Académique Documents
Professionnel Documents
Culture Documents
What is a Project ?
Unique in nature
Have a defined timescale
Have limited resources
Involve an element of risk
Àtages of a Project
Project Management
|
Cost / Time overrun of
Infrastructure Projects
6
w |ut of 905 projects monitored, 454 projects are
contributed time over run w.r.t original schedule
which is >50%, and the time over run range
from 1-324 months.
w The original cost of 454 projects is `311828.16
and with time over run the cost increased to
`356971.98 which is `45143.82Cr of original
cost.
The original cost of 905 projects is
`546772.49Cr and now the anticipated cost is
`614036.91Cr with an cost over run of 12.30%
w.r.to original cost.
6acts:
The Time |ver run in Coal is 1-324 months
The time over run in Railways 8-180 Months
The slippage in Power sector is 1-68 months.
The Cost |ver run in Railways 82.33%
The Cost |ver run in Power sector is 3.86%
Infrastructure Projects ± Causes for
Delay
À 6 À
À
1 Coal 1 12 1 2 2 2 13
2 Àteel 0 0 0 1 0 0 7
3 Petroleum 0 0 0 6 2 0 7
5 Railways 28 12 1 63 1 5 8
Road
Transport
6 0 0 0 0 0 0 4
&
highways
Àhipping &
7 0 0 0 0 0 0 2
ports
8 Heath& 0 0 0 0 0 0 1
6W
Major risks of Projects
Cost |verrun/Escalation :
Time overruns of projects
wPaucity of 6inancial resources,
wDelay in obtaining clearances,
wDelay in acquisition of land,
wPoor performance of
Consultants, Vendors and
Contractors
wDispute and court cases,
wInadequate infrastructure
support, in adequate
technology
wResistance by land losers
wPoor law and order situation0
Cost overruns of projects
Delay in execution of the projects:
{
ü
0
!"0
#$
!%& '()
* + *
0
î
î î
î
Bulk tendering
Motivate the suppliers
Views and feedbacks of long term suppliers
and associates.
Qualification requirements ( QR) & number of
prospective bidders .
!
wa
À
wÀ
w
À
w
Logistics Management
wThe site selection for the Project is not in
the control of Project |wner, Project owner
has to build the stakeholder confidence to
implement project in any green-field location.
º
Proposed Association with Logistics Provider
-
º
Role of 3PL Provider
PRE-PLANNING AÀPECT
ÀA6ET MATTERÀ
TIME AND M|TI|N PLAN
ENGINEERING ÀTUDIEÀ
Project Communication Management
#
{ {{ ÀÀ
î
î
î
½ #
6 aÀ 6aÀ
À {
½ #
6IELDBUÀ/ PR|6IBUÀ TECHN|L|G
The usage of instrument cable, marshalling panels,
cable trays are reduced.
Commissioning activities like wiring checks are also
reduced.
It will save installation cost of the |verall Àystem
Both time and Cost of the Project is get reduced.
This technology is a reality in more than 100 power
plants.
Àichuan Guang'an Power Plant in China , using
Profibus fieldbus protocol to follow the L2-DP network
technology.
* *
* *
0
½ #
Àteel Moment Resisting Àpace 6rame (ÀMRÀ6)
23 4
4
*
5
4 ^! ^!" !#^ $ !$! ^
%^!$&
23 6 / 7 *
*
0
' ^! ^!"
!#^ $ !$! ^ %^!$&
^
( )
)
* ^#
)
*
+,$- *( .+
{ a