source of power supply to all the station auxiliary loads including loads supplied from emergency power supply system. This system derives power from two different sources of supply. The two sources are as follows: a) From the inter-connected grid of 220 kV through two numbers of 220kV/6.9kV/6.9kV start-up transformers (SUTs) located in the transformer yard. b) From the terminals of the main generator through two numbers of 21kV/6.9kV/6.9kV Unit transformers (UT) with GCB closed and from 400 kV grid through GT and UT combination with GCB open. This system has two voltage levels at:
(i) 6.6kV, 3 phase supply for motors above 200
kW rating. (ii) 415V, 3 phase supply for motors below 200 kW rating. 6.6kV system consist of four buses C41-C44. Buses can derive power either from UT or from SUT. Whenever there is a failure in one of the sources due to fault, auto transfer will be initiated and supply from the healthy source will be extended to these buses. From here onwards we will discuss about class-III power supply system as i was involved in erection and commissioning of class-III system. The 415V, Class-IV Power supply is obtained through 6.6kV/433V, 3 phase auxiliary transformers connected to 6.6kV Class IV System buses. Class-IV, 415V switchgear and Auxiliary Transformers are located inside Turbine Building electrical bay at elevation 100M. Class-III power supply system feeds the power to the loads, which can tolerate short time interruption up to two minutes. This system supplies power at two voltage levels.
a) 6.6kV Class-III power supply system.
b) 415V Class-III power supply system. This system derives its power from Class-IV 6.6kV system under normal operating conditions. Class III, 6.6kV consists of buses C31, C33, C32 & C34. Buses C-31 and C-33 are grouped sub- division-IA and sub-division-IB under Division-I and C-32 and C-34 are grouped sub-division-IIA and sub-division-IIB under Division-II for distributing the redundant loads. In each division buses are provided with tiebreakers and these ties are closed in case of loss of supply to the any of the buses through EMTR. Each division in this system consists of two DG sets and associated switchgear. Any one DG set out of 4 can meet 100% emergency load. The system is designed to supply 6.6KV AC, 3 phase, 3 wire, 50Hz with a voltage variation of ±10%, frequency variation of ±5% and combined voltage and frequency variation of ±10%. Maximum voltage dip is limited to 20% so that motor can develop adequate torque to prevent stalling during starting. This system derives its power from Class-III 6.6 kV system through auxiliary transformer. This system consists of busesD31 to D34 located in SABs and PMCCs D35 to D38 located in Safety Related Electrical House (SREH). Buses D31 to D34 are fed from Class-III 6.6 kV system through 2 MVA, 6.6kV/433V Class-III auxiliary transformers. PMCCs D35 to D38 are also fed from Class-III 6.6kV system through 1MVA, 6.6kV/433V Class-III auxiliary transformers. Buses D31& D33 are grouped into sub- division-IA and sub-division-IB under Division-I and D32 & D34 are grouped into sub-division-IIA and sub-division-IIB under Division-II. Each division is provided with one standby transformer. Thus Division-I comprises TR-1, 3 and 5, and Division-II comprises TR-2, 4 and 6. The logics ensure that only one class-III bus is connected to the standby auxiliary transformer at a time. In the event of failure of main auxiliary transformer, transfer to standby auxiliary transformer is done automatically. The system/equipment will be designed to supply 415V AC, 3phase, 4 wire, at 50Hz with a voltage variation of ±10%, frequency variation of ±5% and combined voltage and frequency variation of± 10%. 415V standard supply is selected for motors less than 200KW. Maximum voltage dip is limited to 20% so that motors can develop adequate starting torque to prevent stalling during starting. Short circuit withstand current rating 44 kA for 1 second and making current 11OkA peak. Two trip coils will be provided for all breakers so that with one trip coil failure breaker can be tripped and these are fed from two different DC batteries. All the breakers will be draw out type and electrically operated. Vacuum CBs will be used. Switchgear has local control, indication, protection and metering devices and facilities for remote control, metering and alarm annunciations. Feeders for motors have surge suppressors to limit switching over voltages. The normal input will be 415 V AC+/- I 0%, 3 phase, 4 wire, 50 Hz+/- 5%. Short circuit withstand current rating 50 kA for I second and making current 105kA peak. All the breakers will be draw-out type and electrically operated. Air circuit breakers will be used. Indoor metal enclosed switchgear with air break type circuit breakers / Air Break contactors/ Moulded Case Circuit Breakers / Switch fuse units are provided for MCC feeders. MCCs have local/remote control as per the process requirements, indication, protection and metering devices and facilities for control, metering and alarm annunciations. Verify the route from unloading spot to erection spot for free access. Check the location of Switchgear/MCC/PMCC, identify the EPs, as given in the equipment layout drawing. Ensure correct panel and complete section of each unit is received as per drawing and its being taken to its correct destination at site. Panels shall be tied as necessarily to prevent the movement of the panels. After reaching at nearest to erection spot, unload the MCC/PMCC/Switchgear panels using crane/hydra. Shift the panels by putting skid rollers/ rolling pipes under the wooden pallet and by pushing the panel manually up to the erection spot. Clean the EPs and check the EP for levelling with water level . The base frame shall be placed over EPs as per approved GA drawing. The base frame shall be checked for grid reference / clearance from wall or column as per approved drawing. Check for verticality, alignment & levelling of base frame. If the gap exist between base frame and EP shim plates should be used to achieve the uniform level between base frame and EP. Welding shall be done as per the approved drawing and subject to dye penetration test. Base frame height shall be 150mm for class- III switchgear. All welded areas of EP and base frame shall be touch up with primer and enamel paint. Gap between base frame and EP shall be filled with dry packing. Shift the panels on the welded base frame. Weld the panels for 6.6kV switchgear and bolt the panels and base frame for 415V switchgears and MCCs. Check for front view and sequence, it should match with GA drawing. Gasket between adjacent panels should be ensured and tighten the inter panel coupling bolts. Clean the contact surface of phase, neutral and earth bus bars at the side of each switchgear and MCC and apply electrical contact grease on their surfaces. Couple the bus bars of adjacent units and with bus bar links and necessary hardware. Tighten all the bus bar joints, fasteners using torque ranch. Apply torque of value as per manufacturer recommendation. Provide earthing to panels as per the drawing. Connect the inter panel wiring between adjacent units of panel as per the interconnection scheme. Check the tightness of mounting of panels. Place the transformer over the EPs as per the GA drawing and align. Match holes of flange that will connect with 415V switchgear and MCCs. Mark the holes for anchoring ‘A’ frame and roller frame assembly. Shift the transformer and drill the holes for anchor fasteners. Once again place the transformer over EP. Match holes of flange, ‘A’ frame and roller frame assembly. Fix and tighten nut & bolts of transformer. Tighten all anchor fasteners that are used for ‘A’ frame assembly and roller frame assembly. Welding of enclosure has to be carried out. Earthing shall be provided to the enclosure and neutral bushings. Compare name plate details with the specifications. Check for any physical damage/ hair crack on HV and LV post insulators. Check the tightness of all bolts, clams and connecting terminals. Check earthing of transformer supporting structure/ enclosure and neutral terminals. Check the BOM in the drawing with equipment/ component provided in the panel. Compare panel number, NPC panel designation, feeder description and their sequence, VCB number etc for switchgears. Compare panel number, feeder description, feeder number etc with drawing for MCC. Check and verification of panel and its component mounted inside for transit damage. Check proper connection and termination of internal wires. Clean the panel fully and provide lubrication on moving parts. Check all the earth connections are connected properly. Use a torque wrench and set it to the specified torque value for each size of fasteners as per manufacturers recommendation and then check the continuity for bus bars of phase neutral and earth from one end to another end. Inspect and clean all bus supporting insulators and confirm for no damage. Inspect that external earthing is provided to switchgear and MCC as per the earthing drawing. Verify the welding as per the approved drawing and the quality of the welding. Take insulation resistance of the bus bars with 500V insulation tester for MCC. Take insulation resistance of the bus bars with 5kV Insulator tester before and after HV test. Rack out all the CBs and PTs. Conduct HV test at a voltage specified by the manufacturer for switchgears. Open all doors, panels, removable covers, check for their freeness and gasket is provided all around them. Check all the clearance between phase to earth and phase to phase.