Work Break Down Structure
Shaheen Builders
Hospital Construction
Excavation Interior
Electrical
Roofing Walls Work Plumbing Work Exterior work
Work
concrete
Plastering
concrete Installing plastering
Exterior wires Water lines
foundation walls Tilling
Finishing Installing Glass Work painting
Columns Bath lines
Interior switches
walls Painting
Beams
Finishing
ACTIVITY WORK
P Excavation
Q Foundation
R Column & Beams
S Slab
T Wall
U shelves
V Plumbering
W Electric work
X Plastering
Y Tailing
Z Finish flooring
A Paint
B Windows &ventilators & door installation
C Plumbering work
D Electric work
ACTIVITY IPA
P ---
Q P
R P
S Q,R
T S
U S
V T,U
W T,U
X V,W
Y X
Z Y
A Y
B Z,A
C Z,A
D Z,A
ACTIVITY DURATION E.S E.F L.S L.F T.F F.F
P 7 0 7 0 7 0 0
Q 24 7 31 7 31 0 0
R 20 7 27 11 31 4 4
S 18 31 49 31 49 0 0
T 10 49 59 49 59 0 0
U 3 49 52 56 59 7 7
V 5 59 64 62 67 3 3
W 8 59 67 59 67 0 0
X 14 67 81 67 81 0 0
Y 12 81 93 81 93 0 0
Z 16 93 109 93 109 0 0
A 8 93 101 101 109 8 8
B 4 109 109 109 113 0 0
C 2 109 110 110 113 1 2
D 3 109 110 110 113 1 1