DTP 2.1 is behind the targets and a significant revision is necessary. All
concerns as advised to TGDC through a letter need to address including
resource mobilization plan particularly for major structures that is more
DTP2.1 has been revised in
than critical for the project to complete within the planned date. Dam
accordance with the requirements of
grouting issues and core wall construction should be taken in
the letter issued by the EE. The
consideration during the finalization of DTP 2.1.
detailed dam filling plan and
All concerns related to DTP 2.1 should be well replied during the month of
resource safeguard measures have
6 December 2019 and must be finalized as project is being critical and all
also been prepared. At present,
delays should be recovered with resources and production rates in the
after the email is sent to the plan
revised DTP.
engineer for communication and
DTP V2.1 becomes the first priority issue and need to be finalized within
consent, it will be submitted to the
this month. More effect and immediate action should be taken from TGDC.
EE for review by formal documents.
TGDC commented that everyone has concern about DTP 2.1 because
dam filling is very critical. They have to take risk for speeding up the
progress along with flood control measures and techniques.
Pile load test for Azad Pattan Bridge is still pending for which it
8 was informed that it may not be required. TGDC needs to check TGDC is currently studying this issue.
whether this is needed or not and issue must be closed.
01 02 03 04
02 05 06 07 08
Completed in December
Consolidation grouting
7 264 301 114%
8
Total
of spillway
Intake Tower concrete
Dam filling
7181m³ 5861m³ 82% Plan 23 blocks,Actual 26 blocks
9 Plan:201,000
Powerhouse concrete 10203m³ m314418m³ 141% Plan 32 blocks,Actual 38 blocks
10 Switch yard concrete 3335m³ 3031m³
3 91% Plan 15 blocks,Actual 11 blocks
Actual:242,000
Headrace tunnel lining
m
11 5694m³ 4446m³ 78% Plan 49 blocks,Actual 50 blocks
concrete
120% Yangtze Three Gorges Technology & Economy Development Co.,Ltd
2. Completed in December TGDC
Actual
Plan quantity Qualified by
No. Item quantity in Remarks
in November NDT
November
12 Penstock installation 15sections 10 sections 100%
13 Spiral case assembly 10sections 14 sections 100%
14 Spiral case installation 26sections 24 section 100%
Unit #1 :
Auxiliary powerhouse pouring
for downstream side was
completed to EL.415.97m.
Volute phase 1, 2 layers of
concrete pouring completed
Unit #2 :
Auxiliary powerhouse pouring
for upstream side was
completed to EL.411.47m.
January
Auxiliary powerhouse pouring
for downstream side was
completed to EL.398.47m.
Unit #3 :
Auxiliary powerhouse pouring
for upstream side was
completed to EL.401.47m.
Powerhouse
Upstream Downstream
Powerhouse
Switchyard
• Erection Bay II: Concrete was poured to EL.444.0m.
Powerhouse
Switchyard
Powerhouse
Switchyard
Intake Tower
#1 Intake Tower : Concrete was poured to
EL.467.75m.
Trash rack pier: Concrete was poured to
EL.467.6m.
#2 Intake Tower : Concrete was poured to
EL.463.7m.
Trash rack pier: Concrete was poured to
EL.465.7m.
Intake Tower
#3 Intake Tower : Concrete was poured to
EL.459.5m.
Trash rack pier: Concrete was poured to
EL.461.4m.
#4 Intake Tower : Concrete was poured to
EL.463.7m.
Trash rack pier: Concrete was poured to
EL.465.7m.
Unit #1 completion for welding by 100% Unit #2 completion for welding by 64%
Unit #3 completion for welding by 82% Unit #4 completion for welding by 78%
Yangtze Three Gorges Technology & Economy Development Co.,Ltd
2. Completed in December TGDC
Unit #1 completion for welding by 100% Unit #2 completion for welding by 94%
Spiral Case
Completed assembly of 14
spiral case sections of unit 3#,
qualified by NDT 100%.
Completed installation of 24
spiral case sections of unit 2#,
qualified by NDT 100%.
Construction pictures
Dam
Area Ⅰ upstream of the dam:filling to EL.420.4m
Area Ⅱ downstream of the dam:filling to EL.403m
Asphalt concrete:filling to EL.380.5m
Dam Upstream
Backfilling
Dam Downstream
Backfilling
Spillway
Excavation in December: 392,000m3 .
Support in December: 3620m2.
Excavation completed totally:7million m3,70.5%.
Reservoir Area
AZPT Bridge:
• 1# bridge pier:pouring to the 12th layer。
• 2# bridge pier:pouring to the 13th layer。
01 02 03 0403 05 06 07 08
Progress Analysis
V2.1 V2.1
S. No Item Actual progress
Earliest plan Latest plan
Planned
S. Key Milestone in Progress compared with
Completion Reason for delay
No Contract V2.1
Date
2020-10-31 /
1 Dam Capping No delay
Planned
S. Progress compared
Key Milestone in Contract completion Reason for delay
No with V2.1
date
01 02 03 04
04 05 06 07 08
Manpower
Totally 6,192 people worked in December, including 1,195 Chinese and 4,997 Pakistani.
6192
6000
5294 5246
5000
4000
3000
2000
1000
0
October November December
Equipment
579 sets of Equipment involved in December.
Equipment in last 3 months
700
600 579
503 492
500
400
300
200
100
0
October November December
01 02 03 04
05 05 06 07 08
HSE Management
01 02 03 04
06 05 06 07 08
Dam
Dam filling : 146,000 m3.
AreaⅠupstream of the dam filling to EL.420.6m.
AreaⅡupstream of the dam filling to EL.410m.
Backfill on both sides of the core wall:filling to EL.396.9m.
Spillway
Excavation:300,000m³ • Segment #6: 2 blocks, EL.457.3~462m.
Slope support:3,000m² • Segment #7: 1 block, EL.457.3~460m.
Concrete • Segment #8: 2 blocks, EL.454.3~460m.
• Segment #1: 0 block, EL.464m. • Segment #9: 2 blocks, EL.460~464m.
• Segment #2 0 block, EL.468m. • Segment #10: 1 block, EL.451.3~454.3m.
• Segment #3: 1 block, EL.450~452m. • Segment #11: 2 blocks, EL.452.5~458.5m.
• Segment #4: 1 block, EL.447~450m. • Segment #12: 1 block, EL.464~466m.
• Segment #5: 2 blocks, EL.457.3~462m. • Totally 15 blocks
Powerhouse
Switchyard at erection bay Ⅱ: Masonry EL.419m back wall
Switchyard at Unit #1: To complete 1 block, EL.428.0~430.97m.
Switchyard at Unit #2: To complete 1 block, EL.428.0~430.97m.
Switchyard at Unit #4: To complete 2 blocks, EL.414.0~419.0m.
Powerhouse
Item Plan for Upstream side concrete Plan for Downstream side concrete
Intake Tower
#1 intake Tower : To complete 1 block,
EL.467.75~469.5m.
Trash rack pier: To complete 2 blocks,
EL.467.7~469.5m.
#2 intake Tower : To complete 2 blocks,
EL.463.7~467.7m.
Trash rack pier: To complete 1 block,
EL.465.7~467.6m.
Intake Tower
#3 intake Tower : To complete 2 blocks,
EL.459.5~463.7m.
Trash rack pier: To complete 2 blocks,
EL.461.4~465.7m.
#4 intake Tower : To complete 2 blocks,
EL.463.7~467.7m.
Trash rack pier: To complete 1 block,
EL.465.7~467.6m.
Reservoir area
Azad Patten Bridge
• 1# Bridge Pier: 0 # block first layer of concrete pouring .
• 2# Bridge Pier: 0 # block the first layer of concrete pouring.
• 0# abutment:Concrete pouring on the first warehouse of the abutment.
• 3# abutment: Concrete placement for the first warehouse of the abutment.
Pedestrian bridge
• 1# Bridge Pier:Pile foundation construction,2# Bridge Pier:Pile foundation construction.
• S1# road excavation.
• S2# road excavation.
• S3# road excavation.
• S6# road excavation.
Yangtze Three Gorges Technology & Economy Development Co.,Ltd
• S7# road excavation.
Report Outline TGDC
01 02 03 04
07 05 06 07 08
Highlight Issues
团结 更好
诚信