Académique Documents
Professionnel Documents
Culture Documents
1.Ghouse
2.Adulya
3.Sowmiya
4.Venmathi
5.Arun
6.Merzi
Basic Things To know ..
• Transformers
• Substation
• Breaker room
• MV panel
• LV panel
• HT/ LT
• Connected load
• Diversity
• Sanctioned load
• DG set
• Measuring units
• Distribution voltage level
• 1unit electricity
• Load factor and power factor
Transmission of Electricity
from Power Generation
Station
1.In generation Stations by
using energy we can produce
AC Current which means
Alternating Current.
2.AC current has the capacity
to change its direction from
Positive to Negative
Constantly.So it is used most
because of its ability to be
modified by using Transformer.
3.Using Step Up and Step Doun
Transformers Current will
transferred via Transmission
Lines.
4.Finally once the current
Reached the local junctions it
will be transferred for
commercial or Residential Use
Depending on their
Requirements By Using
Distribution Transformers.
Breaker Rooms for
HT/LT
Transformation Transformers
High Voltage And
Safety Purposes
HT Transformer Of 11kv Capacity Breaker Room For 3 S.S 11 kv VCB panel Room in SS
1) HT/LTCT transformer
2) Breaker room
3) Substation
• Ht(High tension) panels
• Transformer
• MV(Medium voltage) panels
1) DG sets
HT/ LTCT:
• HT is used when high voltage comes from
step up transformer, voltages ranges from
6.6kV, 11kV, 33kV.
• LTCT is used when voltage comes from
step down transformer around 415kV.
DESIGN:
• Generally at the periphery of the premise
with direct access from the road.
• The base should not be more than 1.7m from
ground.
• BREAKER ROOM
• The breaker room is provided when more than one substation is used.
• Breaker room is provided near ht transformer.
METHODOLOGY:
CONCLUTION:
The use of busbar will reduce electricity wastage
• EMERGENCY POWER BACKUP SYSTEM : DG
• LOCATION:
• Dg should be as near as substation.
• The emergency power supply (DG) should not be allowed to be installed above ground floor or
below the first basement level of the building.
• If installed in the enclosed space, facilities for forced ventilation shall be provided.
• The generating set should preferably be housed adjacent to MV switchgear in the
substation building to enable transfer of electrical load efficiently.
DG DIMENSION
1.Connected load is the load connected and used in the particular Area
HT ROOM INTERIOR:
TRANFORMER – I :
capacity of the each transformer – 2500 kva seperate panel room for ups in the basement 2nos each of
300kva for each floor.
incoming 33kv is spliting into 440v and reaches change critical panel for data center 8&4 floor ups date center
over panel through aluminium bus bus duct.
2 dg power for data center as it required critical power supply
hormonics panel for contrilling fluctuations 24x7
eb incomer to ac chiiler in ground level,canteen and
incubatair
DG ROOM:
SWITCH GEAR ROOM Switchroom should be Satisfied , switch gear Switch gear room is
provided in ground room is located in provided with all facilities
floor or basement 1 basement 1
• STAIRS
• ELEVATORS
• ESCALATORS
• MOVING WALKWAYS
ELEVATORS /LIFTS:
• Lift is a type of vertical
transport equipment that efficiently
moves people or goods between
floors or levels of a building .
• Lifts are installed into building to
satisfy the vertical transportation
needs of its occupants and visitors
and are necessary by virtue of
human comfort and convenience , or
by statutory regulations.
• It is recommended that a lift be
installed in all type of buildings ,
where a building contain more than
six storeys .
TYPES OF LIFT
• Passenger lifts.
• Goods lifts.
• Hospital lifts.
• Service lifts.
PASSENGER LIFTS:
Passenger lifts are those designed primarily for passengers .
For designing these lifts human comfort and convenience
are given primary considerations.
GOODS LIFTS:
Available
sizes for 4-20 15-26 persons 1sq.m
passengers Height-1.25m
number of
users
Weight
handling 68 kg/person 500-5000 kg 250kg.
capacity
CLASSIFICATION OF LIFT
ROPE LIFT:
• Low cost.
• Availability from different
manufacturers of reputed class.
• Proven technology.
• Availability for high speed.
• Scope for future research &
development & easy maintenance.
HYDRAULIC LIFT:
• Control room
• Guides
• Lift car
• Lift car door
• Car rail
• Counter weight
• Control panel
• Lift pit
• Buffer
• Hoist
BASIC DESIGN CONSIDERATIONS OF LIFT:
• The quantity of service required.
• The quality of service desired.
• Determine the number and type of lifts to be provided in a particular building.
•The quantity of service factor , that is , how many people might use the lift system
over a defined period of time is represented by the handling capacity.
• The quality of service factor ,that is , how well the lift system deals with its
passengers is represented by passenger waiting time and lobby queuing.
•These factors are interrelated and depend , among the other things , on the type of
buildings and its use on the type of occupier.
•Both these factors require proper study into the character of building , extent and
duration of peak periods , frequency of service required , type and method of
control , type of landing doors, etc.
• Considerations on estimating the passenger demand and usage patterns and not
only calculating its portable performance.
• Designing and discussing of lift system in a early stage to an (Architect /
Engineer)
Is mandatory.
ETD, Estimated Time to Destination, is a patented ThyssenKrupp Elevator algorithm which can
be used in three modes:
( I ) destination dispatch,
(ii) conventional dispatching with up/down hall call buttons,
(iii) a combination of destination input on busy floors, with conventional hall call buttons on other floors. Improvements have been ma
the ETD optimization function so that it can adjust
the relative importance of waiting and transit times.
LIFT PITS/SHAFT PIT:
LOCATION:
SAFELY
• Safety is also major concern in escalator design. Fire protection of
an escalator floor-opening may be provided by adding automatic
sprinklers or fireproof shutters to the opening, or by installing the
escalator in an enclosed fire-protected hall.
• To limit the danger of overheating, adequate ventilation for the
spaces that contain the motors and gears must be provided.
• It is preferred that a traditional staircase be located adjacent to the
escalator if the escalator is the primary means of transport between
floors.
TYPES OF ESCALATORS
TYPES OF ESCALATORS
ANGLE OF ESCALATOR
WHY ?
HOW ITS WORK ?
TYPES OF AC SYSTEM
SPLIT AC SYSTEM
SPLIT AC SYSTEM
(TWO PARTS)
PRESENT DAYS SPLIT UNITS HAVE AESTHETIC LOOKS AND ADD TO THE
BEAUTY OF THE ROOM.
CEILING WALL MOUNTED
MOUNTED
MULTI SPLIT AC SYSTEM
MULTI SPLITS CONNECTS UP TO FIVE
INDOOR UNITS TO A SINGLE OUTDOOR
UNITS.
CENTRALISED AC PLANT
CENTRAL PLANT
EQUIPMENT SPACE BASEMENT
AIR HANDLING
UNIT IN EACH FLOOR
CENTRALIZED AC SYSTEM
WHAT IS A DX SYSTEM ?
DX SYSTEM – DIRECT EXPANSION SYSTEM
MERITS
LONG LIFESPAN
NON CORROSIVE
NON TOXIC & INEXPENSIVE
IT HAS SPECIFIC HEAT VALUE
DEMERITS
CONSUPTION OF WATER IS
HIGH.
THIS TYPE IS NOT SUITABLE
FOR DRY AREAS.
AIR COOLED CHILLER
BENEFITS OF AIR COOLED CHILLERS
NO COOLING TOWER
BETTER ENVIRONMENTAL STABILITY – NO
WATER WASTAGE
LOW MAINTANANCE COSTS
EASIER TO OPERATE & CONTROL – TOWER
FREEZING & TOWER BYPASS
ABSENT
CHEMICAL COST AVOIDED
WATER COST AVOIDED, EXPECIALLY IN CITIES
NO WATER PROBLEMS TO DEAL WITH IN CASE
OF DISASTER
SPACIAL REQUIREMENTS
PREFERABLE AIR CONDITIONER FOR TYPOLOGY OF
BUILDING FOR TOWNSHIP
COMMERTIAL BUILDING
RESIDENTIAL BUILDING
INSTITUTIONAL BUILDING
HOSPITALITY
FOR COOLING LOADS BELOW 100–125 TONS - THE CHILLER(S) SHALL BE AIR- COOLED.
A WATER-COOLED SYSTEM ARE RARELY JUSTIFIED ON THE COOLING LOADS BELOW 125
TONS.
ABOVE 200 TONS PEAK COOLING LOAD, THE WATER-COOLED SYSTEMS BECOME JUSTIFIABLE
DESIGN CONSIDERATION
RECOMMENDED INDOOR TEMPERATURE,RELATIVE HUMIDITY,
AIR VELOCITY
DETAILS OF BUILDING CONSTRUCTION AND ORIENTATION OF
EXPOSURES
OF BUILDING COMPONENTS
FENESTRATION AREA
THERMAL PROPERTIES
SHADING FACTORS
OCCUPANCY- NUMBER OF PEOPLE AND THEIR SHEDULE OF
ACTIVITIES
VENTILATION – REQUIREMENTS FOR FRIESH AIR
INFILITRATION,AIR LEAKAGE
INTERNAL LOAD – EQUIPMENT,COMPUTER/SERVER AND
LIGHTING
EFFECTIVE VOLUME
THUMB RULE FOR AC TUNNAGE
CALCULATION
CALCULATE THE VOLUME OF ROOM IN FEET, DIVIDE IT BY 1000,
THIS WILL GIVE YOU THE REQUIRED CAPACITY IN TR(tons).