Vous êtes sur la page 1sur 76

ELECTRICITY,AC,LIFTS

1.Ghouse
2.Adulya
3.Sowmiya
4.Venmathi
5.Arun
6.Merzi
Basic Things To know ..
• Transformers
• Substation
• Breaker room
• MV panel
• LV panel
• HT/ LT
• Connected load
• Diversity
• Sanctioned load
• DG set
• Measuring units
• Distribution voltage level
• 1unit electricity
• Load factor and power factor
Transmission of Electricity
from Power Generation
Station
1.In generation Stations by
using energy we can produce
AC Current which means
Alternating Current.
2.AC current has the capacity
to change its direction from
Positive to Negative
Constantly.So it is used most
because of its ability to be
modified by using Transformer.
3.Using Step Up and Step Doun
Transformers Current will
transferred via Transmission
Lines.
4.Finally once the current
Reached the local junctions it
will be transferred for
commercial or Residential Use
Depending on their
Requirements By Using
Distribution Transformers.
Breaker Rooms for
HT/LT
Transformation Transformers
High Voltage And
Safety Purposes

Process At Site Level


1.Depending On The Demand load we can
Afford the Desired amount of electricity
From the government.
MV/HV Panels SubStations
2.After the calculation of load Government
will decide the type of Transformer.For Eg: If
the demand load is Less than 4500 W –LOW
TENSION Transformer.If the Demand Load is
More Than 4500 W – HIGH TENSION
Transformer.
3.If there is a number of transformers in our Rooms
site we have to Transfer the Electricity to the
Breaker room there with the help of VCB
panels we can Trip the whole electricity in
case of any issues 5.Then The Current From the Breaker Room or
Transformer will be Received Through the incoming VCB
4.After that the current from Breaker Room Panels in the SubStation.
will be Transfereed to the Sub-Stations by
using Desired Cables.
6.Then through the Transformer the HV Current is
And the Transferring methods is of reduced to MV current And supplied to the separate MV
two types They are
panels in the Substation ;
1.Overhead Transmission Lines
2.Underground Transmission Lines 7.Then From MV panels Current is Distributed to the
Seperate Junctions in the site.
Electrical Supply @ KARE
In Our Campus Electricity is the major thing that we have to make a note to
understand the large scale closed Electrical Transmission.Let us have a look
Over it…….

HT Transformer Of 11kv Capacity Breaker Room For 3 S.S 11 kv VCB panel Room in SS

KARE Campus MV panels For Distribution 500 KVA Transformer OF 2 nos


DESIGN CONSIDERATION OF ELECTRICAL SYSTEM

1) HT/LTCT transformer
2) Breaker room
3) Substation
• Ht(High tension) panels
• Transformer
• MV(Medium voltage) panels
1) DG sets
HT/ LTCT:
• HT is used when high voltage comes from
step up transformer, voltages ranges from
6.6kV, 11kV, 33kV.
• LTCT is used when voltage comes from
step down transformer around 415kV.
DESIGN:
• Generally at the periphery of the premise
with direct access from the road.
• The base should not be more than 1.7m from
ground.
• BREAKER ROOM
• The breaker room is provided when more than one substation is used.
• Breaker room is provided near ht transformer.

• VCB PANEL BREAKER ROOM LAYOUT


SUBSTATION AND SWITCH ROOM:
LOCATION:
•Availability of power line nearby may be kept in view while deciding location.
•Floor level of substation shall not be the lowest point of the basement
•Should not be located immediately above or below plumbing water tanks, STP, water tanks.
DESIGN CONSIDERATION:
•All doors should be open outward
•Vertical shutters(fire rated rolling shutters) 2.5m widthx3m height
•All room should be provided with partition upto ceiling shall have proper ventilation
• TRANSFORMER
• Types : Oil filled installation and Dry type installation
• Oil filled installation Dry Type installation
Uses liquid as cooling material Uses air as cooling material
Maintenance is more, oil need Low Maintenance, Less contamination
to be sampled to test for contamination. of air.
Suitable for township. Suitable for malls, hospitals, hotels.

Oil filled installation


OIL FILLED INSTALLATION DESIGN :
• Suitable soak pit with gravity flow where uses of more than 9000 litres of oil in any one oil
tank
• Equipment having more than 2000 litres of oil baffle walls of 4 hours fire rating is provided.
• Direct access from outside the building for operation and maintenance.
• Separated from adjoining buildings by atleast 6 mts clear distance to allow passage of fire
tender between substation and adjoining building.
• Separate transformer room is provided.
• DRY TYPE INSTALLATION DESIGN :
• In case electric substation has to be located within the main multi-storeyed building itself
for unavoidable reasons, it shall be a dry-type installation.
• Such substations shall be located on the ground level or on first basement, and shall have
direct access from the outside of the building for operation and maintenance of the
equipment.
• No room for transformer is required in substation.
LAYOUT OF SUBSTATION:
For dry type installation For oil type installation
design consideration of electrical
distribution in highrise buildings
INTRODUCTION

 in an electrical distribution system, one area where savings can be made


and provide the features listed above is in the use of busbar trunking
systems.

 busbar trunking systems are designed to withstand the effects of short-


circuit currents resulting from a fault at any load point in the system, e.g.
at a tap-off outlet or at the end of a busbar trunking run.

METHODOLOGY:

 bus bar trunking system (bbt) preforms the function of transporting


current from one point to the other.
 bus bar trunking installations can be categorised into two basic types:
distribution and feeder. the bus bar trunking unit (btu) is designed to
prevent the propagation of fire and limit the propagation of heat through
building divisions (walls and floors), for a specified time under fire
conditions.
 copper and aluminium are both physically and economically viable for use
as conductors in power bus bar trunking systems (bts). aluminium
conductor is used 630a -6000a. copper conductor is used 630a-7500a.

CONCLUTION:
 The use of busbar will reduce electricity wastage
• EMERGENCY POWER BACKUP SYSTEM : DG
• LOCATION:
• Dg should be as near as substation.
• The emergency power supply (DG) should not be allowed to be installed above ground floor or
below the first basement level of the building.
• If installed in the enclosed space, facilities for forced ventilation shall be provided.
• The generating set should preferably be housed adjacent to MV switchgear in the
substation building to enable transfer of electrical load efficiently.
DG DIMENSION

SIDE VIEW END VIEW


Calculation of electric loads
The calculation
part of electric energy
is one of the most
important to know as
a consumer of
electrical energy.
The units of electricity
varies in its cost and
consumption
depending on its
usage and place of
usage.
Thumb rule calculation for various
typology buildings

1.Connected load is the load connected and used in the particular Area

2.Diversity is thecdifference in the calculated load and the usable load


Demand Calculation
of mixed use township
INTRODUCTION:

 it has on basement, ground cum mezzanine with 13 floors.


 total area of the tower is 3.67lakh sqft

SUB STATION [ HT ROOM EXTERIOR] :


CASE STUDY
ESTANCIA IT PARK  total incoming 33kv,from transformer it reaches ring main gear panel room
which contains circuit breaker and reaches panel room of incomer and
outgoing.
 from main transformer 33kv reaches indoor ht panel room located in
basement.

HT ROOM INTERIOR:

 the consumer ht room is located basement floor.


 with three incomers and one outcomer are coupled, each receiving 33kv
together and transform them to the tranformer 1 in ground level.

TRANFORMER – I :

 capacity of the each transformer – 2500 kva


 incoming 33kv is spliting into 440v and reaches change over panel through
aluminium bus bus duct.
 transfomer -1 is for lighting and hvac for all rooms.
 tranformer make vcb system control socomet
TRANSFORMER – III SUPPLY FOR DATA CENTER:

 capacity of the each transformer – 2500 kva  seperate panel room for ups in the basement 2nos each of
300kva for each floor.
 incoming 33kv is spliting into 440v and reaches change  critical panel for data center 8&4 floor ups date center
over panel through aluminium bus bus duct.
 2 dg power for data center as it required critical power supply
 hormonics panel for contrilling fluctuations 24x7
 eb incomer to ac chiiler in ground level,canteen and
incubatair
DG ROOM:

SWITH GEAR ROOM:


 it has 3 dg each of 2000kva
 sunchronising panel
 it has several outgoing for different services.  feeder 3 for the tower
 pcc1a tower panel [distribution system]  it has 3 no of panels one works for data center, another for
ups and the last one for all the floors lighting and other
 there are two raising mains for air handling unit and services.
lighting power which travels to all the floors.
 immediately after the power down all the generators starts
working and after which senses the usage and cut it down.
SUPPLY FOR HUB ROOM:
LIGHTING:
 emergency lighting for all floors there are 2 ups eah of 60kv
 seprate panel room for ups in the basement 2nos
each of 440kva for each floor.  supply from 1a switch gear for the lifts there are totally 9 lifts
in the tower
 outcome ups of 2 number each of 30kva
 lights used in the tower down lights for lobby spaces – 26w [
 out going panels of 5 cables which has separate 2/2 ]
control for each floor  small lights – 18w
 line voltage 411.2  for restroom -15w
COMPARISON WITH NBC
NBC STANDARDS ESTANCIA IT INFERENCE
PARK
SUB STATION [ HT  Location of substaion Satisfied, as the ht is The substation or exterior ht
should be in basement located in basement room is provided with suffiient
ROOM] – source but for fire safety
purpose sprinkler can be
 300 mm above highest provided as tranformer
level provided with sprinkler

TRANSFORMER  Seperate room in case Satisfied , transformer Transformer has sufficient


of oil tranformer . located in ground level supply for the tower
seperately as it is oil type

SWITCH GEAR ROOM  Switchroom should be Satisfied , switch gear Switch gear room is
provided in ground room is located in provided with all facilities
floor or basement 1 basement 1

DG BACK UP  Dg should not be Satisfied , dg is provided in Dg back can be monitored


located above ground ground level with 100% with monitoring system .
level or below backup
basement level
LIGHTING  For working space 150 Partially satisfied , as Smart lighting can be
lux should be provided lighting has some implemented as it reduce
drawback because of glass energy of building
facade
VERTICAL TRANSPORTATION

• STAIRS
• ELEVATORS
• ESCALATORS
• MOVING WALKWAYS
ELEVATORS /LIFTS:
• Lift is a type of vertical
transport equipment that efficiently
moves people or goods between
floors or levels of a building .
• Lifts are installed into building to
satisfy the vertical transportation
needs of its occupants and visitors
and are necessary by virtue of
human comfort and convenience , or
by statutory regulations.
• It is recommended that a lift be
installed in all type of buildings ,
where a building contain more than
six storeys .
TYPES OF LIFT
• Passenger lifts.
• Goods lifts.
• Hospital lifts.
• Service lifts.

PASSENGER LIFTS:
Passenger lifts are those designed primarily for passengers .
For designing these lifts human comfort and convenience
are given primary considerations.
GOODS LIFTS:

Goods lifts are mainly for the transport of


materials ,but may be required occasionally to
carry passengers.
HOSPITAL LIFTS:

Hospital lifts are installed in hospital/dispensary/clinic and designed to


accommodate one number bed/stretcher along its depth , with sufficient
space all round to carry a minimum of three attendants
in addition to lift operator.
SERVICE LIFTS:

Service lifts (dump-waiter) are those


Lifts , which are exclusively used for carrying
Materials , and shall not carry any person.
Passenger lift Goods lift Hospital lift Service lift
Hospital Carrying
Users Passengers Goods stretchers+3 materials in
sometimes attendants +lift hotels , banks
persons operator. & libraries.

Available
sizes for 4-20 15-26 persons 1sq.m
passengers Height-1.25m
number of
users

Standard 0.7 to 3.0m/s at 0.025 to 0.5 to 1.50m/s 0.25 to 0.5m/s


speeds present in India 1.00m/s

Weight
handling 68 kg/person 500-5000 kg 250kg.
capacity
CLASSIFICATION OF LIFT

ROPE LIFT:
• Low cost.
• Availability from different
manufacturers of reputed class.
• Proven technology.
• Availability for high speed.
• Scope for future research &
development & easy maintenance.
HYDRAULIC LIFT:

• A lift where the vertical movement is done by hydraulic


force.
• They use an underground cylinder, common for low level
buildings
with 2-5floors(up to 6-8 floors)
•Have speeds of up to 1m/s.
•It is advantageous where the machine room cannot be
mounted on roof due to aesthetic reasons but it should be
provided in lift pit.
•The advantage with hydraulic lift is smooth and jerk free
movement.
• The disadvantage with hydraulic lifts is that these are not
suitable for high rise buildings as the horse power
consumed in pumping the hydraulic fluid increases and
become less efficient.
•The chances of bursting of the hydraulic piping and
cylinder also increases.
COMPONENTS OF LIFT

• Control room
• Guides
• Lift car
• Lift car door
• Car rail
• Counter weight
• Control panel
• Lift pit
• Buffer
• Hoist
BASIC DESIGN CONSIDERATIONS OF LIFT:
• The quantity of service required.
• The quality of service desired.
• Determine the number and type of lifts to be provided in a particular building.
•The quantity of service factor , that is , how many people might use the lift system
over a defined period of time is represented by the handling capacity.
• The quality of service factor ,that is , how well the lift system deals with its
passengers is represented by passenger waiting time and lobby queuing.
•These factors are interrelated and depend , among the other things , on the type of
buildings and its use on the type of occupier.
•Both these factors require proper study into the character of building , extent and
duration of peak periods , frequency of service required , type and method of
control , type of landing doors, etc.
• Considerations on estimating the passenger demand and usage patterns and not
only calculating its portable performance.
• Designing and discussing of lift system in a early stage to an (Architect /
Engineer)
Is mandatory.
ETD, Estimated Time to Destination, is a patented ThyssenKrupp Elevator algorithm which can
be used in three modes:
( I ) destination dispatch,
(ii) conventional dispatching with up/down hall call buttons,
(iii) a combination of destination input on busy floors, with conventional hall call buttons on other floors. Improvements have been ma
the ETD optimization function so that it can adjust
the relative importance of waiting and transit times.
LIFT PITS/SHAFT PIT:

• LIFT PITS having depth more than 1.6m shall be provided


TWO CAR ARRANGEMENT:

FOUR CAR ARRANGEMENT

THREE CAR ARRANGEMENT


SIX CAR ARRANGEMENT EIGHT CAR ARRANGEMENT
Information given by an Architect: LIFT SPEED :
ESCALATOR
• An escalator is a power-driven, continuous moving
stairway designed to transport passengers up and down
short vertical distances.
• Escalators are used around the world to move pedestrian
traffic in places where elevators would be impractical.

An escalator consists of top and bottom landing platforms connected by a metal


truss.

TOP PLATFORM BOTTOM PLATFORM


PHYSICAL FACTORS:

• Physical factors like the vertical and horizontal distance to be


spanned must be considered.
• These factors will determine the pitch of the escalator and its actual
length.

LOCATION:

• Escalators should be situated where they can be easily seen by the


general public.
• In department stores, customers should be able to view the
merchandise easily.
• Furthermore, up and down escalator traffic should be physically
separated and should not lead into confined spaces.
TRAFFIC PATTERNS
• Traffic patterns must also be anticipated in escalator design.
• In some buildings the objective is simply to move people from one floor to
another, but in others there may be a more specific requirement, such as
funneling visitors towards a main exit or exhibit.
• The number of passengers is important because escalators are designed to
carry a certain maximum number of people. For example, a single width
escalator traveling at about 1.5 feet (0.45 m) per second can move an
estimated 170 persons per five-minute period.

SAFELY
• Safety is also major concern in escalator design. Fire protection of
an escalator floor-opening may be provided by adding automatic
sprinklers or fireproof shutters to the opening, or by installing the
escalator in an enclosed fire-protected hall.
• To limit the danger of overheating, adequate ventilation for the
spaces that contain the motors and gears must be provided.
• It is preferred that a traditional staircase be located adjacent to the
escalator if the escalator is the primary means of transport between
floors.
TYPES OF ESCALATORS
TYPES OF ESCALATORS
ANGLE OF ESCALATOR

•Designed on an incline of 27.3, 30, 35 degrees.


•If the height is more than 6m than incline of 27.3 should be
given
•The speed of the escalator, shall not be more than 0.63 m/s
for 30o angle of incline and 0.50 m/s for 35o angle of incline.
AIR CONDITIONING SYSTEM

WHY ?
HOW ITS WORK ?
TYPES OF AC SYSTEM
SPLIT AC SYSTEM
SPLIT AC SYSTEM
(TWO PARTS)

OUTDOOR UNIT INDOOR UNIT

 OUT DOOR UNIT, FITTED OUTSIDE THE ROOM,


HOUSES COMPONENTS LIKE COMPRESSOR,
CONDENSORAND EXPANSION VALVE.

 INDOOR UNIT ,COMPRISE THE EVAPURATOR OR COOLING COIL


AND COOLING FAN

 PRESENT DAYS SPLIT UNITS HAVE AESTHETIC LOOKS AND ADD TO THE
BEAUTY OF THE ROOM.
CEILING WALL MOUNTED
MOUNTED
MULTI SPLIT AC SYSTEM
 MULTI SPLITS CONNECTS UP TO FIVE
INDOOR UNITS TO A SINGLE OUTDOOR
UNITS.

 INSTALLS A COMPLETE AIR


CONDITIONING SYSTEM TO MULTIPLE
ZONE INTERIOR SPACES WITH NO NEED
FOR DUCTWORK.

 ENABLE INDOOR UNITS OF DIFFERENT


STYLES & CAPACITIES IN ONE SYSTEM FOR
CUSTOMISED SOLUTIONS UNIQUE TO
EACH RESIDENTIAL SETTINGS
CENTRALIZED AC SYSTEM

CENTRALISED AC PLANT

DX SYSTEM CHILLED WATER SYSTEM


 IN LARGE BUILDINGS USING CENTRAL SYSTEMS , OFTEN INCLUDES
THREE TYPES OF EQUIPMENT ROOMS:

CENTRAL PLANT
EQUIPMENT SPACE BASEMENT

COOLING TOWER ROOF TOP

AIR HANDLING
UNIT IN EACH FLOOR
CENTRALIZED AC SYSTEM
WHAT IS A DX SYSTEM ?
DX SYSTEM – DIRECT EXPANSION SYSTEM

 A DIRECT EXPANSION AIR CONDITIONING UNIT


COOLS INDOOR AIR USING A CONDESED
REFRIGERANT LIQUID.
CHILLED WATER SYSTEM
COMPONENTS
 COOLING TOWER
 CONDENSOR WATER PUMPS
 MAKE UP WATER PUMPS
 CHILLERS
 TES RESERVOIRS

MERITS
 LONG LIFESPAN
 NON CORROSIVE
 NON TOXIC & INEXPENSIVE
 IT HAS SPECIFIC HEAT VALUE

DEMERITS
 CONSUPTION OF WATER IS
HIGH.
 THIS TYPE IS NOT SUITABLE
FOR DRY AREAS.
AIR COOLED CHILLER
BENEFITS OF AIR COOLED CHILLERS
 NO COOLING TOWER
 BETTER ENVIRONMENTAL STABILITY – NO
WATER WASTAGE
 LOW MAINTANANCE COSTS
 EASIER TO OPERATE & CONTROL – TOWER
FREEZING & TOWER BYPASS
ABSENT
 CHEMICAL COST AVOIDED
 WATER COST AVOIDED, EXPECIALLY IN CITIES
 NO WATER PROBLEMS TO DEAL WITH IN CASE
OF DISASTER
SPACIAL REQUIREMENTS
PREFERABLE AIR CONDITIONER FOR TYPOLOGY OF
BUILDING FOR TOWNSHIP
 COMMERTIAL BUILDING
 RESIDENTIAL BUILDING
 INSTITUTIONAL BUILDING
 HOSPITALITY

 FOR COOLING LOADS BELOW 100–125 TONS - THE CHILLER(S) SHALL BE AIR- COOLED.
 A WATER-COOLED SYSTEM ARE RARELY JUSTIFIED ON THE COOLING LOADS BELOW 125
TONS.
 ABOVE 200 TONS PEAK COOLING LOAD, THE WATER-COOLED SYSTEMS BECOME JUSTIFIABLE
DESIGN CONSIDERATION
RECOMMENDED INDOOR TEMPERATURE,RELATIVE HUMIDITY,
AIR VELOCITY
DETAILS OF BUILDING CONSTRUCTION AND ORIENTATION OF
EXPOSURES
OF BUILDING COMPONENTS
FENESTRATION AREA
THERMAL PROPERTIES
SHADING FACTORS
OCCUPANCY- NUMBER OF PEOPLE AND THEIR SHEDULE OF
ACTIVITIES
VENTILATION – REQUIREMENTS FOR FRIESH AIR
INFILITRATION,AIR LEAKAGE
INTERNAL LOAD – EQUIPMENT,COMPUTER/SERVER AND
LIGHTING
EFFECTIVE VOLUME
THUMB RULE FOR AC TUNNAGE
CALCULATION
CALCULATE THE VOLUME OF ROOM IN FEET, DIVIDE IT BY 1000,
THIS WILL GIVE YOU THE REQUIRED CAPACITY IN TR(tons).

ROOM SIZE = 10’X10’


HEIGHT OF ROOM = 10’
AC TON CALCULATION = 10’X10’X10’
=1000 Cu.ft./ 1000
=1 ton
CASE STUDY – ESTANCIA IT PARK
• Estancia IT park was developed by arun excelo Group,it was designed by crn architects and constructed by l & t construction.It
has on basement, ground cum mezzanine with 13 floors. Total area of the tower is 3.67lakh sqft
• The load of the building is 1800 TR which includes the datacenter, tower and all other places.
• The system of air conditioning used is the Water chilled conditioning and packaged units for server rooms
CHILLER UNIT FOR TOWER
• There are four chillers in the ground level along the extent of the site supporting the office building excluding the data centers
and server hub.
• Water source: Raw water tank in the ground level
• Condensation process that converts water to 8 degrees and supplied to the
AHUs of different floors from the basement where the secondary pump is used
to pump the water.
• There are four secondary pumps.
• The return water is 30-31 degrees when it reaches the chiller unit again
where the water is pumped using primary pump.
• The pressure is driven by the variable speed drive (VSD) and it is maintained
either manually or automatic.
CHILLER UNIT – DATA CENTRE (4&8 FLOOR)
 The temperature is set to 14 degree and it is sent to the LCP in the AHU room.
 3 pumps are used which runs in 4 bar pressure.It is controlled by BMS.
 When there is no flow of water in the chiller the flow switch and the actuator indicates that there is no flow of water and the
chiller is shut down automatically.
 Motorized valve or motorized dampers are used to shut the flow.
 Differential pressure switch controls the pressure of the supply and return air which is set to 13.
CASE STUDY – ESTANCIA IT PARK
PACKAGED UNITS
 They are used as an alternative in the server/ hub rooms.The outdoor units r in the terrace.It was fully
operational before setting up PAHU
VRF SYSTEM
 It consists of an outdoor unit paired with several indoor units, copper refrigerant piping and specialized
communication wiring consisting of a two wired cable linking outdoor to all indoor unit.
 The system gets inputs from the user (eg temperature preference) as well as from the natural external
environment (outside ambient temperature)
 The VRF system is more space efficient as it could be connected with up to 64 indoor units, and also
advanced control solution to meet different applications.
 The frequency is 45-50. when it is set in automatic it is controlled by BMS.
FRESH AIR UNITS
• There are 3 fresh air units in the terrace.Supplies fresh air for AHU, Lifts and Staircase.
• The CO2 level is maintained to 1000 PGA in all the floors. When the CO2 level is increased treated fresh air is
supplied.
• Atmospheric air can be given but as the temperature outdoor goes upto 45 degrees only treated fresh air is
used.
DIRECT DIGITAL CONTROL (DDC) SYSTEM
• HVAC controller that operates the direct digital control (DDC) system.
• In a DDC system, a controller is a dedicated computer, which means it is designed to operate only one
specific program.
• An HVAC controller receives information from sensors and sends signals to actuators.
CASE STUDY – ESTANCIA IT PARK
AIR HANDLING UNIT
• AHU is also used for recycling the return air.
• There are 26 AHUs in the building with at least two on each level.
• Each level is divided into 2 zones and each AHU is assigned to one zone depending on the levels of the
building.
• Each AHU unit supplies 12000 CFM (unit of airflow) which supplies 24000 CFM per floor.
• The two AHUs are connected with a plenum so that the flow is equally distributed and there is no variation in
the pressure.
PAHU (precision air conditioners for data centers)
• This unit collects fresh Air from Outside and filtered with G4 type of air filter. The G4 class air filter is made
of synthetic material which is replaceable.)
• The filtered air will travel through the supply ducting and further filtered to AHU ( Air Handling Unit ) .
• This AHU will be assigned to the respective room depend on the temperature and humidity requirement.
• Dampers are used.
FAN COIL UNIT
• Fan Coil Unit is a system similar to AHU but in a smaller scale and the fan speed can be controlled. It serves
the purpose of cooling using chilled water with air flow to the room ensured by one or more electrically
driven fans.
• It is not connected to the duct work, but is used to control the temperature in the space where it is installed.
• FCU is similar to inducting system with the inducting unit replaced by the fan coil.
CASE STUDY COMPARISON WITH STANDARDS
S.NO DESCRIPTION ESTANCIA INFERENCE
1. Refrigerants The refrigerant used in This type is not
Residential, small unitary light the park is R-452B flammable and used
commercial, VRF application — R-22, R- for the precautionary
32, R-410A, R-452B and R-290. system for the data
centre
2. Precision Air Conditioning Provided with the PAC is given 24x7 for
PAHU in the 4th and 8th the maintenance of
floors data centre
3. Type of air conditioning Centralized and
packaged system of
AC(server hub room)
4. Chiller plant 4 nos x 1800 HP Trane The vendor for the
chiller unit is the
predominantly used
vendor for chillers
5. Air flow and filtration Provided with 10m Satisfed
Outside air intakes shall be located at distance
least 8 m away from exhaust stacks,
cooling tower and/or any other
polluting source.
6. Air change per hour for an office should 8 air change / hour is Satisfied
be 6-10 (NBC) maintained

Vous aimerez peut-être aussi