03
MILESTONE 3
Finish dinding, & aci
Finish façade, & atap
01
MILESTONE 1 04
MILESTONE 4
Erection equipment
Start install equipment
02
MILESTONE 2
Finish steel structure
Finish cable room
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Durasi Pekerjaan
Description Start Finish Days
Instal equipment 17-Feb-20 2-Mar-20 14
Instal gland box 3-Mar-20 24-Mar-20 21
Instal cable tray 25-Mar-20 15-Apr-20 21
Instal grounding 24-Feb-20 23-Mar-20 28
Pulling cable 16-Apr-20 7-May-20 21
Glanding 8-May-20 29-May-20 21
Terminasi 30-May-20 13-Jun-20 14
TOTAL 17-Feb-20 13-Jun-20 117