Académique Documents
Professionnel Documents
Culture Documents
ACCOUNTS OFFICE
ORDNANCE FACTORY
VARANGAON
2
Progress till date
3
Wage Shri Prashant Verma, Ishapore
AAO
Progress till date
Details of Personnel Deputed for Training from Factory Side:
Wages NONE
4
Progress till date
The matter regarding expeditious implementation was taken
up with Factory ITC Section vide this office letter no.
AO/OFV/Gen/Corr dated 19.07.2019 asking for providing Data
in CSV/Text format for further follow-up action from Accounts
Side, which however has not materialised till date.
Factory has informed that, pending installation of a new
Server(WEB), it is not possible for them to implement the
packages and have requested for a further three months time,
and the apprehension from Fy side was that the running PPC
server can’t be put to risk.
Matter was brought to the knowledge of the CFA on tour, on
01/08/2019, through a letter given by the Fy side vide no.
2301/ITC/LAO/COMMON DATABASE Dated 30.07.2019
5
6