Académique Documents
Professionnel Documents
Culture Documents
where:
Qf = skin/shaft friction or side shear
Qb = end bearing or point resistance
• Alpha (α) Method
The
*Qf = αcuPL
*Qb = Nc(cu)bAb
*cu = qu/2 or su/2
(2/3)L
At
Am
Ab
Problem 6.4
Three columns x four rows of group piles are installed into a uniform clay layer.
The groundwater table is at the ground surface.
Clay soil:ɣsat = 21kN/m3,cu = 40kPa, Nc = 7.5
cc =0.36, eo = 0.85
Piles: diameter = 0.3m, pile to pile spacing = 0.75m,
length = 50m
a. Determine the ultimate capacity of the pile using single pile capacity if α =
0.74.
b. Determine the ultimate capacity of the pile using group pile capacity if α =
0.74.
c. If the total thickness of the clay layer is 60m, determine the vertical stress
increase using Simpson’s Rule if FS = 3.5.
d. Determine the primary consolidation settlement.
Applied Load (Qa)
Pile Cap
(2/3)L
L
At
Plan View
Am
Ab
Side View
Applied Load (Qa)
Pile Cap
(2/3)L Sand
L
Po
At
Clay Plan View
Am
Ab
Side View
Problem 6.5
The foundation shown in the figure is supported by 9 piles. The
foundation rests on a sand layer underlain with 3m thick of normally
consolidated clay.
a. Compute the effective stress at the midheight of the clay layer.
b. Determine the increase in pressure at the mid-height of the clay layer.
c. Determine the consolidation settlement of the clay layer.
2400kN
Pile Cap
4m
el.0
Dry Sand 3m
(2/3)L Ɣd = 17.8kN/m3
L = 6m el.3 Sand
Ɣb = 10.2kN/m3 Po
el.5 At Clay
e = 0.54, Cc = 0.3
Ɣb = 9.3kN/m3 Plan View
Am
el.8
Ab
Side View
Braced Cuts/Excavations
- Excavations which are laterally supported
Cuts In Sand
Cuts In Clay
Cuts In Clay with Different Properties
Cuts In Stratified Soil
Problem
A long trench is excavated in medium dense sand for the foundation of a
multistory building. The sides of the trench are supported with sheet pile
walls fixed in place by struts and wales as shown in figure the wales are
braced at every 4m center to center.
a. Determine the strut load at A.
b. Determine the strut load at B.
c. Determine the strut load at C.
Problem
A four-strut braced sheet pile installation is designed for an open cut in a
multistory layered stratum as illustrated in the figure . Spacing of struts
is 4m center to center.
a. Determine the strut load at A, B, C and D.
Slope Stability
-the potential of soil covered slopes to withstand and undergo movement.