“Fix Tube Sheet” Heat Exchanger

General Assembly view

Gasket

Tube side Inlet Shell side Outlet


Gasket
Shell Tube Sheet

End Flange
Cover

Distributor

Saddle
Gasket

Tube side Outlet Shell side Inlet

Tube Sheet

1
“Fix Tube Sheet” Heat Exchanger
Cross Sectional View Assembly
Tube Sheet
Baffle Shell
Tube Cover

Tube sheet
Distributor

2
“Fix Tube Sheet” Heat Exchanger
Split view sectioned parts

Distributor Gasket Gasket


Shell-Tube sheet-Tubes
Cover

Gasket

End Flange

3
“Fix Tube Sheet” Heat Exchanger
Split View of Parts

Gasket Gasket
Shell Tube Sheet
Cover

Saddle
End Flange
Gasket
Distributor Tube Sheet

4
Do Not Start The Job Without a Safety Plan

5
“Fix Tube Sheet” Heat Exchanger
Maintenance Activity Description
Blind Inlets-Outlets at Install Blinds in-Out of
plant area shell
Disconnect and remove
Distributor with gasket
Remove Cover with gasket

Ground level
6
“Fix Tube Sheet” Heat Exchanger
Shell Hydro-test
Install pressure gauge Eliminate leaks if found
Connect water pump Drain water from shell
Fill the shell by water Remove PG & Water pump
Raise the pressure at value
Remove blinds, fix gaskets
indicated by Inspection
& tight bolts

PG

Drain

Ground level Water Pump

7
“Fix tube sheet” Heat Exchanger
 Shell Side Hydro-test …Leak elimination from tubes [Details]
Tube sheet Blind Tube sheet
PG

Shell

Leak elimination
by Plugs
Water

Plug
Leak

Plug
Tube

PG

Leak elimination
by Expansion
Leak Water

Expander
8
“Fix tube sheet” Heat Exchanger
 Tube Side Hydro-test [Details]
Install distributor with new Fill Water tube side
gasket
Raise the pressure up to the
Install blinds at inlet-outlet value indicated by Inspection
Check sealing distributor to shell
Install Pressure gauge &
water pump Check sealing distributor to end flange
Install cover with gasket Check sealing cover to Shell
Discharge water remove PG & pump

PG Remove blinds at distributor in-out

Water Pump Ground level


9
“Fix Tube Sheet” Heat Exchanger
Handover & Final House Keeping By Maintenance
 Remove tools and equipment  Close Work permit
 Clean and wash the area  Remove scaffold after unit start-up

Ground level
10