VOCATIONAL TRAINING AT HARDUAGANJ

THERMAL POWER STATION

Duration: July 3-30, 2014

MOHAMMAD AHMAD SHOEB


FACULTY NO. - 12KEB513
B.TECH. CHEMICAL (IV YEAR),
ALIGARH MUSLIM UNIVERSITY
Overview

Extension Work
Introduction to Thermal Power Division– V,
Company and Plant and its Harduaganj
Plant Operation Thermal Power
Plant
THERMAL POWER PLANT (TPP)

• Converts energy content of an energy carrier (fuel) either into


heat or electricity or both.

• Coal is the largest source of fuel for electricity generation.


• 60.8% of electricity in India is generated from coal (As on 24-08-
2015)*

• Efficiency of conventional TPP: 33-48%.

*Source: ‘Power Sector at a Glance All India’, Ministry of Power, Govt. of India.
UPRVUNL

UPRVUNL (Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd.) is the company handling thermal
power stations of Uttar Pradesh.

Constituted on 25 Aug.1980

TOTAL GENERATING CAPACITY: 5933 MW

Construction Stage: 1320 MW


UPRVUNL
Planning Stage: 7260 MW
5933 MW

Anpara, Obra, Panki, Parichha, Harduaganj,


Sonebhadra Sonebhadra Kanpur Jhansi Aligarh
2630 MW 1288 MW 210 MW 1140 MW 665 MW
HARDUAGANJ THERMAL POWER
STATION

• It is located at Qasimpur Power House Colony - 18 Kms from Aligarh Railway Station.
• All units are coal fired, having a total generating capacity of 665 MW.

Generating capacity Equipment


• * (MW) Manufacturer
5 60
7 105 M/s Bharat Heavy
8 250 Electricals Limited
9 250
Total 665

• The coal to all these units is fed from coal mines of Bharat Coking Coal Limited (BCCL),
Eastern Coalfields Limited (ECL) by means of railway.
• Government decided in July 2014 to add another unit of 660 MW that will be
constructed by Toshiba.
*source: Harduaganj Thermal Power Station. www.uprvunl.org/location_har.htm
SECTIONS OF A TYPICAL TPP

Main Plant
•Boiler
•Turbines
•Generator alongwith associated auxiliaries (Condenser, Superheater, Reheater,
etc.)

Balance of Plants (BOP) system - includes all plants and


equipment other than those included in main plant system.

•Coal Handling Plant


•Ash Handling Plant
•Fuel Oil Handling Plant
•Water Treatment Plant
•Circulating Water System
•Fire Protection System
•Electrical and Control Instrumentation System
•Miscellaneous (Compressors, Hydrogen generation plant, Chimney, etc.)
OPERATION OF TPP

Source: http://indianpowersector.com/power-station/thermal-power-plant/
Diagram of a typical coal-fired thermal power station
Rankine Cycle

A Rankine cycle with a two-stage steam


turbine and a single feed water heater.

Source:
https://en.wikipedia.org/wiki/Thermal_power_
station#/media/File:Feedwater-heating.png

(BFP) (CEP)

Water is heated, turns into steam and spins a steam turbine which
drives an electrical generator. After it passes through the turbine, the
steam is condensed in a condenser and recycled to where it was
heated; this is known as a Rankine cycle.
EXTENTION WORK DIVISION
(EWD-V)

Circulating Water Treatment Hydrogen Fire Protection


Water System Plant Generation Plant system

Cooling Clarified Fire pump


towers water house

Cooling
Booster
water pump DM water
pump house
house

Foam pump
house
Circulating Water System

• Provided for supplying clarified water to the condenser for condensing the LP turbine
exhaust steam.
• May be of once through type or closed type (uses cooling tower).
Cooling Towers:
• Mechanical induced draft type or natural draft type.
• Hot water(60-70˚C) gets cool to 30-35˚C and runs down in forebay.
• For each unit (8 no. & 9 no.) there are 12 cells and 24 risers.
Cooling Water Pumps:
• CW pumps supply cold water from forebay to condenser at flowrate of 36000 mᶟ/h.
• 2 pumps for each unit and 1 common standby pump.
Clarified Water

Cooling
Water Forebay
Pumps

Cooling
Condenser
Tower

Fig. Block Diagram of Circulating


Water System
Water Treatment Plant

• Clarifier Tank:
Water Treatment Plant

• De-mineralised(DM) Water:
• It is exclusively used to generate steam.
Hydrogen Generation Plant
(Generation not started yet)

• 99.9% pure hydrogen gas is used in cooling of generator.


• Current requirement of H2 is met through H2 cylinder.
• Airox Nigen Equipment Pvt. Ltd.
• Electrolysis is used for H2 generation.
Fire Protection System

• Installed by Lloyd Insulation Pvt. Ltd.


• Provided to protect the plant against fire damage to avoid loss of life and
property.
• Clarified water is used for fire fighting service.
• 2 tanks each of capacity 1100 m3 is dedicated for this system.
Fire Pump House:
• 3 Spray pumps (7 kg/cm2). Used in case of electric fires
• 2 Jockey pumps (1.5 kg/cm2). Used to maintain line pressure.
• 2+2 (electric + diesel) hydrant pumps (>7 kg/m3).
Fire Protection System

Booster Pump House:


• Connected in series with hydrant pumps, increases the pressure up to 15
kg/cm2.
• 1+1 electric and diesel.
Foam Pump House:
• A foam tank and a pump.
• Water + foam mixture form aq. film on burning oil surface thereby cutting
O2 supply.
References

1. Harduaganj Thermal Power Station.


www.uprvunl.org/location_har.htm
2. Thermal Power Plant.
www.indianpowersector.com/home/home/thermal-power-plant
3. Thermal power station.
https://en.wikipedia.org/wiki/Thermal_power_station
4. “Standard Design Criteria/ Guidelines for Balance of Plant of 2 X
(500mw or Above) Thermal Power Project”, Central Electricity
Authority, New Delhi, September 2010.