Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Chute Penetration
North
- Typical level detail
• Penetration to be created from L01 
L06
• Penetration to be bound by concrete
encased steel beams (North and West),
and concrete ribs (South and East)
• Ribs compromised by creation of
penetration to be supported with a
combination of a prop-and-beam
system, and the scaffold walls
themselves
– Scaffold standard = 5 kN EW = 1.870 m
• Prop-and-Beam system to consist of:
– 200UB to be installed every
second level (i.e. L01, L03, L05) NS = 2.310 m
– Beam to be installed NS across
structural beams
– 70 kN @ 3000 mm Alshor prop to
be installed from top of Beam to
the soffit of the slab above
• Prop-and-Beam system to be installed
tight to the eastern face of the eastern
scaffold bay
• For the levels without beams (i.e. L02,
L04), props to be based off timber
spreaders to distribute load and
maintain vertical continuity through
misaligned ribs.
= Slab Ribs = Scaffold = Prop (70 kN) = 200UB = Load pathway

Delta Group Demolition Plan "Commercial in Confidence" 1


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Ground details Existing masonry wall
North
• Western face of Chute on Ground floor
be left open. Crash barriers and scaffold
to be installed west of chute opening to
East
protect against ejected material.
• Area surrounding chute base to be
enclosed in Geofabric and ATF Fencing
to suppress dust.

4.66 m

Ground

Structural Column
Section A

Section A

= Steel Plate = Scaffold = Tyres = Personnel and Dust screen = Ply and LVL

Delta Group Demolition Plan "Commercial in Confidence" 2


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Ground details
North
• Scaffold installed on Ground floor to be
positioned around the perimeter of the
Chute bay to create a widened base.
• Propping of the compromised L01 ribs to
be provided by the eastern bay of
scaffold
– Single scaffold standard = 5 kN
– Scaffold standards to support L01
slab ribs, transferring load
through to LG reinforcement.
• Chute base to consist of a layer of tyres,
covered by steel plate. Ground
– Tyres to dampen dynamic loading
– Steel plate to distribute load over Existing masonry wall
chute base area
• A rubble pad (fines and small dimension
concrete) to be installed over the steel
plate to dampen dynamic (impact)
loading
– Impact force, and the associated
vibration transfer, is inversely
proportionate to stopping
distance. Therefore, as falling
rubble impacts and displaces the
pad, force and thus vibration are Structural Column
dissipated.
• Shunt barrier to be employed at the
eastern extent of the chute base,
allowing materials to be gathered by a
Bobcat. = Steel Plate = Scaffold = Rubble pad = 200UB = Shunt barrier = Ladder Beam

Delta Group Demolition Plan "Commercial in Confidence" 3


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Slab loading capacity
TS-SH-10-00-01[1] extract
North
• The bay in which the chute is to be
established is limited to 4.6 kPa Live
Load and 7.0 kN Point Load.
• Unaffected ribs surrounding the chute
penetration will maintain the LL and
Point Load capacity. Ribs that are to be
partially removed are to be supported
through the application of a beam-and-
prop system throughout the building,
and the load bearing capacity of the
scaffold used to define the chute itself.
• Material stockpiling within the chute
base and Ground floor storage area to
utilise the Live Load capacity of two (2)
levels simultaneously. i.e. 4.6 kPa x 2 =
9.2 kPa (?)

Typical Level

= Chute area

Delta Group Demolition Plan "Commercial in Confidence" 4


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Ground details
North
- Stockpile area
• Ground floor area adjacent Eastern Fire
Stair to be reinforced to allow for
stockpiling of dumped material
• Area to be propped from Lower Ground
(LG) to Ground (G)
– A-Frames installed in NS series,
perpendicular to the span of the
7.07 m
slabs
– Single A-Frame leg = 45 kN
– A-Frames to be installed mid span
– Headers and Bearers to be utilised Ground
to distribute load
– A-Frame dimensions
• Length = 1.6 m L01 East
• Width = 1.3 m
• Available stockpiling height, with 7.03 m 0.8 m
uniform distribution = 0.8 m (?) G

= Rubble LG

= Header/Bearer

= Rib/slab
B
= A-Frame Section B
Section B
= Reinforced area 5.74 m

Delta Group Demolition Plan "Commercial in Confidence" 5


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Structural Column
- Chute Base
North
- Reinforcing
• Beams defining the Lower Ground slab
around the chute base

Lower Ground
15” x 6” @ 45 lb/ft – 4.25 m
2.93 m
16” x 6” @ 50 lb/ft – 3.30 m

18” x 8” @ 80 lb/ft*** – 6.52 m

18” x 6” @ 55 lb/ft – 3.97 m

Vantage A

*** = additional reinforcing, see next slide

Delta Group Demolition Plan "Commercial in Confidence" 6


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Chute Base
- Reinforcing
• Properties of the beams defining the
Lower Ground slab around the chute base.
• Note the additional reinforcing applied to
the western NS beam during construction.
Assumed Pls = plates, i.e. additional plate
steel installed along the flange of the
beam.

*** =

Delta Group Demolition Plan "Commercial in Confidence" 7


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Vantage A
- Chute Base
L01 East
- Reinforcing
• Retention/reinforcement of the LG
Beam-to-Beam connections required to
distribute load on grillage back to
structural elements.
Structural Column

Chute Base
G

Structural Beam
LG

= 200 UB = Prop (45 kN) = Beam-to-Beam retention = Load pathway

Delta Group Demolition Plan "Commercial in Confidence" 8


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Structural Column
- Chute Base
North
- Reinforcing
• Chute base to be supported from Lower
Ground Slab C45
• Grillage installed on Lower Ground slab,
transferring mass and loading back to
structural elements of the building (Beams
and Columns)
• The configurations of the Lower Ground
slab in this area contains two (2) beam-to-
beam connections which require
additional reinforcing to maintain
structural integrity.
• LG western Beam-to-Beam connection to
be hung from G (?), creating a rigid load C17
distribution system over the LG and G NS
beams (C44-to-C45) Lower Ground
• LG eastern Beam-to-Beam connection to
be supported by the B-to-LG brick pier that
exists on the southern face of C17
– Void present below soffit of Beam-
to-Beam connection to be Grout
packed (shrinkless – 40 MPa) to
establish load transfer
C44 Structural Beam

Vantage A

= 200 UB = Prop (45 kN) = Hung junction = Pier supported

Delta Group Demolition Plan "Commercial in Confidence" 9


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Chute Base
North
- Reinforcing
• 300 PFC installed above Ground slab, and
below Lower Ground soffit
• Holes to be drilled through web of PFC to
accommodate M20 thread
• Ground (G) and Lower Ground (G) slabs
surrounding beam-to-beam junction to be
hammered to allow for installation of All
Thread hangers through to soffit of Lower
300 PFC
Ground slab

M20 All Thread

Vantage A

Delta Group Demolition Plan "Commercial in Confidence" 10


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Vantage A
- Chute Base
L01 East
- Reinforcing
• Two (2) lengths of M20 All Thread to be
passed through PFCs.
• M20 All Thread to be fastened, applying
compressive loading to the Beam-to- 300 PFC
Beam connections.
• (Question) Two (2) x PFC, or four (4) x
PFC?
• (Question) How will this support the G
additional loading applied to Ground
during dumping, and how will this
support the load transferred to the
junction by the grillage? M20 All Thread

LG

= Load pathway

Delta Group Demolition Plan "Commercial in Confidence" 11


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Vantage A
- Chute Base
L01 East
- Reinforcing
• Two (2) lengths of M20 All Thread to be
passed through PFCs.
• The double PFC configuration applying
compressive loading to the Beam-to- 300 PFC
Beam connections, while simultaneously
adding stiffness to the G-LG coupling.
– G-LG stiffness dependent upon
the buckling capacity of the M20 G
thread over 3000 mm
• (Question) Two (2) x PFC, or four (4) x
PFC configuration?
• (Question) Will stiffening with the M20 All Thread
buckling capacity of the M20 be enough
to share loads over both beams
simultaneously?
LG

= Load pathway

Delta Group Demolition Plan "Commercial in Confidence" 12


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Transfer Deck
North
• Transfer Deck establishes a connection
between Shell House and the Super Shell House Super Deck
Deck, allowing material to be loaded out
after dumping via the chute.

Carrington Street

= Transfer Deck = Void = Load Out pathway = Reinforced area = Chute Bay

Delta Group Demolition Plan "Commercial in Confidence" 13


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Not to scale
- Transfer Deck
North
- Shell House Location
• The location of the Transfer Deck,
relative to the G and LG features and
infrastructure,:
– Eastern face Ezy Mart C2 (SD SC
offset) = 2.734 m
– Eastern face Ezy Mart B3 (SD
offset) = 2.734 m SC offset = 2.43 m C11
– Western extent of southern
scaffold opening (SD offset) =
3.000 m
– Southern scaffold opening = 3.255 Grid Spacing = 8.82 m
m
– Eastern extent of southern
scaffold opening (SC offset) =
2.430 m
– Western face of C11 (SC offset) =
2.140 m SD offset = 3.00 m
• Transfer Deck located within the
SD
southern scaffold opening.

= Scaffold opening

= Transfer Deck = Ezy Mart Stair = Span = Ezy Mart Beam = Transfer Deck

Delta Group Demolition Plan "Commercial in Confidence" 14


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Not to scale North
- Transfer Deck
- Shell House tie 14” x 5.5” @ 40 lb/ft – 2.73 m
• The Transfer Deck will bear onto Shell
House – Ground Floor – South Western 18” x 6” @ 55 lb/ft – 7.12 m
bays.
• The introduction of the Ezy Mart stairs
(1970) reduced the EW span of the ribs,
extending from the NS Internal beam to
the face of B3.
– Span = 3.6 – 3.9 m
• Mass of Transfer Deck loads
perpendicular to span of Edge Beam and
Slab Ribs C1 B3 C2
• The majority of the mass is transferred
to the southern face Edge Beam
– 18” x 8” @ 55 lb/ft – 7.12 m B1 B2
• Mass of one (1) Bobcat + Transfer Deck =
2.8 T + 3.2 T = 6.0 T

Shell House Super Deck

= Prop

= Ezy Mart Concrete Columns = Ezy Mart Stair = Span = Ezy Mart Beam = Transfer Deck

Delta Group Demolition Plan "Commercial in Confidence" 15


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Not to scale C11
- Transfer Deck SP01
0.681 m North
- Shell House tie North
78.60 kN
Note: SC = SC gridline, SD = SD gridline
1.874 m
• (G) (B) Western face of C11 (SC offset) = SP02
2.140 m
78.60 kN
• (G) Eastern extent of southern scaffold
opening (SC offset) = 2.430 m C11

2.760 m
(G) Eastern face of Transfer Deck (SC SP03
offset) = 2.625 m
74.50 kN
• (B) Eastern face of SP01 (SC offset) = 2.821
m
• (B) Western face of SP01 (SC offset) =
2.991 m
• (B) Eastern Face of SP02 (SC offset) = North
C2
74.50 kN

78.60 kN

78.60 kN
C1 B3
4.865 m
• (B) Western Face of SP02 (SC offset) =
5.035 m
B1 B2
• (B) Eastern extent of Access (SC offset) =
5.035 m Scaffold
• (G) Western face of Transfer Deck (SC Needle Props
SP03 SP02 SP01
Access

offset) = 5.625 m
• (G) Western extent of southern scaffold
C11
opening (SC offset) = 5.685 m
• (B) Western extent of Access (SC offset) =
6.007
• (B) Eastern face of SP03 (SC offset) = 7.795 = Prop
m
= Ezy Mart Concrete Columns = Ezy Mart Stair = Span = Ezy Mart Beam = Transfer Deck

Delta Group Demolition Plan "Commercial in Confidence" 16


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN Not to scale C11
- Transfer Deck SP01
0.681 m North
- Shell House tie North
78.60 kN
• (G) Eastern face of Transfer Deck (SC
offset) = 2.625 m
1.874 m
– Prop – G  LG  B SP02
• (G) Western face of Transfer Deck (SC
78.60 kN
offset) = 5.625 m
• (B) Western extent of Access (SC offset) = C11
6.007 2.760 m
SP03
– Prop – G  LG  B
74.50 kN
• Transfer Deck propping
– Eastern prop clear to basement
– Western prop obstructs access,
North
therefore C2
74.50 kN

78.60 kN

78.60 kN
C1 B3
• Prop to be positioned to the
south of Ezy C2, transferring
load to southern edge beam
B1 B2
• Prop offset to vertical
continuity of load = 0.322 m Scaffold
• Prop specs SP03 SP02 SP01 Needle Props
Access

– Load Bearing capacity = 150 kN @


3000 mm C11
• System 15 prop
– Quantity = 4
– Certification of competency for = Prop
Basement southern Edge Beam to
accommodate additional point
loading, above the present scaffold = Ezy Mart Concrete Columns = Ezy Mart Stair = Span = Ezy Mart Beam = Transfer Deck
needle load

Delta Group Demolition Plan "Commercial in Confidence" 17


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Transfer Deck
• Engineering drawings for Transfer Deck
fabrication.

Delta Group Demolition Plan "Commercial in Confidence" 18


Project: [Wynyard Place]

Work Methodology Job No: [N6315]


Date – Revision: [02/05/18 Rev 09]

Developed By: David Mullane Revised By: Approved By: Method Ref: [SH-CHUTE-01]

Description Diagram
EN
- Transfer Deck Section C
- Lifting and Installation
• Chain length > 7.221 m to achieve lifting
geometry
• Transfer Deck mass = 5.7 T (1.5x safety 2121 mm
factor), apply appropriate reeve factor to Section C Sling configuration to be mirrored
accommodate. in the opposite direction

1500 mm
45 deg. Hook
300 mm 300 mm

3000 mm

= Lifting Slings/Chains = Load pathway

Delta Group Demolition Plan "Commercial in Confidence" 19