Académique Documents
Professionnel Documents
Culture Documents
PROJECT
In The Name of Allah
The Most Beneficent The Most Merciful
Project Background
WAPDA identified 26 potential Hydropower Project (HPP)
sites in Northern Areas. Dasu HPP is one of the identified sites
on run-of-river Indus with total capacity of 4320 MW.
Page 2 of 11
Project Background (Cont’d)
Based upon the enhanced generating capacities of Dasu and
other downstream Hydro Power Projects, Techno-Economic
Studies, as well as limitation on the available corridors in the
difficult mountainous terrain, M/s. KEPCO recommended 765
kV voltage level for the project which was also supported by
Independent Panel of Experts (IPoEs) and the World Bank.
Page 11 of 11
Proposed Route for 765kV Transmission Line
Page 8 of 11
Location of the Project
Page 5 of 11
Scope Of Work
Design of 765 kV Double Circuit 250 Km long
Transmission Line (Tower Design, Conductor and
Insulator Optimization etc.)
Geo-Technical Assessment Studies for Transmission Line
Design of two 765/ 500/220 kV Substation
1. Islamabad West Substation
2. Mansehra Substation
Environmental and Social Impact Assessment (ESIA)
Studies and Resettlement Action Plan (RAP) for whole
Transmission Line and two Substations
Page 11 of 11
Technical Details
• Length of Line: 250 Km (Dasu to Islamabad)
• Conductor:
2. Inception Report
Finalized
Page 6 of 11
Progress Status (Cont’d)
S.No
.
Description Status
5. Geo-Technical 25 out of 77 boreholes are
Assessment done on site
Page 7 of 11
Economic Evaluation of
765kV Project (Estimated)
Thank You!