Académique Documents
Professionnel Documents
Culture Documents
For discussion
● Most contracts provide for retention ○ Employer may utilise monies for its
sum (usually 5%) own purposes
Contractually: ● JKR
○ Contractor’s beneficial interest subject to ● Even though PAM provides for contractors
deductions certified by Architect to demand for monies to be held in trust
account, it is extremely rare for contractors
○ Contractor can demand for monies to be
held in trust account at its cost to do so. Why do you think that is so?
● CIDB
Retention Monies- must it be
in a separate account? (4)
● Contractor sought declaration retention ● So, how would you argue against the
monies were held in trust Employer in this case?
Retention Monies- must it be
in a separate account? (5)
Case Law: Qimonda Malaysia Sdn Bhd (in ● No issue of preferential treatment because
liquidation) v Sediabena Sdn Bhd & Anor retention monies do not belong to Employer
[2012] 3 MLJ 422, CA in the first place
● Express clause not a precondition of trust- So, how would you decide if you were the
can be by operation of law panel?
Case Law: Qimonda Malaysia Sdn Bhd (in ● No requirement to be held in separate
liquidation) v Sediabena Sdn Bhd & Anor account or Contractor must make such
[2012] 3 MLJ 422, CA request. Contractor may not want to
jeopardise relationship/applied its mind
Held by the Court:
● Failure to separate monies cannot defeat
● Property in retention sum resides with the trust. Release or preservation of monies
Contractor and is held by Employer in trust after liquidation is not preferential treatment
because monies do not belong to Employer
● Retention Sum already earned by
Contractor for works already done- mere ● Allowing retention to be part of general
provision for making good defects. Even if funds would unjustly enrich other creditors
mixed in common fund, is traceable
Back to Back Payments (1)
● Back-to-back
● Pay if paid
Back to Back Payments (2)
Case Law: UDA Holdings Bhd v Bisraya ● CIPAA as new procedural legislation
Construction Sdn Bhd & Anor and introduces new forum, and no vested
another case [2015] 11 MLJ 499, HC rights under law affected, so can apply
retrospectively
Held by Court:
● Section 35 CIPAA is merely
● “Substantive rights” are not vested by declaratory in nature
written law but merely in contracts
● In any case, if conditional payment
● Rights not accrued, vested or acquired defence is allowed, it would defeat
save for pending liti/ arb preserved CIPAA
under s41
Right of Contractor to
Suspend, Go Slow and
Terminate (1)
For Discussion
Outside the scope of CIPAA, the Contractor ● Contractor may also terminate the
would have to rely on contractual provisions contract for failure to pay certified
or common law principles sums or obstruction from issuance of
certificates by Employer
For example, PAM:
● Note: Going slow is not provided in all
● Failure to pay certified sums allows contracts. If not provided, it would
Contractor to suspend works after 14 seem a riskier approach because time
days’ notice continues to run leading to potential
issues with delay/LAD
Right of Contractor to
Suspend, Go Slow and
Terminate (4)
Case Law: Kah Seng Construction Sdn ● On basis of estimated costs for
Bhd v Selsin Development Sdn Bhd defective works and LAD, Employer
[1997] 1 CLJ Supp 448, HC withheld payment of later certificates
● Contractor made claims progressively So how would you decide if you were the
and certificates were issued judge in this case?
Right of Contractor to
Suspend, Go Slow and
Terminate (5)
Case Law: Shen Yuen Pai v Dato Wee ● But for issuing certificates, Architect is
Hood Teck & Ors [1976] 1 MLJ 16 independent authority
● This case discussed, inter alia, the ● Architect owes duty of care not to
position of the Architect’s Final issue final certificate unless satisfied
Certificate with work. Once issued, final cert is
conclusive
Held by Court:
● Form of cert depends on contract
● Architect is owner’s agent to give terms. If no form is prescribed,
instructions for works Architect can determine the form.
Interim, Penultimate and Final
Certs (4)
c.f. Thamesa Designs Sdn Bhd & Ors v Certificate of final payment issued by
Kuching Hotels Sdn Bhd [1993] 3 MLJ consultant authorizing deduction of
25, SC LAD is invalid and not binding on
parties
Held:
LAD which was deducted from retention
Employer handed over site late to fund must be restored
contractor
Note: Article by Vinayak Pradhan questions
Employer therefore not entitled to LAD case- Shen Yuen Pai not brought to
Court’s attention
Revision of certificates (1)
PAM: CIDB:
For discussion:
● JKR contracts provide for direct ● Section 30 CIPAA allows for requests
payment to nominated sub-contractors to be made to principal for direct
payment of adjudicated sum
● Even in non-JKR contracts, some
NSCs require direct payment when ● But there is no provision for
nominated- usually by a side letter or consequences to principal who fails to
supplemental agreement comply
Thank You
khenghoe@khenghoe.com