SCOD.
• Payable with 1st Annuity payment
- Cost of Construction
- Interest during Construction
Bid Project Cost - Working Capital
- Physical Contingencies and
- Other Costs, except costs pertaining to variation in Price Index, Change in Law and Change in Scope
Price Index 70% of WPI and 30% of CPI (IW)
For every month occurring after the Appointed Date, the Authority shall compute the variation in Price
Price Index Multiple Index occurring between the Reference Index Date preceding the Bid Date and the Reference Index Date
preceding the date of Invoice, and shall express the latter as a multiple of the former
* Calculated on the basis of weightages for different elements as per Annexure – I of Schedule - G
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
O & M payments
Construction Support
Lump sum financial support in the form of biannual payments
Amount: 40% of Bid Project Cost Computed on the amount quoted by the selected bidder
5 instalments of 8% each Each instalment is the product of amount determined and the PIM
Adjusted for Price Index Multiple
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
1 CONCESSIONAIRE DEFAULT
Payment Milestone Termination Payment
Authority to make Termination
1 NIL Payment to the Concessionaire
2 50% of Debt Due or 5.25% of Bid Project Cost , whichever is lower equal to 65% of the sum of Annuity
Payments remaining unpaid for and
3 60% of Debt Due or 11.70% of Bid Project Cost , whichever is lower
in respect of the remaining
4 70% of Debt Due or 24.00% of Bid Project Cost , whichever is lower Concession Period, including
5 80% of Debt Due or 32.00% of Bid Project Cost , whichever is lower interest up to the Transfer Date
2 NON-POLITICAL EVENT
Payment Milestone Termination Payment Authority to make Termination
1 90% Debt Due or 1.35% of Bid Project Cost , whichever is lower Payment to the Concessionaire
2 90% Debt Due or 9.45% of Bid Project Cost , whichever is lower
equal to 75% of Annuity Payments
remaining unpaid for and in respect
3 90% Debt Due or 17.55% of Bid Project Cost , whichever is lower
of the remaining Concession Period,
4 90% Debt Due or 30.38% of Bid Project Cost , whichever is lower including interest up to Transfer
5 90% Debt Due or 36.45% of Bid Project Cost , whichever is lower Date
1. Termination payments can cover up to 70% of the bid project cost since they are linked to completion cost which is indexed
2. Lenders can hence provide debt funding to the extent of 70% of the Bid project cost
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
Defects Liability after Termination Debt Due definition (as per MCA)
• Concessionaire responsible for 120 days post Termination for Aggregate of the following sums expressed in INR outstanding on the
all defects and deficiencies Transfer Date:
• Obligation of Concessionaire to repair / rectify at its own cost • the principal amount of the debt provided by the Senior Lenders
• 15% of the Annuity Payment due and Payable immediately under the Financing Agreements for financing the Total Project Cost
before the transfer date to be retained in Escrow Account for (the “principal”) but excluding any part of the principal that had
120 days post Termination fallen due for repayment two years prior to the Transfer Date
• On the basis of inspection by Independent Engineer, larger
• all accrued interest, financing fees and charges payable under the
amount might be retained for longer period
Financing Agreements on, or in respect of, the debt referred to in
• Bank Guarantee may be given for the amount specified above
Sub-clause above until the Transfer Date but excluding (i) any
interest, fees or charges that had fallen due one year prior to the
Interest for delay in Termination Payment Transfer Date, (ii) any penal interest or charges payable under the
Financing Agreements to any Senior Lender, and (iii) any pre-
• Termination Payment sue and payable within 15 days of a
payment charges in relation to accelerated repayment of debt except
demand being made
where such charges have arisen due to Authority Default; and
• Interest equal to 3% above the daily average Bank Rate on the
amount of Termination Payment remaining unpaid, provided • any Subordinated Debt which is included in the Financial Package
that such delay shall not exceed 90 days and disbursed by lenders for financing the Total Project Cost
provided that if all or any part of the Debt Due is convertible into Equity
at the option of Senior Lenders and/or the Concessionaire, it shall for the
Debt Due limitation purposes of this Agreement be deemed to be Debt Due even after such
conversion and the principal thereof shall be dealt with as if such
• Shall not exceed 85% of the 60% of Bid Project Cost at any time conversion had not been undertaken;
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
Post-COD: Post-COD:
Maximum of 65% of balance unpaid Since the termination payment in case of
Annuity with interest would be paid in Concessionaire default post COD is 65% of balance
case of termination due to unpaid Annuities, the D/E ratio would be limited to
Concessionaire default 70:30 for 60% of the Bid Project Cost for covering the
debt outstanding.
Suggestion to lenders:
Debt financing could be structured in such a way so
as to ensure that the outstanding debt is fully covered
by termination payment during the entire operations
period.
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions
4 Right of Way: Past experience of road projects suggest Only unencumbered contiguous land with 3H in place
The Authority shall grant vacant access and Right of Way for that in the absence of physical shall be considered for the purpose of 80% on Appointed
at least 80% of the length of the project before Appointed possession of land in terms of area Date and 3E for balance 20%
Date required for construction of at least However, 100% land with 3H in place should be
Appendix to be provided within 90 days from Appointed Date 80% of the length of the project lead to provided within 90 days of Appointed Date
with no damages payable cost and time overruns. Some projects
Construction works for Land given within 180 days from awarded with 3D notified land, and 3G
Appointed Date shall be completed on or before SCOD in process, would delay project
Concern with regards to discontinuous stretch, which affects timelines thereby resulting in cost
construction works, has not been addressed overrun
Hybrid Annuity Model Project Cost Payment Terms Termination Payments Issues & Suggestions