Vous êtes sur la page 1sur 28

Practical Construction

Law for Practitioners


- Payments
Chan Kheng Hoe
Topics Covered

● Must retention sum be in separate account?

● Can sub-contract provide for back-to-back


payments?

● Can contractor suspend, go slow or


terminate due to non-payment?

● Difference between interim, penultimate and


final certs?

● Can certificates be revised?


Retention Monies- must it be
in a separate account? (1)

For discussion

Why is this question important?


Retention Monies- must it be
in a separate account? (2)

Why is this question important? ● If not set aside in separate account:

● Most contracts provide for retention ○ Employer may utilise monies for its
sum (usually 5%) own purposes

○ Monies at risk if employer enters into


● Usually released in 2 moiety
liquidation before full release
○ 1st moiety upon CPC
○ Employer may be indebted to other
○ 2nd moiety upon CMGD creditors whose claim may affect the
monies held
Retention Monies- must it be
in a separate account? (3)

Contractually: ● JKR

● PAM ○ No retention sum - use of performance bond


instead
○ Employer has fiduciary duty as trustee of
money to Contractor For discussion:

○ Contractor’s beneficial interest subject to ● Even though PAM provides for contractors
deductions certified by Architect to demand for monies to be held in trust
account, it is extremely rare for contractors
○ Contractor can demand for monies to be
held in trust account at its cost to do so. Why do you think that is so?

● CIDB
Retention Monies- must it be
in a separate account? (4)

Case Law: Qimonda Malaysia Sdn Bhd (in Employer’s Arguments:


liquidation) v Sediabena Sdn Bhd & Anor
[2012] 3 MLJ 422, CA ● Contract does not provide for a trust

Facts: ● Retention sum not set aside in separate


account (no request by Contractor either)
● Employer voluntarily wound up
● Contractor filed proof of debt as creditor-
● Did not release in excess of RM6m of claim as trust money would be preferential
retention sum to contractor & sub-con treatment of Contractor as a creditor

● Contractor sought declaration retention ● So, how would you argue against the
monies were held in trust Employer in this case?
Retention Monies- must it be
in a separate account? (5)

Case Law: Qimonda Malaysia Sdn Bhd (in ● No issue of preferential treatment because
liquidation) v Sediabena Sdn Bhd & Anor retention monies do not belong to Employer
[2012] 3 MLJ 422, CA in the first place

Contractor’s Arguments: ● Filing of proof of debt as an estoppel is an


afterthought and non-issue, and is without
● Retention monies, by nature, are trust prejudice to Contractor’s claim for retention
monies sum as trust money

● Express clause not a precondition of trust- So, how would you decide if you were the
can be by operation of law panel?

● Employer is fiduciary to the trust


Retention Monies- must it be
in a separate account? (6)

Case Law: Qimonda Malaysia Sdn Bhd (in ● No requirement to be held in separate
liquidation) v Sediabena Sdn Bhd & Anor account or Contractor must make such
[2012] 3 MLJ 422, CA request. Contractor may not want to
jeopardise relationship/applied its mind
Held by the Court:
● Failure to separate monies cannot defeat
● Property in retention sum resides with the trust. Release or preservation of monies
Contractor and is held by Employer in trust after liquidation is not preferential treatment
because monies do not belong to Employer
● Retention Sum already earned by
Contractor for works already done- mere ● Allowing retention to be part of general
provision for making good defects. Even if funds would unjustly enrich other creditors
mixed in common fund, is traceable
Back to Back Payments (1)

Commonly known as:

● Back-to-back

● Pay when paid

● Pay if paid
Back to Back Payments (2)

Not so much an issue any longer. For discussion:

Section 35(1) CIPAA ● Are conditional payment clauses in


construction contracts entered into
● Renders conditional payment prior to CIPAA void?
provisions void
● Wouldn’t a retrospective application of
CIPAA be an interference with vested
interests/rights?
Back to Back Payments (3)

Case Law: UDA Holdings Bhd v Bisraya Important Consideration:


Construction Sdn Bhd & Anor and
another case [2015] 11 MLJ 499, HC ● CIPAA not only introduces
adjudication but also affects
Central Issue: Whether CIPAA applies to substantive rights, including:
payment disputes and their underlying
○ Right of Contractor to suspend works
contracts which arose before the coming
into force of CIPAA ○ Right of Contractor to demand direct
payment from principal

○ Prohibition of conditional payments


Back to Back Payments (4)

Case Law: UDA Holdings Bhd v Bisraya ● CIPAA as new procedural legislation
Construction Sdn Bhd & Anor and introduces new forum, and no vested
another case [2015] 11 MLJ 499, HC rights under law affected, so can apply
retrospectively
Held by Court:
● Section 35 CIPAA is merely
● “Substantive rights” are not vested by declaratory in nature
written law but merely in contracts
● In any case, if conditional payment
● Rights not accrued, vested or acquired defence is allowed, it would defeat
save for pending liti/ arb preserved CIPAA
under s41
Right of Contractor to
Suspend, Go Slow and
Terminate (1)

For Discussion

Based on general principles of law, do you


think that a contractor has the right to
suspend works, go slow on works, or even
terminate the contract for failure of the
Employer to make timely progress
payments?
Right of Contractor to
Suspend, Go Slow and
Terminate (2)

100% Safe Approach ● When he does so, the Contractor:

Section 29 CIPAA ○ Is not in breach of contract

● Contractor may suspend works or ○ Is entitled to reasonable EOT


reduce rate of progress after 14 days’
○ Is entitled to recover loss and
notice if adjudicated sum is not paid expenses

○ Must resume work within 10 working


days after being paid
Right of Contractor to
Suspend, Go Slow and
Terminate (3)

Outside the scope of CIPAA, the Contractor ● Contractor may also terminate the
would have to rely on contractual provisions contract for failure to pay certified
or common law principles sums or obstruction from issuance of
certificates by Employer
For example, PAM:
● Note: Going slow is not provided in all
● Failure to pay certified sums allows contracts. If not provided, it would
Contractor to suspend works after 14 seem a riskier approach because time
days’ notice continues to run leading to potential
issues with delay/LAD
Right of Contractor to
Suspend, Go Slow and
Terminate (4)

Case Law: Kah Seng Construction Sdn ● On basis of estimated costs for
Bhd v Selsin Development Sdn Bhd defective works and LAD, Employer
[1997] 1 CLJ Supp 448, HC withheld payment of later certificates

Facts: ● Contractor suspended works and sued


for payment. Employer counterclaimed
● There was no formal contract for damages.

● Contractor made claims progressively So how would you decide if you were the
and certificates were issued judge in this case?
Right of Contractor to
Suspend, Go Slow and
Terminate (5)

Case Law: Kah Seng Construction Sdn ● There is no intermediate right to


Bhd v Selsin Development Sdn Bhd suspend works
[1997] 1 CLJ Supp 448, HC
● Any suspension becomes a
repudiatory breach by the Contractor
Held:
In Conclusion, how would you advise a
● Contractor can elect to terminate if Contractor client who wants to suspend
there is repudiatory breach by works for non-payment?
Employer or to affirm the contract and
proceed with works
Interim, Penultimate and Final
Certs (1)

Interim certificates: Final certificate:

● Issued progressively to estimate ● Issued at end of contract period to


amount and value of work carried out verify final amount due (after CMGD)
and payment due to Contractor
The effect and conclusiveness of the
Penultimate certificate: certificate largely depends on the
contractual terms, but even a “conclusive”
● Issued after completion and before certificate may be reviewed by an arbitrator
final certificate- usually after CPC to or challenged before a judge.
facilitate release of retention sums
Interim, Penultimate and Final
Certs (2)

Example of Contractual Term in PAM:

● Final Certificates are conclusive with


regard to the final value of the works
carried out

● But not conclusive that any work,


materials, goods and designs are in
accordance with the Contract
Interim, Penultimate and Final
Certs (3)

Case Law: Shen Yuen Pai v Dato Wee ● But for issuing certificates, Architect is
Hood Teck & Ors [1976] 1 MLJ 16 independent authority

● This case discussed, inter alia, the ● Architect owes duty of care not to
position of the Architect’s Final issue final certificate unless satisfied
Certificate with work. Once issued, final cert is
conclusive
Held by Court:
● Form of cert depends on contract
● Architect is owner’s agent to give terms. If no form is prescribed,
instructions for works Architect can determine the form.
Interim, Penultimate and Final
Certs (4)

c.f. Thamesa Designs Sdn Bhd & Ors v Certificate of final payment issued by
Kuching Hotels Sdn Bhd [1993] 3 MLJ consultant authorizing deduction of
25, SC LAD is invalid and not binding on
parties
Held:
LAD which was deducted from retention
Employer handed over site late to fund must be restored
contractor
Note: Article by Vinayak Pradhan questions
Employer therefore not entitled to LAD case- Shen Yuen Pai not brought to
Court’s attention
Revision of certificates (1)

PAM: CIDB:

● Architect cannot revise payment ● Superintending Officer can by any


certificates except for clerical, Interim Certificate correct any error in
computational and typographical previous Interim Certificate and adjust
errors amount due to account for any under
or over valuation
● But Architect can by a subsequent
certificate correct or modify any
valuation errors in earlier certificates
Revision of certificates (2)

Case Law: Fairweather Ltd v Asden ● After issuing Final Certificate,


Securities Ltd (1979) 12 BLR 40 Architect was functus officio and
precluded from issuing further CNC
Facts:
cf. Bukit Cerakah Development Sdn Bhd v
● After issuing Final Certificate, L’Grande Development Sdn Bhd [2008] 3
Architect subsequently issued CNC MLJ 547, CA held:

Held by Court: ● It is a question of construction and not


a question of general law as to
whether an Architect is functus
Claims for Direct Payment (1)

For discussion:

Can a sub-contractor make a claim for


direct payment from the Employer?

Would your answer be different if it was a


nominated sub-contractor?
Claims for direct payment (2)

General Principle: Privity of Contract Exceptions:

There is no privity of contract between a ● Contractual exceptions (eg JKR


subcontractor and an Employer to allow a contracts)
direct claim
● Statutory exceptions (CIPAA)
Claims for direct payment (3)

Contractual Exceptions Statutory Exception

● JKR contracts provide for direct ● Section 30 CIPAA allows for requests
payment to nominated sub-contractors to be made to principal for direct
payment of adjudicated sum
● Even in non-JKR contracts, some
NSCs require direct payment when ● But there is no provision for
nominated- usually by a side letter or consequences to principal who fails to
supplemental agreement comply

● Must be agreed to by the Main ● So what can be done if principal fails


Contractor to comply?
Claims for direct payment (4)

Practical Problems with Direct Payment ● This issue arose in:

● Potentially creates a collateral contract ○ Joo Yee Construction Pte Ltd v


between sub-contractor and Employer Diethelm Industries Pte Ltd & Ors
[1990] 2 MLJ 66, HC (S’pore)
(would it subject Employer to potential
adjudication claims?) ● Direct payment to sub-contractor may
not have taken into account defects or
● Potentially an undue preference of the
delays, leaving main contractor
sub-contractor as an unsecured
saddled with all defects and LAD
creditor in the event of insolvency of
claims by Employer
Main Contractor
That’s all Folks!

Thank You

Chan Kheng Hoe

khenghoe@khenghoe.com

Vous aimerez peut-être aussi